Keeping the Core Standard in SAP Activate Projects
Assume you understand ERP processes, project phases, and the difference between SAP S/4HANA and SAP ECC. This chapter focuses on decisions after Fit-to-Standard analysis and through Run.
Keep the core standard
The clean core principle means keeping SAP-delivered software close to its standard form. Use in-app extensibility, which adds fields, logic, or applications inside SAP S/4HANA using supported tools, for small changes. Use side-by-side extensibility, which runs custom applications on SAP Business Technology Platform, when the solution needs separate scaling, integrations, or release cycles.
Avoid modifying SAP standard code. Custom modifications increase upgrade effort and can create defects during maintenance.
Deploy: cutover and go-live
In Deploy, the team prepares the production system and moves the approved solution into use. Key activities include:
- Completing integration, security, and user-acceptance testing.
- Loading and reconciling migrated data.
- Training users and publishing support instructions.
- Rehearsing the cutover sequence.
- Freezing changes, executing cutover, and confirming business readiness.
A cutover plan assigns each task an owner, dependency, start time, and verification step.
Run: stabilize and improve
Run begins with hypercare, the period of intensive support immediately after go-live. The team monitors transactions, interfaces, jobs, and user issues. It prioritizes incidents, restores normal operations, and transfers knowledge to the support organization.
After hypercare, operations continue through monitoring, incident management, problem management, and planned improvements. New requests should follow change control rather than entering production informally.
Quality gates and exit criteria
A quality gate is a formal review that checks whether a phase is ready to end. Typical evidence includes tested deliverables, accepted risks, approved decisions, and a plan for the next phase.
| Gate | Example evidence |
|---|---|
| Explore to Realize | Signed fit-gap decisions and an approved backlog |
| Realize to Deploy | Accepted tests, trained users, and a rehearsed cutover |
| Deploy to Run | Go-live approval and an active support model |
Tools and roadmap selection
The SAP Activate roadmap viewer provides phase activities, deliverables, and accelerators. SAP Cloud ALM supports cloud implementation tracking, testing, and operations. SAP Solution Manager supports established on-premises landscapes and traditional implementation management.
Select a roadmap by deployment model, implementation scenario, scope, and team responsibilities. Tailor it by adding required workstreams and removing irrelevant tasks. Keep mandatory quality checks, dependencies, and deliverables visible.
Exercise
A requirement needs a separate user interface, independent deployment, and integration with several systems. Which extension approach is usually suitable?
Show answer
A side-by-side extension is usually suitable because it keeps custom code outside the S/4HANA core and allows independent deployment.