Sub topic 16
Test cycles and cutover planning
This chapter assumes you can create a migration project, select migration objects, and run the validate, convert values, simulate and migrate steps. It also assumes you can read the cockpit's messages. Here you will use those skills to plan repeated test loads and the final productive load, called the cutover.
Why one successful load is not enough
A single clean simulation tells you that one data set worked in one system at one moment. It does not tell you three things you need for go-live:
- How long the full load takes with production data volumes.
- Whether the load order holds up when every object is loaded together.
- Whether the people involved know their tasks without improvising.
Test cycles answer these questions before the productive run. Each cycle repeats the same procedure with fresh data, and each repeat should leave fewer surprises.
Kinds of test cycles
Projects use different names for these cycles. The purposes below are the useful part.
| Cycle | Purpose | Typical data | Target system |
|---|---|---|---|
| Unit load | Check that each object's template, mapping and value conversion work | Small sample per object | Development or sandbox |
| Integrated load | Check load sequence and dependencies across all objects | Reduced but representative set | Test system |
| Mock cutover (dress rehearsal) | Rehearse the real timeline, roles and checkpoints, and measure runtimes | Full production-sized extract | System that mirrors production |
| Productive cutover | Load the final data into the production system | Final, frozen extract | Production |
Run at least one mock cutover with full data volumes. Runtime estimates from small samples are unreliable. Load time often does not scale in a straight line with record count, because dependent objects wait for earlier ones and error rounds add time.
What to record in every cycle
Treat each cycle as a measurement, not just a pass or fail. Keep a log with one row per migration object and update it each time:
- Number of source records, records that passed validation, records that migrated, and records that failed.
- Duration of each step: validation, simulation, migration.
- The top error messages and their root causes (source data, mapping, or object configuration).
- The fix that was applied and where it lives, for example a corrected source file, a changed value mapping, or an adapted object.
- The person who performed each step.
The error causes matter most. A message you fixed by hand in cycle 1 will return in cycle 2 unless the correction is built into the source extract or the mapping. If you correct data directly in the target system, the fix is lost the next time you load from the legacy data.
A cycle as a loop
The cycles form a loop with a decision at the end. Fixes found in one cycle feed the next.
Defining exit criteria
Decide in advance when a cycle counts as good enough. Without written criteria, the go or no-go discussion becomes a matter of opinion. Examples of measurable criteria:
- Every object reaches at least an agreed success rate, such as 100 % for financial balances and a lower threshold for low-risk master data.
- No unresolved error remains without a documented decision to accept it or fix it manually after go-live.
- Reconciliation totals match the legacy system, for example open item totals per company code, or the count of business partners per type.
- The measured total runtime fits inside the planned downtime window with a safety margin.
- The mock cutover was executed by the same people who will run the productive cutover.
Reconciling the result
Migrating without error messages does not prove the data is right. After each integrated or mock load, compare the target system with the source using figures that the business can confirm:
- Record counts per object, source versus target.
- Control totals, such as the sum of G/L balances or open receivables.
- A sample of individual records checked by a data owner from the business side.
Record the reconciliation result in the same log as the runtimes. A count that is off by a few records often points to records that were filtered out in the extract or rejected during validation.
Building the cutover plan
The cutover plan is a time-ordered list of tasks for the productive switch. For the data migration part, it usually contains these blocks:
- Preconditions. Target system configuration is complete and transported, migration project and objects are ready, and authorizations are in place for everyone who runs steps.
- Freeze. The date and time after which the legacy system stops accepting changes to the data in scope. The extract must reflect this freeze.
- Final extract and preparation. Create the files, fill the staging tables, or confirm the direct transfer connection. Run your own pre-checks before the cockpit validation.
- Validation, value conversion and simulation. Repeat the same steps used in the mock cutover. Simulation on the final data is your last chance to find problems before records are created.
- Migration in dependency order. Master data first, then the objects that depend on it, and balances and open items last. The order is the one you proved in the integrated and mock loads.
- Reconciliation and sign-off. Business owners confirm the control totals. This is a formal checkpoint.
- Release. Unlock the system for users or for the next cutover activity.
For each task, record the owner, the planned start and duration (taken from the mock cutover), the predecessor task, and the person who confirms completion. Add a fallback decision point after reconciliation. If the exit criteria are not met by then, the plan must say who decides and what happens next.
Handling data that changes after the extract
Transactional data keeps changing while loads run. Plan how you will treat it:
- Master data is often loaded early, with a short list of changes carried over manually or in a second small load.
- Balances and open items are usually extracted at a defined cut-off date. Plan the cut-off to match the period-end or key date that finance needs.
- Changes after the freeze need a rule. Either the business stops entering them, or it records them in a list for manual entry after go-live.
Whatever you choose, write it into the cutover plan so that nobody decides it under time pressure.
Reusing what you built between cycles
Keep the migration project, its mappings and the file templates stable across cycles, and change them only through a controlled fix. Keep a dated copy of each extract, so you can reproduce a result and compare it with a later cycle. Check the documentation for your release to see how migration projects and their settings are copied or moved between systems. Handling differs by approach and release, and you should not assume that projects move the same way as configuration transports.
Common errors
| Problem | Likely cause | Prevention |
|---|---|---|
| Productive load takes much longer than planned | Runtime estimated from a small sample | Time the mock cutover with full volumes |
| The same errors appear in every cycle | Fixes made in the target system or in a copy of the file | Fix in the source extract, mapping or object, and log the change |
| Objects fail because required data is missing | Load order differs from the proven one | Follow the dependency sequence from the integrated load |
| Reconciliation differs after a clean load | Extract filters or a changed cut-off date | Document extract rules and keep dated extracts |
| Nobody knows who starts the next step | Roles left vague in the plan | Name an owner and a confirmer for every task |
Exercise
Your first mock cutover with full data volumes took 14 hours, but the downtime window is 10 hours. Name two kinds of actions you could take before the next cycle, and what you would measure to confirm they worked.
Show answer
Examples: reduce error-handling rounds by fixing the root causes of the most frequent messages in the extract or mapping, so fewer records need reloading; and review the load sequence or the data in scope, for example moving data that is not needed on day one to a later load or loading it before the freeze. In the next cycle, measure the duration per object and per step (validation, simulation, migration), plus the number of error rounds, and compare them with the log from the first mock cutover to see which change saved time.
Exercise
Why must a correction made by hand in the test system be added to the extract or mapping as well?
Show answer
The productive cutover starts again from the legacy data. A manual fix in the target system does not change the source data or the mapping, so the same error will return in the next cycle and in production unless the fix is reproducible.