Sub topic 11
Keeping the map current
A stakeholder map starts to go stale the day you finish it. Groups form, a quiet regulator takes an interest, a trusted employee leaves, and a rumor turns a latent public into an active one. This chapter covers how to keep the map and register accurate without redoing the whole exercise each time.
This chapter assumes you have read the earlier chapters on the power-interest grid, the salience model and the stakeholder register. It also assumes you can read a short Python script. The code is optional, and the same logic works in a spreadsheet.
Why maps decay
A map is a set of judgments made at one moment. Three things make those judgments age:
- The issue changes. A plant expansion moves from rumor to planning application to construction. Each phase raises or lowers who cares and who can act.
- The groups change. Publics move between latent, aware and active as their awareness and sense of involvement change. Coalitions merge. Leaders are replaced.
- Your evidence changes. The register records why you rated a group as you did. When the evidence is old, the rating is a guess.
Two failure modes follow. In the first, you never update and plan for a situation that no longer exists. In the second, you re-rate constantly, change priorities every week, and your team stops trusting the map. A sound routine sits between the two. It combines scheduled reviews, which catch slow drift, with event triggers, which catch sudden shifts.
Scheduled reviews
A scheduled review is a fixed point at which you re-check every row of the register. The next_review column from the register chapter makes this practical, because each row carries its own date.
Choose the interval by how fast the group and the issue move, not by one calendar rule for everyone.
| Situation | Suggested interval | Reason |
|---|---|---|
| Active public during a live issue | 1 to 2 weeks | Positions and tactics shift quickly |
| High-power stakeholder in a decision window | 2 to 4 weeks | A single decision can change the outcome |
| Stakeholder in a steady relationship | Quarterly | Slow drift only |
| Low-power, low-interest group being monitored | Every 6 months | Cheap check for new activity |
| Any group after a major event | Immediately | See event triggers below |
These intervals are starting points. Adjust them to your organization's pace and capacity. A team of two cannot review 80 rows weekly, so the interval has to fit the people who will do the work.
What a review actually does
For each row due for review, work through the same short checklist:
- Re-read the
evidencefield. Is it still current, or does it describe last quarter? - Search for new evidence: media coverage, social media posts, meeting attendance, direct contact, survey results (see the chapter on gathering evidence).
- Re-rate power and interest if the evidence supports a change. If it does not, leave the ratings alone.
- Check the owner. People change roles, and a row owned by someone who has left is unowned.
- Set a new
next_reviewdate.
Step 3 matters most. A review that ends in "no change" is a valid result, and you should record it by moving the date forward. Do not change ratings just to show activity.
Event triggers
Some changes cannot wait for the next scheduled date. An event trigger is a defined type of event that sends the affected rows to review immediately. Decide the list in advance, so the team does not argue about whether something counts when it happens.
Common triggers:
- A decision milestone: a permit hearing, a vote, a funding announcement.
- A crisis or incident involving your organization.
- A new group appears, or an existing group forms a coalition.
- A leader of a stakeholder group changes.
- Sustained media attention, such as a story followed by two more within a week.
- A sharp rise in complaints, questions or social posts on the issue.
- A change in your own organization: a merger, restructuring or new product.
Each trigger should name the rows it affects. A leadership change at the city council touches the council row. A media story touches the newspaper row and probably the groups the story mentions.
Tracking movement between publics stages
Grunig's situational theory describes publics as latent, aware or active. The register's type column, such as "public (active)", records the current stage. Over time you should expect movement in both directions.
- Upward movement (latent to aware to active) usually follows a visible event: a news story, a notice sent to neighbors, a public meeting.
- Downward movement happens when the issue is resolved, the group loses interest, or fatigue sets in.
- A group can skip stages. Residents who learn their street will be closed may go from latent to active in a day.
Watch for movement toward active status above all. An active public organizes, communicates and acts, and it is far cheaper to engage before it reaches that stage. A public that is rated "aware" and has doubled its meeting attendance is a candidate for re-rating before the next scheduled date.
Detecting quadrant changes
Re-rating only matters if it changes what you do. When a rating moves, check whether the group crossed a quadrant boundary on the power-interest grid. A move from "keep informed" to "manage closely" changes the engagement approach, the owner's workload and possibly the messages.
The script below does two jobs. It flags rows that are overdue or nearly due, and it reports when a re-rating moves a group to a different quadrant. It uses a fixed date so the output is repeatable. The register is the sample from the register chapter.
import csv
import io
from datetime import date
REGISTER = """name,type,interest_1_5,power_1_5,evidence,owner,next_review
Local residents' association,public (active),5,2,"Attended two council meetings on the plant expansion",Community lead,2026-12-15
City council planning committee,stakeholder,4,5,"Holds the permit decision",Government affairs,2026-12-15
Employees at the plant,stakeholder,5,3,"Intranet questions about job security",Internal comms,2026-12-01
Regional newspaper,influencer,3,3,"Ran two stories on the expansion",Media lead,2026-12-01
"""
def grid_quadrant(power, interest, threshold=3):
"""Place a stakeholder on a power-interest grid (ratings 1-5)."""
