Sub topic 6
Mitigation: the claimant's duty to limit loss
This chapter assumes you know the expectation measure of damages and the remoteness rule from the earlier chapters. It also assumes you can tell a breach from a valid discharge. Here you learn what the claimant must do after a breach, what the claimant may recover for doing it, and where the rule stops.
What the rule says
A claimant cannot recover for loss that they could reasonably have avoided. This is usually called the duty to mitigate. The name is misleading. It is not a duty owed to the defendant, and breaching it gives the defendant no claim. It is a limit on the damages the claimant can recover.
The rule has three working parts:
- Avoidable loss is not recoverable. If the claimant could reasonably have avoided part of the loss and did not, that part is deducted.
- Costs of mitigation are recoverable. If the claimant spends money on reasonable attempts to limit loss, the defendant pays those costs, even if the attempt fails.
- Gains from mitigation are credited. If the claimant's steps avoid loss, the defendant gets the benefit of that.
The standard of conduct is reasonableness. The claimant is not held to a standard of perfection. The leading English statement is that a wronged party is not required to take unreasonable steps. A claimant who acts reasonably in a crisis the defendant created is not criticised because a cleverer course existed.
Why the rule exists
Expectation damages aim to put the claimant where performance would have left them. They do not aim to punish the defendant. Loss that the claimant could have prevented is, in a practical sense, caused by the claimant's own inaction. Remoteness asks what the defendant could foresee. Mitigation asks what the claimant did after the breach. The two rules work together to cap the award.
A worked example
A supplier agrees to sell a retailer 1,000 units at 10 each, delivery on 1 March. The retailer has agreed to resell them at 14 each. The supplier refuses to deliver.
The retailer finds identical units on the market on 2 March at 11 each. The expectation loss is 1 per unit, or 1,000.
Suppose the retailer ignores the market, waits until June, and buys at 13 each. The retailer cannot claim 3 per unit. The retailer could reasonably have bought at 11 in March, so damages are assessed as if that purchase had been made.
| Step | Per unit | Total for 1,000 units |
|---|---|---|
| Contract price | 10 | 10,000 |
| Reasonable replacement price in March | 11 | 11,000 |
| Recoverable difference | 1 | 1,000 |
| Actual June price (not recoverable beyond March figure) | 13 | 13,000 |
If the retailer also paid a broker 200 to find the replacement units, that 200 is recoverable as a cost of mitigation.
The same logic appears in sale of goods legislation. Under the usual rule, where there is an available market, the measure is the difference between the contract price and the market price at the time of breach. The market price is used because the claimant could have gone to the market.
The rule has limits
The claimant need not take unreasonable steps
Courts do not require a claimant to:
- risk their commercial reputation,
- start a lawsuit against a third party,
- spend large sums of their own money they cannot easily raise,
- accept a materially inferior substitute, or
- take steps that involve serious harm to other business relationships.
What is reasonable depends on the facts. The burden of proof sits with the defendant. The defendant must show that the claimant failed to mitigate and must show how much loss that failure caused. A claimant does not have to prove that they tried.
Accepting the defendant's own offer
Sometimes the best way to mitigate is to take a new offer from the party in breach. The claimant may be expected to do this when the offer is genuine, comes with no loss of dignity or rights, and the dealing is not unreasonable given the history. Courts have held that a claimant may be required to accept a fresh deal from the defendant, but only where a reasonable person would do so. A claimant who has been wrongly dismissed and offered the same job on the same terms, with no stigma, may be expected to take it. A claimant who would have to work alongside the very people who accused them is not.
Mitigation does not require the claimant to affirm a doomed contract
The rule interacts with the choice after repudiation. When one party signals they will not perform, the other can either accept the repudiation and end the contract, or affirm it and keep it alive.
- If the claimant accepts the repudiation, the duty to mitigate applies at once. The claimant must look for alternatives.
- If the claimant affirms, the contract continues. In the classic case, a claimant may in some circumstances carry on performing and claim the full price, without any duty to mitigate. This is allowed only where the claimant has a legitimate interest in doing so and can perform without the defendant's co-operation. Courts treat this exception narrowly. Where the claimant would be acting wastefully or oppressively, the court applies the usual mitigation reasoning anyway.
Mitigation gains and the "set-off" question
If the claimant mitigates successfully, the gain is taken into account. There is a well-known qualification: the gain must arise from the mitigation and be connected to the breach.
Consider a seller whose buyer refuses to take goods. The seller resells to someone else at the same price. If the seller could have supplied both buyers (a "lost volume" seller with unlimited stock), the second sale was not a substitute. The seller made the second sale anyway. In that case the seller has lost a sale and recovers the lost profit on the first contract. Without that limit, the rule would wrongly deny damages to businesses that can serve every customer.
This is a decision rule you can apply:
- Would the claimant have made the second transaction even if the first contract had been performed?
- If yes, the second sale does not reduce damages.
- If no, the second sale replaces the first and reduces damages.
Timing
Mitigation is judged on what was reasonable at the time, not with hindsight. Two points follow.
- A claimant who acts sensibly but whose attempt fails loses nothing. The cost of the failed attempt is recoverable.
- A claimant who acts sensibly and then does better than expected must give credit for the gain. A claimant who does worse than reasonable alternatives was available gets no credit for the shortfall.
The date used to assess loss is normally the date of breach. Courts depart from this when it would be unfair, and the claimant may be allowed a reasonable time to find a substitute.
Common errors
- Treating mitigation as a duty to the defendant. It is a cap on recovery. There is no separate claim.
- Putting the burden on the claimant. The defendant must prove the failure.
- Forgetting the costs of mitigation. These are recoverable, which is why a claimant should keep records.
- Ignoring lost volume. Substitute sales do not always reduce damages.
- Applying hindsight. Judge the claimant's steps by what they knew then.
- Assuming a claimant must accept any offer. The offer must be one a reasonable person would take.
How mitigation fits the damages framework
Looking ahead
Mitigation is one of the inputs to the final chapter on choosing remedies. A claimant weighing damages against specific performance needs to know that damages will be reduced by avoidable loss. Where the claimant has a real chance of finding a substitute, damages are more likely to be an adequate remedy. That makes an order to perform less likely.
Exercise
A builder agrees to build a garage for a homeowner for 20,000. The homeowner cancels the job before work begins. The builder had planned to use two workers and spare capacity for the job, and could have taken on other work as well. A month later, the builder takes a different 20,000 job. The builder sues for lost profit on the first contract. Does the second job reduce damages, and why? What else could the builder recover?
Show answer
The second job probably does not reduce damages. The builder had spare capacity and could have done both jobs, so the second job was not a substitute for the first. The builder is a lost volume contractor and can recover the profit lost on the cancelled contract. The builder can also recover reasonable costs incurred in trying to limit the loss, such as advertising to find replacement work. The homeowner would bear the burden of proving that the builder failed to mitigate.
Exercise
A claimant is wrongly dismissed. The employer then offers the same job back on the same terms, with no accusation or loss of status. The claimant refuses and takes no other work for a year. The claimant sues for a year's salary. What is the likely result, and who must prove what?
Show answer
Damages are likely to be reduced or removed. A reasonable person would have accepted the offer, so the loss during the year was avoidable. The employer must prove that the claimant failed to mitigate and must show how much loss that failure caused. The claimant need not prove that they tried to mitigate. If the offer had involved working with people who had publicly accused the claimant, refusing could have been reasonable.