Sub topic 5
Remoteness: which losses the defendant must pay for
This chapter assumes you know the expectation measure of damages from the previous chapters. That measure puts the claimant where performance would have left them. It also assumes you know that a breach has already been established. Remoteness asks a narrower question: how far down the chain of consequences does the defendant's liability run?
Why a limit is needed
A breach can set off a long chain of events. A late delivery can close a factory, which can lose a customer, which can sink a business. If the defendant had to pay for every loss that the breach caused, the cost of making any contract would be unpredictable. Remoteness is the rule that cuts off liability for losses that were too unlikely or too unexpected at the time the parties made the contract.
Remoteness is a separate test from factual causation. A loss can be caused by the breach and still be too remote. A loss can also be foreseeable and still not be recoverable, because the claimant should have mitigated it.
The rule in Hadley v Baxendale
In Hadley v Baxendale (1854), a mill's crankshaft broke. The mill owners sent it to an engineer by carrier, and the carrier delivered it late. The mill stayed closed longer than necessary, and the owners claimed their lost profits. The court refused the claim. The carrier had not been told that the mill had no spare shaft and would stop work until the repair came back.
The court set out two limbs. Recoverable loss is loss that:
- arises naturally from the breach, in the usual course of things (the first limb); or
- was in the reasonable contemplation of both parties at the time they made the contract, as the probable result of a breach (the second limb). The second limb usually depends on special facts the defendant knew about.
The first limb works on ordinary knowledge. Everyone is taken to know what usually follows from a given breach. The second limb works on actual knowledge. If the claimant told the defendant about unusual circumstances, the defendant is liable for losses flowing from them. If the claimant did not, the defendant is liable only for the ordinary losses.
How likely must the loss be?
Later cases settled how probable the loss needs to be. In Victoria Laundry v Newman Industries (1949), a boiler was delivered months late. The laundry could recover the ordinary profits it lost through the delay. It could not recover the profits from unusually lucrative dyeing contracts, because the supplier had not been told about them.
In The Heron II (1969), sugar arrived late in Basra and the market price fell. The House of Lords held the loss recoverable. The test is whether the loss was "not unlikely" to result, or a serious possibility or real danger. This is a lower threshold than "more likely than not". It is a higher threshold than "conceivable".
Tort uses a looser test, simple foreseeability. Contract is stricter because the parties chose their own risks and could have bargained over them.
Type of loss, not exact extent
The defendant need only have contemplated the type or kind of loss. The exact size does not have to be foreseen. In Parsons v Uttley Ingham (1978), a farmer bought a defective hopper for pig feed. The feed went mouldy and the pigs died of illness. The court allowed the claim for the dead pigs. Illness in the pigs was a foreseeable type of loss, even though death on that scale was not.
The "type" label can be hard to apply. Courts disagree at the margins about whether a given loss is a different type or just a bigger version of a foreseeable one.
Assumption of responsibility
Transfield Shipping v Mercator Shipping (The Achilleas) (2008) added a complication. A charterer returned a ship about nine days late. The owner had agreed a new, better-paid charter, which fell through because of the delay. The market had risen sharply, so the owner's loss on the follow-on deal was large. The usual measure for late redelivery is the difference between the market rate and the contract rate for the overrun period. The House of Lords held that the charterer was liable only for that smaller sum. The larger loss was foreseeable in a loose sense. Even so, the majority held that the charterer had not assumed responsibility for it.
The case has been read narrowly since. The Court of Appeal has treated assumption of responsibility as a gloss that applies in unusual cases, mainly where market practice or the contract's allocation of risk points the other way. In the ordinary case, the Hadley test still governs. Treat the point as unsettled and check current authority.
Other jurisdictions
US law reaches a similar result. Restatement (Second) of Contracts §351 limits damages to losses the defendant had reason to foresee as a probable result of breach when the contract was made. The Uniform Commercial Code §2-715 allows consequential damages for losses a seller had reason to know of at contracting. The UCC applies to sales of goods.
A decision path
A worked example
A bakery contracts with a mechanic to repair its oven by Monday. The mechanic does not turn up until Thursday. The bakery tells no one that it has a large wedding order due Wednesday. It loses three days of normal sales and also loses the wedding order.
- The three days of normal sales arise naturally from a delayed oven repair. They are recoverable under the first limb.
- The wedding order is a special loss. If the bakery never told the mechanic, it falls under the second limb and fails for lack of knowledge.
- If the bakery had said "we need the oven by Monday for a wedding order", the mechanic knew the special facts. The wedding profit would then be recoverable, provided the loss was not unlikely.
Note that the bakery must still mitigate. If it could have borrowed an oven cheaply to fill the wedding order, the avoidable loss is not recoverable.
Common errors
- Mixing up the time frames. Foreseeability is tested at contracting, not at breach.
- Treating remoteness as causation. Show the loss was caused first, then test whether it is too remote.
- Using the tort test. Reasonable foreseeability is not enough. Ask whether the loss was not unlikely.
- Assuming silence is harmless. A claimant who wants protection for unusual losses should tell the other party about them before contracting.
- Overlooking contract terms. An exclusion clause or a cap on liability can override the default remoteness rules.
Exercises
Exercise
A tailor agrees to deliver a wedding dress two days before the ceremony and delivers it a week late. The tailor was told it was for a wedding. The bride cancels the wedding venue booking, which is non-refundable. Is the lost deposit recoverable, and under which limb?
Show answer
Probably yes, under the second limb. The tailor knew it was for a wedding, which is a special fact. A lost dress could make a non-refundable venue cost wasted, so the loss was not unlikely to follow from a missed deadline. The claim would still need to pass mitigation, such as hiring a replacement dress.
Exercise
A supplier is late with a part. The buyer loses a very profitable contract with a third party, but never told the supplier that the part was needed for that contract. Explain why the claim for the lost contract fails, and what the buyer can still recover.
Show answer
The lost contract falls under the second limb, which needs the defendant to know the special facts when the contract was made. Without that knowledge it was not in the parties' contemplation, so it is too remote. The buyer can still recover ordinary losses that arise naturally from a late part, such as the normal profit lost from the delay.