Sub topic 9
Partial delivery and installment contracts
This chapter assumes you have read the earlier chapters on delivery terms and delivery dates. You should know what a delivery clause fixes (place, method, date) and why a missed date can be a breach. It is general education, not legal advice. The rules differ by jurisdiction and contract type, and the examples below are labeled by the legal system they come from.
Two different situations
The two terms in the title describe different things, and mixing them up causes drafting errors.
- Partial delivery means the supplier delivers less than the contract called for at a time when the contract expected one complete delivery. The shortfall is usually unplanned.
- An installment contract is one that plans for delivery in separate lots, often with a schedule. The parties agreed in advance that performance would come in pieces.
The difference matters because the default rules treat them differently. A buyer can often refuse a surprise partial delivery. A buyer who agreed to installments has accepted the idea of receiving goods in pieces, and the law then asks a different question: how serious is a problem with one piece, and what does it say about the rest?
The default position on partial delivery
Many legal systems start from the idea that a buyer should receive what was promised, all at once, unless the contract says otherwise. Three examples:
- Under the US Uniform Commercial Code (UCC) § 2-307, unless the circumstances give either party the right to make or demand delivery in lots, all goods called for by a contract for sale must be tendered in a single delivery, and payment is due only on that tender.
- Under the English Sale of Goods Act 1979, s. 31, the buyer is not bound to accept delivery by installments unless the contract says so.
- Under the UN Convention on Contracts for the International Sale of Goods (CISG) Article 51, if the seller delivers only part of the goods, the buyer's remedies apply to the missing part. The buyer can avoid the whole contract only if the failure to deliver completely amounts to a fundamental breach.
Because of this, a buyer that receives 800 of 1,000 units on the due date may usually refuse them, or accept them and claim damages for the shortfall. A buyer that wants to receive and use the 800 must say what happens to payment and to the remaining 200. A silent contract leaves that to the default rules, which may not match what the business wants.
Writing a partial delivery rule
A good clause answers four questions: may the supplier deliver in part, may the customer refuse, how is payment handled, and what happens to the balance.
Partial delivery. Supplier may deliver the Goods in more than one shipment only with Customer's prior written consent. If Supplier delivers fewer Goods than the Order requires without that consent, Customer may (a) accept the delivered quantity and pay for it at the unit price in the Order, or (b) reject the shipment under Section 5. Acceptance of a partial shipment does not waive Customer's right to the balance or to damages for late delivery of the balance. Supplier shall deliver the balance within ten (10) business days after the original Delivery Date.This clause gives the customer the choice, which fits the default position. A supplier would likely want a different version: a right to ship in lots, a duty on the customer to accept lots that conform, and payment for each lot. Which version is right depends on who has the bargaining power and how the goods are used. Ten units of a nine-part assembly are of little use until the ninth part arrives.
Designing an installment contract
An installment schedule needs more than a list of dates. Each of these items should be stated.
- The lots. State the quantity or deliverable and the delivery date for each installment.
- Separate or single price. State whether each installment has its own price and invoice, or whether the price is one amount allocated across installments.
- Payment trigger. State whether payment for each installment is due after that installment's acceptance, as in the payment clause earlier in this tutorial.
- Acceptance per installment. State whether each installment is tested and accepted alone, and whether acceptance of one lot is final for that lot.
- Effect of a defect. State what a failure in one installment does to later ones: can the customer suspend, cancel the rest, or only claim damages?
The payment clause from earlier in the tutorial can be adapted for installments by tying each invoice to acceptance of its own lot:
Installments. Supplier shall deliver the Goods in the installments listed in Schedule A. Each installment is a separate delivery for the purposes of Sections 4 (Delivery), 5 (Acceptance) and 6 (Payment), and Supplier may invoice each installment only after Customer accepts it. A defect in one installment does not entitle Customer to cancel any other installment unless the defect substantially impairs the value of the Goods as a whole, in which case Customer may cancel the remaining installments by written notice given within thirty (30) days after it learns of the defect.The standard "substantially impairs the value of the whole" appears in this clause deliberately. It copies a test used by the law, so a court is less likely to treat the clause as inconsistent with the default.
