Break the Work Into Tasks
Assume you already have a project goal, a rough scope, and a basic task list. This chapter shows how to turn that goal into work that people can estimate, assign, and track.
A task is a piece of work with one clear outcome. Good tasks are small enough that one person can finish them without creating a second project inside the first. They also have a condition that says when the work is done.
Start With the Outcome
Write the desired outcome before listing activities. For example:
> Launch a customer feedback form on the website.
Then ask:
- What must exist for this outcome to be true?
- What decisions or inputs are required?
- What must be tested before release?
- What work depends on other work?
This produces deliverables, which are concrete results such as approved questions, a working page, or a test report. Break each deliverable into tasks.
Make Tasks Trackable
Each task should have these fields:
| Field | Question it answers |
|---|---|
| Title | What work is being done? |
| Owner | Who is responsible for finishing it? |
| Done-when condition | What evidence proves it is complete? |
| Estimate | How much effort might it require? |
| Dependency | What must happen first? |
Use one owner for each task. Several people may help, but one person should be responsible for moving the task to completion.
A vague task such as “Work on the form” is difficult to estimate and report. Split it into actions with visible results:
- Draft the form questions.
- Review the questions with the product owner.
- Build the form page.
- Connect the form to test storage.
- Test submission and error handling.
- Fix release-blocking issues.
The tasks are now easier to assign and sequence.
Define “Done”
A done-when condition prevents activity from being mistaken for progress. “Design the page” is an activity. “Page layout approved in the design file” is a result.
Use observable conditions:
- “Questions reviewed and approved by the product owner.”
- “Form submits and stores responses in the test environment.”
- “No open issues that block release.”
Avoid conditions such as “mostly finished,” “looked at,” or “working well.” They leave different people with different interpretations.
goal: Launch a customer feedback form on the website
tasks:
- id: 1
title: Draft the form questions
owner: Priya
done_when: Questions reviewed and approved by the product owner
estimate_days: 1
- id: 2
title: Build the form page
owner: Sam
done_when: Form submits and stores responses in the test environment
estimate_days: 3
depends_on: [1]
- id: 3
title: Test and fix issues
owner: Priya
done_when: No open issues that block release
estimate_days: 2
depends_on: [2]Check Size and Dependencies
A task may be too large when its estimate is uncertain, its owner cannot describe the next action, or its done-when condition contains several unrelated results. Split it again.
Dependencies describe order, not importance. In the example, testing depends on the form page. If a task has many dependencies, identify the one that blocks the most work and make it explicit.
Common Errors
- Assigning a task to a group instead of one owner.
- Listing steps without saying what completion means.
- Making tasks so small that tracking them costs more than doing them.
- Ignoring dependencies until someone is blocked.
- Treating an estimate as a promise rather than a planning assumption.
Review the task list with the people doing the work. They can identify missing inputs, hidden dependencies, and estimates that do not fit the available time.
Exercise
The task “Prepare the launch” has three owners and no completion condition. What should you change first?
Show answer
Split it into tasks with separate outcomes, give each task one owner, and add a specific done-when condition. Then identify dependencies and estimate each task.