Sub topic 11
Spot and Manage Risks Early
Assume you know the project goal, scope, and main tasks. This chapter focuses on uncertainty: events that might prevent the team from reaching its goal. A risk is a possible future event with an uncertain outcome. A problem is an issue that is already happening.
Find Risks Before They Become Problems
Review the project plan with the people doing the work. Ask questions such as:
- What could delay this task?
- What information, approval, or person does this depend on?
- What assumption might be wrong?
- What would make the result unusable?
- What warning would tell us that the situation is getting worse?
For a customer feedback form, the team might identify these risks:
- The product owner may take longer than expected to approve the questions.
- The form may not work with the website's mobile layout.
- Responses may not be stored correctly.
- Too few customers may complete the form.
Do not record every imaginable concern. Record risks that could change the deadline, cost, quality, security, or usefulness of the project.
Assess Probability and Impact
For each risk, estimate:
- Probability: How likely is it to happen? Use low, medium, or high.
- Impact: How serious would the result be? Consider schedule, cost, quality, and users.
- Exposure: A simple view of priority. High probability combined with high impact deserves attention first.
The estimate does not need to be precise. Its purpose is to help the team decide where to spend limited time.
| Risk | Probability | Impact | Response | Owner |
|---|---|---|---|---|
| Questions are approved late | Medium | High | Review a draft early and set a decision date | Priya |
| Mobile layout fails | Medium | Medium | Test a small prototype on common screen sizes | Sam |
| Responses are not stored | Low | High | Run an end-to-end test before release | Priya |
Choose a Response
A risk response is the action you take because the risk exists.
- Avoid: Change the plan so the risk no longer applies.
- Reduce: Lower the probability or impact. For example, test a prototype early.
- Transfer: Move responsibility to another party, such as a service provider. You still need to track the result.
- Accept: Take no preventive action when the cost of prevention is greater than the likely loss. Define what you will do if it happens.
Give each important risk one owner. The owner watches for changes and starts the agreed response. The owner does not have to solve the risk alone.
Monitor Triggers and Decisions
A trigger is an observable sign that a risk is becoming more likely or has happened. For late approval, a trigger might be “no review comments by Wednesday.” When a trigger appears, the owner acts instead of waiting for the weekly meeting.
Keep a short risk register in the project workspace. Review it at each status check. Close risks that no longer apply, update estimates when new information appears, and add decisions to the same record. A decision record should state the choice, date, reason, and person who approved it.
Practice
Use the feedback-form project. Choose one risk that could affect its deadline or usefulness. Write its probability, impact, response, owner, trigger, and next review date. Then decide what information would cause you to change the response.
Exercise
The form works technically, but the team has no evidence that customers will complete it. Is this a risk or a problem, and what could you do?
Show answer
It is a risk because low completion is a possible future outcome. Reduce it by testing the questions with a few customers, simplifying the form, and setting a trigger such as a completion rate below the agreed target.