What the law does when an installment goes wrong
When a contract is divisible into installments, three outcomes are possible for a defective lot. The first is that the buyer rejects only that lot and the contract continues. The second is that the buyer treats the defect as a breach of the whole contract. The third is that the buyer accepts the lot and claims damages.
The UCC, in § 2-612, sets the main rules for installment contracts in the US:
- The buyer may reject an installment only if the nonconformity substantially impairs the value of that installment and cannot be cured. If the seller gives adequate assurance of cure, the buyer must accept it, unless the nonconformity is a defect in the required documents.
- If a default in one or more installments substantially impairs the value of the whole contract, the whole contract is in breach.
- The buyer loses the right to cancel for past installments, and reinstates the contract, by accepting a nonconforming installment without telling the seller promptly that it cancels, or by suing only for past installments, or by demanding performance of future ones.
The CISG takes a similar approach in Article 73. A party may avoid the contract for one installment if a failure in that installment is a fundamental breach. It may avoid the contract for future installments if the failure gives good grounds to conclude a fundamental breach will occur in them, and it must do so within a reasonable time. It may avoid installments already delivered or yet to be delivered if they are interdependent, meaning they cannot be used for the purpose the parties had in mind at the time of the contract unless all are delivered.
Waiver and reinstatement
A common failure is acting as if the contract continues without saying so. Suppose a buyer takes lot 3 although it was defective, pays for it, and then months later tries to cancel the contract because of the same defect. A court may find that the buyer accepted the defect and waived the right to cancel. The usual protection is a notice clause that requires prompt written notice of a defect and states that accepting an installment does not waive claims about it.
Suppliers face the mirror problem. A supplier that has been paid late for two installments and keeps shipping may be treated as having waived the late payment, or as having accepted the new pattern. The supplier should write a reservation of rights letter and use the contract's suspension right, described in the late payment chapter, before the pattern becomes the norm.
Choosing the structure
| Feature | Single delivery | Installment contract |
|---|---|---|
| Default right to refuse partial delivery | Strong | Weak; lots are expected |
| Payment timing | After the whole delivery | Per installment if the contract says so |
| Effect of a defect | Reject or accept the whole | Affects the lot, and the whole only if it substantially impairs the contract |
| Supplier's cash flow | Delayed | Smoother |
| Buyer's leverage | Strong, until payment | Weaker after early lots are paid for |
| Drafting burden | Lower | Higher: schedule, per-lot acceptance, cancellation rules |
Common drafting errors
- No statement of whether lots are separate. Without it, a dispute about lot 4 can freeze payment for lots 1 to 3.
- A price stated only as a total. If the contract is cancelled midway, nobody can tell what was paid for the delivered lots.
- Cross-default without a threshold. "Any failure allows cancellation of everything" invites a dispute about whether a trivial failure triggers it. A materiality test is a better choice.
- Silence on interdependent items. If lot 1 is useless without lot 5, say so, and let the customer reject lot 1 if lot 5 is not delivered.
- No deadline for notice. Open-ended rights to cancel leave the supplier exposed indefinitely.
Exercise
A contract requires four monthly installments of 500 units each, with each installment invoiced after acceptance. In month 2 the supplier delivers 500 units, but 40 of them fail the specification. The defect can be repaired within a week. The buyer wants to cancel the whole contract. Using the framework in this chapter, what is the buyer's likely position, and what should the buyer do to protect it?
Show answer
The defect affects 8 percent of one installment and can be cured, so it probably does not substantially impair the value of that installment, and very probably not the value of the whole contract. The buyer likely cannot cancel the whole contract. Under the UCC approach it must allow cure if the seller gives adequate assurance, and its remedies are to reject or reduce payment for the defective units and claim damages for any loss. To protect its position, the buyer should give prompt written notice describing the failure, say that accepting the conforming units does not waive claims, and not accept the defective units silently, because acceptance without notice can reinstate the contract and waive the right to cancel.