Sub topic 1
The Core Exchange: What Each Party Must Do
Prerequisites
This chapter assumes you know the basic idea of a contract: an offer, an acceptance of that offer, and consideration (something of value each side gives). You should recognize common commercial terms such as buyer, seller, supplier, and customer. No legal training is needed. This is general education, not legal advice. Rules differ by jurisdiction and contract type, and a later chapter covers those differences.
Why start with the exchange
A commercial contract is mostly a plan for swapping performance. One party delivers goods or services. The other pays. Most clauses in the contract exist to answer practical questions about that swap:
- Who must do what?
- By when?
- In what order?
- What happens if one side does not do it?
Three clauses carry most of this work:
- The payment clause says what the buyer owes, in what form, and when.
- The delivery clause says what the seller hands over, where, when, and how.
- The acceptance clause says how the buyer confirms that what arrived is what was promised.
Each clause can be read alone, but disputes usually arise where two of them meet. For example, a buyer withholds payment because it says the goods are defective, and the seller says the buyer already accepted them. This chapter sets up the vocabulary and the working model. Later chapters take each clause in detail.
Performance obligations
A performance obligation is something a party has promised to do under the contract. Performing means doing it in the way the contract requires. Simply doing something close to it may not count.
In a typical sale of goods or a services contract, the main obligations look like this:
| Party | Core obligations | Clause that usually governs them |
|---|---|---|
| Supplier (seller) | Deliver conforming goods or services; transfer title where goods are sold; correct defects as agreed | Delivery, acceptance |
| Customer (buyer) | Pay the price; take delivery; test and accept or reject within the agreed process | Payment, acceptance |
Conforming means matching the contract's description, quantity, quality, and specifications. Goods that do not match are non-conforming.
Note that the buyer has duties besides paying. A buyer who refuses to accept a delivery date, does not provide access to a site, or ignores a testing deadline can be in breach even if it has money ready. A breach is a failure to perform an obligation without a legal excuse.
Concurrent and sequential performance
The contract also sets the order of performance. There are three common patterns:
- Concurrent performance. Both sides perform at the same time. A retail purchase works this way: you hand over money and receive the goods in one step.
- Seller first. The supplier delivers, the customer then tests and accepts, and payment follows. Most business-to-business supply and software or construction contracts work this way.
- Buyer first. The customer pays in advance or at milestones before the supplier completes. Deposits and prepayments follow this pattern.
The order matters because it decides who carries the risk of the other side's failure. The party that performs first extends credit to the other. A supplier who delivers before payment bears the risk that the customer will not pay. A customer who prepays bears the risk that the supplier will not deliver, or will deliver something defective. Much of the drafting in later chapters, such as milestones, acceptance testing, and set-off, exists to manage that risk.
Conditions and promises, briefly
Not every obligation has the same weight. Lawyers distinguish between a few kinds of terms, and the difference affects remedies. A later chapter covers this fully. For now, keep three ideas in mind.
- A promise (sometimes called a covenant) is a commitment to do something. If a party breaks it, the other party can usually claim damages, meaning money to compensate for the loss.
- A condition is an event or fact that must occur before another obligation becomes due. A clause saying "Supplier may invoice only after Customer accepts the Deliverable" makes acceptance a condition of invoicing.
- A serious breach of an important term may let the innocent party end the contract, while a minor breach usually leaves it with damages only. Which terms count as important varies by legal system and by what the contract says.
The practical lesson: if you want a payment to depend on an event, such as acceptance, say so in words that create a condition. A vague sentence invites argument about whether the payment obligation was ever triggered.
How the three clauses link
The clauses depend on each other. Here is the working model for a seller-first contract.
- Delivery starts the process. It fixes the moment the customer can inspect the goods, and it often decides who bears the risk if they are lost or damaged.
- Acceptance closes the inspection step. It says whether the customer has agreed that the delivery meets the contract.
- Payment is often triggered by acceptance, or at least timed from invoice receipt or delivery.
If any link is vague, the chain breaks. Consider these common gaps:
- The contract says payment is due "30 days after delivery" but also says the customer has 20 days to test. The customer may have to pay for something it has not yet had time to accept.
- The contract says the supplier delivers "promptly" without a date. Neither side can tell whether delivery is late.
- The contract does not say what happens if the customer stays silent after testing. Silence may or may not count as acceptance.
The example clauses below show how a careful drafter closes these gaps. Read them as a connected set.
