Sub topic 4
Creating a migration project
This chapter assumes you can open SAP Fiori apps and that your user already has the migration authorizations from the previous chapter. It also assumes you have chosen a transfer approach (files, staging tables, or direct transfer). A migration project is where that decision is recorded. Everything else in the cockpit hangs off the project.
What a migration project is
A migration project is a container in the migration cockpit. It holds four things:
- The transfer approach you chose.
- The list of migration objects you plan to load.
- The data you upload or stage for each object.
- The state of every step for each object: validation, value mapping, simulation, and migration.
The project is the unit you track, test, and hand over. A typical program has one project per target system and per test cycle. The cutover run uses its own project in the productive system.
The project belongs to the system where you create it. It is not transported like configuration. If you build a project in a test client, you recreate it in the next system, and you re-upload or re-stage the data there.
Before you start
Check these items before you click Create. Each one is cheaper to fix now than after you have uploaded data.
- Target system and client. Confirm you are logged on to the system you intend to load. A project created in the wrong client is easy to miss, because the project list looks the same everywhere.
- Authorizations. You need the roles for the migration cockpit app, as covered in the previous chapter. If the app tile is missing or the Create action is disabled, the cause is almost always a missing role. It is rarely a defect.
- Approach decision. Know which approach the project will use. The next section explains why this matters.
- Prerequisites of the approach. Direct transfer needs a working connection to the source SAP system. Staging tables need access to the staging database schema. File transfer needs nothing beyond the cockpit.
- Naming convention. Agree on one before the first project exists.
Choosing the approach at creation time
When you create a project, the cockpit asks for the transfer approach. In the releases we describe here, the approach applies to the whole project. If you later decide you need a different one, you create a new project. You cannot convert an existing one.
| Approach | What you provide | Typical use |
|---|---|---|
| Transfer data using files | A project name | Small to medium volumes, data prepared in spreadsheets or extracts |
| Transfer data using staging tables | A project name, plus the database connection for the staging schema | Large volumes, or data prepared by ETL tools or database scripts |
| Transfer data directly from an SAP system | A project name, plus the connection to the source SAP system | An SAP ERP source system where predefined extraction is available |
The exact wording of the options and the availability of each approach depend on your release and on whether you run SAP S/4HANA Cloud or an on-premise system. Check the options your system shows before you plan around one of them.
Creating the project step by step
The steps below follow the usual flow in the Fiori app for migrating data. Labels can differ slightly between releases.
- Open the migration cockpit app from the launchpad. The tile is usually called Migrate Your Data.
- Choose Create on the project list.
- Enter a project name. Use a name that tells a colleague the purpose, the cycle, and the scope, for example
FIN_CYCLE2_MASTERDATA. - Select the transfer approach.
- If the approach needs a connection (staging database or source SAP system), select or enter it. Test the connection if the dialog offers a test.
- Confirm. The cockpit creates the project and opens it.
- Choose the option to add migration objects, and select the ones you need. The next chapter explains how to choose them.
After step 7 the project shows one line for each object. Each line has a status and the actions that apply to the current step.
Naming that survives a long program
Project names are free text. Over many test cycles, vague names such as Test1 or Max_new become a problem. A useful pattern has three parts:
- Area or wave, such as
FINorLOG. - Cycle, such as
C1orC2. - Content, such as
MASTERDATAorOPENITEMS.
For example, LOG_C2_MATERIALS. Splitting a program into projects by business area also lets different teams work in parallel without changing each other's projects.
One project or several
A single project can hold many objects, but that does not mean it should. Consider these criteria:
- Ownership. If finance and logistics teams load their own data, separate projects keep their uploads and error lists apart.
- Load sequence. Objects that depend on each other must be loaded in order. A project for master data and a second one for transactional data makes the sequence visible. Dependencies are covered in a later chapter.
- Approach. Different approaches need different projects. If most objects arrive as files but one large object arrives through staging tables, you need two projects.
- Reporting. One project per cycle and area gives you a simple progress report.
The cost of too many projects is overhead: more lists to open and more statuses to check. For a small migration, one project per cycle is enough.
What the project does not do
Some common expectations are wrong, and they cause rework:
- The project does not transform your legacy data. Conversion happens in later steps, in value mapping and through the object's own rules.
- The project does not check dependencies for you in advance. It lets you select objects in any order. The order of execution is your responsibility.
- The project does not guarantee that data is complete. Validation and simulation find problems in the data you gave it. They do not find records you forgot to extract.
Common errors at project creation
| Symptom | Likely cause | What to do |
|---|---|---|
| The app tile is not on the launchpad | Missing role or catalog assignment | Ask your administrator to assign the migration roles and check the launchpad space or page |
| Create is disabled | Missing authorization for creating projects | Check the authorization objects of the assigned role |
| The staging option fails with a connection error | Database connection or schema not set up | Ask the database administrator to verify the connection and the schema |
| Direct transfer shows no source connection | The connection to the source system was not configured | Create the connection first, then create the project |
| The object list is shorter than expected | The object is not available for this approach or release | Check the object's availability for your approach before planning |
| You created the project with the wrong approach | The approach cannot be changed | Create a new project with the right approach and reuse your prepared data |
A short checklist
Before moving to object selection, confirm the following:
- The project exists in the right system and client.
- The approach matches how your data will arrive.
- Any required connection is created and tested.
- The name follows your convention and is understood by the team.
- The owner and purpose are recorded outside the cockpit.
The next chapter explains how to select migration objects inside the project.
Exercise
Your team receives 12 object files from a legacy ERP and one very large table that an ETL tool writes directly to a database. A colleague proposes one project that uses the file approach for everything. What is wrong with this plan, and what would you do?
Show answer
The transfer approach is fixed per project, so one file-based project cannot take data that arrives through a database. Create two projects. Use a file project for the 12 objects. Use a staging table project, with its database connection, for the large table. Name them so their scope is obvious, for example LOGC1FILES and LOGC1STAGING. Keep in mind that load order across the two projects is still your responsibility if the objects depend on each other.
Exercise
You created a project last week and now find it was created in the quality client instead of the intended test client. Does deleting the project fix the situation? Explain.
Show answer
Only partly. Deleting the project removes the project and its cockpit bookkeeping, but it does not remove business data that migrations already created. If you only prepared or uploaded data and never ran a migration, deleting and recreating the project in the right client is enough. If a migration already ran, you must also clean up the created business data using the normal processes for those objects, and then recreate the project in the correct client.