Sub topic 14
Change Management Process
This chapter assumes you know what a help desk ticket is and how asset records work. Both come up here because every change should trace back to a ticket and update an asset record. Change management is the process that controls how modifications to systems are requested, reviewed, approved, done, and documented. It reduces the risk that a well-meant fix causes an outage.
Why changes need a process
An unplanned change can break a system that was working. It can also leave no record of what was altered. A formal process makes sure that someone other than the technician has looked at the risk, and that a way back exists if the change fails. The A+ exam tests the steps in this process and the documents that support them.
The steps of a change
- Submit a request for change that states the reason for the change.
- Define the scope: which systems, users, and locations are affected.
- Analyze the risk, including what could go wrong and how badly.
- Write the plan, including the schedule and the person responsible.
- Write the backout plan, which is the procedure for restoring the earlier state.
- Get approval from the change advisory board (CAB) or other authority, before any work starts.
- Carry out the change, often in a scheduled change window, such as after hours.
- Test the result against the acceptance criteria.
- Update the documentation, including asset records and the knowledge base.
A worked example
The change request below uses the fields the exam expects. A battery charging fault on laptops is fixed by a vendor BIOS update, so the technician writes the request first.
Change request
Title: Update BIOS on accounting laptops
Reason: Vendor fix for a battery charging fault
Scope: 12 laptops, Accounting department
Risk: Low to medium; a failed update can leave a device unbootable
Plan: Update one pilot laptop, verify, then update the rest after hours
Backout plan: Keep the previous BIOS file and a recovery procedure ready
Approval: Change advisory board, before the work starts
Acceptance: Pilot user confirms the laptop charges and boots normally
Documentation: Update asset records and the knowledge base after completionNotice three details. The scope is limited to 12 laptops. The plan starts with one pilot device, which limits the damage if the update fails. The acceptance criteria say how everyone will know the change worked.
Common errors
- Starting work before approval. Approval must come first, even for a change that looks small.
- Writing no backout plan, or writing one that was never checked. A backout plan you cannot run is not a plan.
- Vague acceptance criteria such as "it works." Name an observable result.
- Skipping documentation. If asset records and the knowledge base are not updated, the next technician sees outdated information.
- Treating an emergency as an excuse to skip the process. Emergency changes usually follow a shorter approval path, but they are still recorded.
Exercise
A technician plans to update firmware on 40 workstations. The request has a reason, a scope, and a schedule. Which two items are missing before it can be approved, and why does each matter?
Show answer
A backout plan and acceptance criteria (a risk analysis is also needed). The backout plan lets the team restore the old firmware if the update fails. The acceptance criteria define how the team will confirm the change worked. A risk analysis tells the approvers how much damage a failure could cause. Approval must be obtained before the work starts.
Exercise
A pilot update fails and the laptop will not boot. What should the technician do next, and what happens to the rest of the rollout?
Show answer
Run the backout plan to restore the earlier BIOS and recover the pilot laptop. Stop the rollout to the other laptops, document what happened, and revise the plan before asking for approval again.