Payment. Customer shall pay each undisputed invoice in US dollars within thirty (30) days after the date Customer receives the invoice. Supplier may invoice only after Customer accepts the Deliverable under Section 5. Amounts not paid when due accrue interest at the lesser of one percent (1%) per month and the maximum rate permitted by law.This clause fixes the currency and the payment period, and it starts the period at receipt of the invoice, not at some earlier date. It ties invoicing to acceptance, so payment depends on the acceptance clause. It also limits interest to a rate the law allows.
Delivery. Supplier shall deliver the Goods to the Customer's warehouse at the address in the Order on or before the Delivery Date. Risk of loss passes to Customer when the Goods are unloaded at that address. Title passes to Customer on payment in full.This clause names the place and the date. It separates risk of loss (who bears the cost if goods are damaged or destroyed) from title (legal ownership). Here the customer bears the risk from unloading, but owns the goods only after paying.
Acceptance. Customer has ten (10) business days after delivery to test the Deliverable against the Specifications. If Customer gives written notice within that period describing how the Deliverable fails the Specifications, Supplier shall correct the failure and redeliver within ten (10) business days. If Customer gives no notice within the testing period, the Deliverable is deemed accepted.This clause sets a testing window and requires written notice of failure. It also gives the supplier a chance to fix the problem, and it says what silence means. Silence counts as acceptance.
Where disputes usually start
Most disputes over the core exchange fall into a few patterns. Knowing them tells you what to look for when you read or draft a clause.
| Dispute | Typical cause | Clause to check |
|---|---|---|
| Late payment | Unclear due date, unclear start of the payment period, disputed invoice | Payment |
| Missed delivery date | Vague date wording, no stated consequence for delay | Delivery |
| Rejected goods or services | Vague quality standard, no testing procedure, no cure period | Acceptance |
| Withheld payment | Payment not clearly tied to acceptance, or right to withhold not stated | Payment and acceptance |
| Lost or damaged goods | Risk of loss not allocated, or tied to a vague event | Delivery |
A worked reading
Suppose a customer orders 500 units from a supplier. The Order names a warehouse and a Delivery Date of 1 March. The units arrive on 28 February and are unloaded the same day. Using the three clauses above:
- Delivery is on time, since 28 February is before the Delivery Date. Risk of loss passes to the customer at unloading on 28 February.
- Title has not passed, because the customer has not paid in full.
- The testing period runs for ten business days from delivery. If the customer finds that 40 units fail the Specifications, it must give written notice inside that period, describing the failure.
- The supplier then has ten business days to correct the failure and redeliver.
- The supplier may invoice only after acceptance. Once the customer receives the invoice, the 30-day payment period begins.
If a fire destroys the warehouse on 2 March, the customer bears the loss, even though it does not yet own the goods, because risk passed at unloading. A buyer who did not expect this should negotiate a different risk rule, or buy insurance. This is why separating risk from title matters.
Summary of the working model
- Each side has performance obligations. The order of performance decides who extends credit to whom.
- Payment, delivery, and acceptance are connected. Acceptance often triggers invoicing, and delivery starts the testing clock.
- Clear dates, defined tests, and explicit conditions reduce disputes.
- Remedies depend on whether a term is a condition, a promise, or an important term, and this varies by jurisdiction.
Exercise
A contract says "Customer shall pay Supplier within 30 days of delivery." It also says "Customer has 20 days after delivery to test the goods." On day 25 the customer rejects the goods in writing, and it has not paid. Supplier says payment was due on day 30 regardless. Identify the drafting gap, and suggest one change that fixes it.
Show answer
The payment period runs from delivery, but acceptance happens later, so the customer may owe payment for goods it has not yet accepted or may later reject. Also, the rejection on day 25 falls outside the 20-day testing window, so the contract does not clearly say whether it is valid. Fix: start the payment period when the customer accepts the goods (or receives an invoice issued after acceptance), as in the sample payment clause. Also state whether late rejection is allowed and what silence means.
Exercise
In the sample delivery clause, a fire destroys the goods one day after unloading and before the customer pays. Who bears the loss, and who owns the goods?
Show answer
The customer bears the loss, because risk of loss passed at unloading. The supplier still owns the goods, because title passes only on payment in full. The customer may still owe the price depending on the contract and governing law, which is why the customer should insure the goods or negotiate a later risk transfer.