A purchase requisition (PR) is an internal request that asks purchasing to buy a material or service. It does not commit the company to a supplier. This chapter assumes you know the organizational units from earlier chapters (company code, plant, purchasing group) and that the material master data already exists.
What a requisition contains
A PR has no header data of its own that matters for the process. All the meaning sits in its items. Each item holds:
- The material (or a short text for a non-stock item) and the requested quantity and unit.
- The plant and, optionally, a storage location.
- The delivery date, which drives planning and later the purchase order schedule line.
- The purchasing group responsible for buying it.
- An item category and account assignment category, for example K for cost center. This matters when you buy something that is consumed directly rather than stocked.
- An optional fixed supplier or source, such as a contract or info record.
Two ways a requisition is created
Manual creation is done by a requester, typically in the Fiori app Create Purchase Requisition (the classic transaction is ME51N). Automatic creation comes from material requirements planning (MRP), which creates requisitions when stock falls below what planning data says is needed. Planned orders from MRP are converted into PRs, so the buyer sees the same document either way.
Creating one manually
- Open Create Purchase Requisition.
- Enter the material, quantity, plant, and delivery date on the item.
- For a non-stock purchase, choose the account assignment category and enter the cost center or other object.
- Check the purchasing group and fix it if the default is wrong.
- Save. The system returns a PR number.
For a material with a source list, a contract, or a single info record, the system proposes the supplier during assignment. If it finds none, the buyer picks one later.
Common errors
- Missing purchasing group. The group is not defaulted for the user, and the material master has none. Enter it on the item.
- Material blocked for procurement. The plant-level status in the material master blocks the purchase. Fix the status, not the PR.
- Delivery date in the past. The system warns or rejects it, depending on settings. Enter a realistic date.
- Wrong account assignment. Changing the category after the PR is converted is not possible. Correct it before the order exists.
Approval of requisitions
Some companies release requisitions before purchasing may act on them. This uses a release strategy based on value or account assignment. Release strategies are covered in a later chapter. A PR that is not yet released cannot be converted.
Exercise
A requester needs office chairs charged to a cost center, and the chairs have no material master record. Which item settings must the requester supply, and what happens to the PR afterwards?
Show answer
The requester enters a short text, the quantity, the plant, the delivery date, and account assignment category K with the cost center. After saving, the PR waits for the buyer, who assigns a supplier and converts the item into a purchase order. If a release strategy applies, the PR must be released first.