Sub topic 3
Make and Record Decisions
This chapter assumes you have worked on a team project and use a shared task board or to-do list. It covers decisions, risks, status reporting, feedback, conflict, retrospectives, and closing a project.
Make and Record Decisions
A decision log is a running list of the choices a project has made, with the reason, the owner, and the date. Keep it in one place the team can search.
| Date | Decision | Reason | Owner |
|---|---|---|---|
| 2026-12-01 | Use the existing form tool | Saves two weeks of build time | Priya |
Decide with the information you have. Set a deadline for the decision, name what would change your mind, and reopen the question only if that trigger happens.
Spot and Manage Risks Early
A risk is an event that may happen and would hurt the project. Keep a risk register with four columns: risk, likelihood, impact, and owner. Review it at each status check. For each high-likelihood or high-impact risk, name one action.
Track Progress and Report Status
Send a weekly status update with a Green, Yellow, or Red rating, the work done, the work planned, and the help you need. Report facts, such as tasks closed against tasks planned.
One-on-Ones and Feedback
Hold a 30-minute one-on-one every one or two weeks. Ask what blocks the person, then listen. Give feedback soon after the event. Describe the behavior, its effect, and the next step, then ask for the person's response.
Handle Conflict and Difficult Conversations
Address conflict within a few days, while the facts are fresh. Meet privately, describe the specific behavior and its impact, and ask for the other person's view before proposing a fix. Agree on one next step and schedule a check-back.
Run a Retrospective
At the end of each milestone, ask three questions: What went well? What did not go well? What will we change? Give each change one owner and one date. Keep the session to 45 minutes.
Close the Project and Hand Off
Confirm whether each success measure was met, and record the reason for any that were not. Transfer open tasks, documents, and access to named owners. Archive the decision log and risk register, then send stakeholders a short closing note listing what was delivered and who now owns it.
Exercise
A teammate asks why the project dropped a feature. Which record should you point to, and what should it contain?
Show answer
Point to the decision log entry for that feature. It should show the date, the decision, the reason, the owner, and any trigger that would reopen the question.