Running a First Kaizen Event: Measuring the Current State
This chapter assumes you know basic waste concepts, can read a simple flowchart, and are comfortable with time and count arithmetic.
Measuring the current state
Record how the process performs today before you change anything. Use these measures:
- Lead time: elapsed time from start to finish, including waiting.
- Cycle time: time between completed units at one step.
- Takt time: available work time divided by customer demand.
- Process cycle efficiency (PCE): value-added time divided by lead time.
available_minutes_per_day = 450 # 480-minute shift minus 30 minutes of breaks
daily_demand_units = 90
takt_minutes = available_minutes_per_day / daily_demand_units
print(f"Takt time: {takt_minutes:.1f} minutes per unit")
value_added_minutes = 12
lead_time_minutes = 240
pce = value_added_minutes / lead_time_minutes
print(f"Process cycle efficiency: {pce:.0%}")The script prints a takt time of 5.0 minutes per unit and a PCE of 5%, so most lead time is waiting.
Preparing before the event week
Confirm the sponsor, book a room, and tell the affected staff when observation will happen. Collect the baseline data in advance so the team starts with facts.
> Tip: Record at least five days of lead times. One day rarely shows the normal pattern.
Replace the block quote above with a callout in your own materials. Plain-text tips work fine in internal notes.
Running the event week day by day
| Day | Focus |
|---|---|
| Monday | Observe the current state and build the process map |
| Tuesday | Analyze root causes |
| Wednesday | Design and test countermeasures |
| Thursday | Standardize the best method and prepare the report-out |
Finding root causes with 5 Whys and a fishbone
5 Whys
Ask "why" until you reach a cause you can change. For example, orders wait because data entry is manual, which happens because the system cannot import orders, which happens because no one owns the import script.
Designing countermeasures
Each countermeasure should target one root cause. Test it in a small trial, and keep it only if the measured lead time falls.
Exercise
Exercise
A process has 240 minutes of lead time, of which 12 minutes are value-added. What is the PCE, and what does a low value suggest?
Show answer
PCE is 12 / 240 = 5%. A low value suggests that most of the time is waiting or handoffs, so waste reduction is the first target.