Sub topic 11
Dated Events: Payments, Anniversaries and Maturities
This chapter assumes basic Excel formulas, relative and absolute references, and a monthly model with periods across columns. You should also know how to use SUMIFS and the YEAR, MONTH, and DAY functions.
Financial models often need to place dated events into a monthly timeline. Examples include loan payments, contract anniversaries, lease renewals, and maturity dates. The event date should be calculated from one source date and then tested against each model period.
Calculate event dates with EDATE
EDATE shifts a date by a whole number of months. Its first argument is the original date. Its second argument is the number of months to move.
For a loan drawn on 31-Jan-2025, the payment for month 1 is one month after the drawdown date:
Inputs:
C4 = 31-Jan-2025
Payment date for period n:
=EDATE($C$4,D8)
If D8 = 1, the result is 28-Feb-2025.
If D8 = 2, the result is 31-Mar-2025.
If D8 = 12, the result is 31-Jan-2026.The absolute reference $C$4 keeps every payment calculation tied to the original drawdown date. The period counter in row 8 changes as the formula is copied across.
Day-of-month clamping
Some months do not contain the original day. Excel returns the last day of the target month instead of an error.
=EDATE(DATE(2025,1,31),1) -> 28-Feb-2025
=EDATE(DATE(2024,1,31),1) -> 29-Feb-2024
=EDATE(DATE(2025,1,31),2) -> 31-Mar-2025Calculate every event from the original date. Do not calculate the next event from the previous result. Chaining can make a schedule depend on an earlier clamped date.
=EDATE(DATE(2025,1,31),1) -> 28-Feb-2025
=EDATE(EDATE(DATE(2025,1,31),1),1) -> 28-Mar-2025
=EDATE(DATE(2025,1,31),2) -> 31-Mar-2025The first approach chains from 28-February and produces 28-March. The second calculates two months from the original 31-January and produces 31-March.
Assign an event to a model period
A monthly timeline normally has a period start in row 5 and a period end in row 6. To determine whether an event belongs in a period, test both boundaries.
Event date in F4:
=EDATE($C$4,D8)
Event belongs to the period in column D:
=AND($F$4>=D$5,$F$4<=D$6)The result is TRUE when the event date is on or after the period start and on or before the period end. This includes events on the first or last day of a month.
You can use the test as a flag for payment amounts:
Payment amount in period D:
=IF(AND($F$4>=D$5,$F$4<=D$6),$C$5,0)Here, C5 contains the payment amount. Copy the formula across the monthly columns.
Anniversaries and maturities
For a contract anniversary, calculate the date from the contract start date:
First anniversary:
=EDATE($C$6,12)
Second anniversary:
=EDATE($C$6,24)For a maturity date defined as a fixed number of months after drawdown, use the same pattern:
Maturity date:
=EDATE($C$4,$C$7)If maturity must occur at month end, use EOMONTH instead:
Month-end maturity:
=EOMONTH($C$4,$C$7)This distinction is a modeling decision. A contract that matures on the same day number uses EDATE. A facility that matures on the final calendar day uses EOMONTH.
Exercise
Exercise
A loan is drawn on 31-Jan-2025. The model has a period from 1-Mar-2025 through 31-Mar-2025. Which formula tests whether the two-month payment falls in that period, and what is the result?
Show answer
Use =AND(EDATE(DATE(2025,1,31),2)>=DATE(2025,3,1),EDATE(DATE(2025,1,31),2)<=DATE(2025,3,31)). The result is TRUE because the payment date is 31-Mar-2025.