Info records, contracts, and source determination
This chapter assumes you know the purchasing organization and plant structure, and that a supplier Business Partner and a material master record already exist. Here you will see how SAP decides which supplier and price to propose when a purchasing need appears.
Why sourcing data exists
Without sourcing data, a buyer types the supplier and price into every purchase order. Sourcing data stores that agreement once. The system then proposes it in requisitions, RFQs, and purchase orders. Two objects carry most of this work: the purchasing info record and the outline agreement (contract).
The purchasing info record
A purchasing info record links one supplier to one material. It holds data that applies to that pair:
- Planned delivery time and standard order quantity
- Net price, price conditions, and validity dates
- Under-delivery and over-delivery tolerances
- Supplier's own material number and order unit
The record can exist at purchasing organization level, or at plant level for the same organization. The plant-level record wins when both exist. The info record type (standard, subcontracting, pipeline, or consignment) decides which kind of order can use it.
Info records are created manually in transaction ME11, or in the Fiori app Manage Purchasing Info Records. They are also created automatically when you post a purchase order, if the material's info update indicator is set.
Contracts and scheduling agreements
An outline agreement is a long-term agreement with a supplier. It is not an order and does not trigger delivery on its own.
| Type | Key feature | Typical use |
|---|---|---|
| Quantity contract | Agreed total quantity | Buying a fixed volume in several orders |
| Value contract | Agreed total value | Services or mixed materials |
| Scheduling agreement | Delivery schedule lines | Regular deliveries in a repeating pattern |
A purchase order that references a contract is called a release order. Each release reduces the remaining target quantity or value on the contract.
How source determination works
Source determination is the logic that picks a source for a requisition item. The system checks sources in this order:
- The source list, if the material is flagged as source-list required for the plant.
- Outline agreements valid on the requirement date.
- Purchasing info records valid on the requirement date.
If exactly one source qualifies, the system assigns it. If several qualify, the buyer chooses. A fixed source in the source list overrides the other checks.
Common errors
- A missing plant assignment on the contract item means the plant's requisitions never find it.
- Setting a source list as mandatory without any entries blocks all purchasing for that material and plant.
- A price in the info record does not update itself when a contract changes. The purchase order price comes from whichever source was picked.
Exercise
A plant has a valid info record for a material and also a valid quantity contract with the same supplier. The material is not source-list required. Which source does the system propose, and what happens to the contract when the order is created?
Show answer
Source determination checks outline agreements before info records, so the contract is proposed. The resulting purchase order is a release order against the contract, and it reduces the contract's remaining target quantity.