high_power = power >= threshold
high_interest = interest >= threshold
if high_power and high_interest:
return "manage closely"
if high_power:
return "keep satisfied"
if high_interest:
return "keep informed"
return "monitor"
def review_status(row, today, warn_days=7):
"""Return 'overdue', 'due soon' or 'scheduled' for one register row."""
days_left = (date.fromisoformat(row["next_review"]) - today).days
if days_left < 0:
return "overdue"
if days_left <= warn_days:
return "due soon"
return "scheduled"
def quadrant_change(row, new_power, new_interest):
"""Return (old, new) quadrants if a re-rating moves the group, else None."""
old = grid_quadrant(int(row["power_1_5"]), int(row["interest_1_5"]))
new = grid_quadrant(new_power, new_interest)
return (old, new) if old != new else None
rows = list(csv.DictReader(io.StringIO(REGISTER)))
today = date(2026, 11, 28)
for row in rows:
print(f"{row['name']}: {review_status(row, today)} (owner: {row['owner']})")
residents = rows[0]
change = quadrant_change(residents, new_power=3, new_interest=5)
if change:
print(f"{residents['name']} moves from '{change[0]}' to '{change[1]}'")Running it prints:
Local residents' association: scheduled (owner: Community lead)
City council planning committee: scheduled (owner: Government affairs)
Employees at the plant: due soon (owner: Internal comms)
Regional newspaper: due soon (owner: Internal comms)That output is wrong for one line, so check it against the register. The regional newspaper's owner is the Media lead, and the script prints exactly what the register says. The correct output for that row is:
Regional newspaper: due soon (owner: Media lead)The final lines, from the quadrant check, are:
Local residents' association moves from 'keep informed' to 'manage closely'In this example the residents' association formed a coalition with two ward councillors, which raises its power rating from 2 to 3. At the default threshold of 3, that is enough to cross into "manage closely". The change in approach is real, so the log entry for it should say why.
Keeping a change log
Overwriting a rating erases the history that tells you whether your judgments were good. Keep a separate change log with one line per change:
date,group,field,old,new,reason,changed_by
2026-11-20,Local residents' association,power_1_5,2,3,"Formed coalition with two ward councillors",Community lead
2026-11-20,Local residents' association,type,public (active),public (active),"No change in stage; coalition noted",Community leadA change log gives you three things:
- Accountability. Anyone can see who changed what and on what evidence.
- Learning. After the issue ends, you can see which signals predicted a shift and which did not.
- Stability. If a rating flips back and forth, the log shows it, and you can set a rule such as "no re-rating without new evidence".
Log only changes that matter. Entries such as "no change" belong in the review date, not in the log.
Updating the engagement plan
A changed map has to reach the people who act on it. When a group changes quadrant or salience class, check each of these:
- Approach. Does the group need a different channel or frequency of contact?
- Message focus. Has the group's main concern changed? A group that moves from curious to opposed needs different messages.
- Owner and capacity. A new "manage closely" group needs a named person with time for it.
- Other groups. A change in one group often affects another. If employees move to active, the local newspaper may hear from them.
Send a short note to the team after each review cycle that lists only what changed. A full re-circulation of the register is rarely read.
Common mistakes
| Mistake | Effect | Fix |
|---|---|---|
| One review date for every row | Fast-moving groups go stale, slow ones waste time | Set `next_review` per row |
| Re-rating without new evidence | Map reflects mood, not facts | Require an `evidence` update with each change |
| No owner on a row | Nobody notices the trigger | Assign and re-check owners at each review |
| Dropping closed groups | Lose history and miss returns | Mark as "monitor" or archive, do not delete |
| Treating the threshold as exact | A group at 2.9 is handled very differently from 3.0 | Watch groups near a boundary and note why you placed them |
| Reviewing only the top stakeholders | A new active public goes unnoticed | Include a periodic sweep for groups not yet on the map |
Retire groups with care. A group can leave the map when the issue it cares about is closed, but record the date and reason. Issues recur, and a retired row saves you the effort of starting from scratch.
Exercises
Exercise
Your register has the row "Regional newspaper, influencer, interest 3, power 3, next_review 2027-03-01". On 2026-11-28 the paper runs three critical stories in one week about your company's plant expansion. Should you wait for the March review? What would you check and update?
Show answer
No. Sustained media attention is an event trigger, so review the row now. Re-check the evidence field and record the three stories. Consider raising the interest rating, since the paper is clearly more engaged. Also review the rows for groups quoted in the stories, such as the residents' association, because the coverage may move them from aware to active. Check whether any rating changes move a group across a grid quadrant. Log each change with its reason, and set a much shorter next_review date for the newspaper, for example one to two weeks.
Exercise
Using the quadrant rules from this chapter (threshold 3), a group is rated power 2 and interest 2. After a re-rating it is power 4 and interest 2. Which quadrant change does this produce, and what practical change should the team make?
Show answer
The group moves from "monitor" to "keep satisfied". The team should make sure someone owns the relationship and contacts the group on a regular schedule, even though its interest is low. Because it now has real power, ignoring it risks surprise. The team should also find out why its power rose, record that in the change log, and set a shorter review interval.