Sub topic 1
From Doer to Lead: What Changes
Prerequisites
This chapter assumes you have contributed to a team or group project and can use a basic task list or board. You should also be willing to have conversations that feel uncomfortable at first. No prior experience managing people is required.
The Role Shift
As an individual contributor, your output is the work you finish. As a lead, your output is the team's result. You still do some work, but your main jobs change. You set direction, decide what comes first, remove blockers, and keep people informed. Success now means the group reached the goal, not only that you completed your own tasks.
Define the Goal and Desired Outcome
Write one sentence that states the outcome and who benefits. "Launch a feedback form" describes an activity. "Customers can report a problem within one day of purchase" describes an outcome. An outcome gives the team a way to choose between options.
Know Your Stakeholders
A stakeholder is anyone affected by the project or able to influence it. List them, then write down what each one expects. Conflicting expectations are the earliest sign of trouble. Ask each stakeholder directly: "What would make this project a success for you?"
Set Scope and Success Measures
Scope is the boundary of the work. Write down what is in scope and what is out of scope. Success measures show whether the goal was met. Use an observable number or a clear yes or no check.
# Project Brief: Customer Feedback Form
**Goal:** Customers can report a problem within one day of purchase.
**In scope:** Web form, email confirmation, storage of responses.
**Out of scope:** Phone support, refunds.
**Success measures:** At least 30 responses in the first week.
**Stakeholders:** Product owner (approves wording), support team (handles responses).
**Lead:** Your nameBreak the Work Into Tasks
Split the goal into tasks that take a few days or less. Give each task one owner and a "done when" condition. Tasks with dependencies should show which task must finish first.
Exercise
Which is the better success measure: "users like the form" or "at least 30 responses in the first week"? Why?
Show answer
The second. It is observable and has a number, so the team can check it at the end.