Prepare to Realize: Mobilizing and Validating the Project
This chapter assumes you understand ERP business processes, project phases, and the difference between SAP S/4HANA and SAP ECC. It focuses on how SAP Activate moves a project from mobilization into business validation and iterative delivery.
Prepare: Mobilizing the Project
The Prepare phase turns an approved idea into an organized project. The project team confirms scope, governance, responsibilities, environments, and the delivery plan.
Typical deliverables include:
- A project charter and confirmed scope
- A project organization, including business process owners and implementation partners
- A communication and meeting plan
- Initial risks, dependencies, and mitigation actions
- System access, project tools, and development environments
- A detailed plan for Explore workshops
The team also confirms how decisions will be made. For example, a steering committee may approve scope changes, while process owners approve business-process decisions.
Explore: Validating the Solution with the Business
In the Explore phase, the team validates SAP’s standard processes against business needs. The main technique is the Fit-to-Standard workshop.
Business representatives review a standard process, such as procure to pay or order to cash. They compare the process with current operations and decide whether the standard process is acceptable.
The goal is to adopt standard functionality wherever possible. This reduces custom development, simplifies upgrades, and supports a cleaner system core.
Fit-to-Standard Results
Each workshop records process decisions, requirements, integrations, data needs, and open questions. A fit-gap result classifies a business need:
| Result | Typical action |
|---|---|
| Fit | Use the standard process and configure permitted settings |
| Gap | Change the business process, configure another option, or approve an extension |
A gap is not automatically a reason to customize. The team should assess business value, compliance, cost, risk, and future upgrade impact before approving a deviation.
Realize: Iterative Delivery
In the Realize phase, the team converts approved decisions into a working solution. Configuration, integrations, extensions, data preparation, and testing proceed in short iterations.
Each iteration should produce measurable evidence, such as a tested process or resolved defect. Frequent validation exposes incorrect assumptions before they spread across the solution.
Exercise
Why should a fit-gap be reviewed before custom development begins?
Show answer
The team may satisfy the requirement through a process change, standard configuration, or a lower-risk extension, avoiding unnecessary custom code.