Sub topic 11
Spot and Manage Risks Early
What this chapter assumes
You have read the earlier chapters on scope, work breakdown, estimation, and decision making. You should have a project brief, a task list with owners and estimates, and a rough idea of who your stakeholders are. This chapter uses those artifacts as inputs. Risk work is mostly a way of reading them critically.
Risks, issues, and assumptions
A risk is something that might happen and would affect the project if it did. An issue is a risk that has already happened. An assumption is something you are treating as true without having checked it.
Keeping these three apart changes what you do:
| Term | Has it happened? | Your response |
|---|---|---|
| Risk | Not yet, it is uncertain | Decide whether to prevent it, reduce it, or prepare for it |
| Issue | Yes | Fix it now, and escalate if you cannot |
| Assumption | Unknown | Check it, or record it as a risk if you cannot check it |
Many first-time leads treat every worry as an issue. They fire-fight and never get ahead. Others write a long list of vague worries and never act on any of them. A useful risk practice sits between these: a short list, reviewed often, with an action on every item.
Where risks come from
You do not need a formal method to find risks. Walk through the artifacts you already have and ask one question at each.
- Goal and scope: What would make us build the wrong thing? Is any success measure outside our control?
- Stakeholders: Who could change their mind late? Who has not yet seen the plan?
- Tasks and dependencies: Which task, if late, delays three others? Which tasks have a
depends_onchain longer than two links? - Estimates: Which estimates are guesses about unfamiliar work? These are your widest ranges.
- People: Does only one person know how to do a critical task? Is anyone on leave, shared with another project, or new to the work?
- External factors: Do we wait on another team, a vendor, an approval, or a purchase?
The task list from the work-breakdown chapter is the best source. Look at this fragment:
tasks:
- id: 2
title: Build the form page
owner: Sam
estimate_days: 3
depends_on: [1]
- id: 3
title: Test and fix issues
owner: Priya
estimate_days: 2
depends_on: [2]Several risks are visible without any extra information. Sam is the only owner of the build, so illness stops the project. Task 3 cannot start until task 2 ends, so any slip in the build moves the release date by the same amount. Two days of testing and fixing is a guess if nobody has tested a form like this before. Each of these becomes a line in your risk list.
A quick technique: the pre-mortem
A pre-mortem is a short team exercise. You say, "Imagine it is the deadline and the project failed. Why?" Everyone writes down reasons for a few minutes, then you group them. It works because people who would feel awkward raising a worry in a planning meeting find it easy to answer a hypothetical failure. It also draws on what the team knows and you do not. This depends on the trust you built earlier, so if people stay silent, treat that silence as information about safety and not as proof that nothing is wrong.
Rate each risk
You need enough rating to decide what to work on first, and no more. For each risk, estimate two things:
- Likelihood: how probable it is. Low, medium, or high is enough.
- Impact: how much it would hurt the deadline, budget, quality, or a stakeholder's outcome if it happened.
Then sort. High likelihood and high impact come first. Low and low can stay on the list, or come off it, without an action.
Avoid false precision. A score such as "37%" for a risk you have never seen before hides how little you know. Low, medium, and high, plus a sentence of reasoning, is more honest and easier to challenge.
Watch for hidden high-impact risks
Some risks look unlikely but would end the project. Examples include losing the only person who holds key knowledge, or a stakeholder with veto power who has not been consulted. Rate these by impact first. A rare event with a severe result still deserves a plan.
Choose a response
Every risk you decide to act on gets one of four responses.
| Response | What it means | Example |
|---|---|---|
| Avoid | Change the plan so the risk cannot occur | Drop a feature that depends on an unproven tool |
| Reduce | Lower the likelihood or the impact | Ask Priya to review Sam's work early, so a second person understands it |
| Transfer | Move the consequence to someone better placed to carry it | Use a supported service instead of building and maintaining your own |
| Accept | Do nothing now, knowingly | A low-impact delay in a non-critical task |
Accepting is a legitimate choice, but it must be explicit. "We accept this risk" written in the log is a decision. Ignoring it is neglect. Record accepted risks as decisions using the method from the previous chapter, so you can explain later why you did not act.
Also decide on a trigger, an observable sign that a risk is becoming real. For "the vendor may deliver late," a trigger might be "no confirmed delivery date by Friday." A trigger turns a vague worry into something you can check at a regular meeting. It also tells you when to start the backup plan.
Keep a lightweight risk log
A risk log can be a table in a shared document. Each row needs an owner, because a risk with no owner is not managed by anyone. The owner does not have to fix the risk alone. They are responsible for watching it and raising it.
## Risk log
| ID | Risk | Likelihood | Impact | Response | Action and owner | Trigger | Status |
| --- | --- | --- | --- | --- | --- | --- | --- |
| R1 | Sam is the only person who can build the form page | Medium | High | Reduce | Priya pairs with Sam for one hour on day 1 (Priya) | Sam unavailable for 2+ days | Open |
| R2 | Product owner changes the questions after the build starts | Medium | Medium | Reduce | Get written approval before task 2 starts (Lead) | Request for new questions after approval | Open |
| R3 | Testing finds more issues than 2 days can fix | Medium | Medium | Accept | Add 1 day of buffer before the release date (Lead) | More than 5 blocking issues on day 1 of testing | Open |Keep the log short. Five to ten live risks is manageable for a small project. If you have thirty, you are tracking worries and not managing risks, so merge duplicates and close the ones that no longer matter.
Buffers
A buffer is time you add on purpose to absorb the uncertainty you cannot remove. Place it at the end of a chain of dependent tasks, or before a fixed deadline, rather than padding every estimate. Padding every task hides the real estimate, and people tend to use all the time they are given. Say openly that the buffer exists and what it is for. Then you can show stakeholders when it is being used.
Review risks on a rhythm
A risk log that is written once and never opened is a common failure. Tie it to meetings you already have.
- In your weekly check-in, spend five minutes on the log.
- For each open risk, ask: has the trigger fired, has the likelihood or impact changed, and is the action done?
- Add new risks raised by the team. Close risks that have passed or been dealt with.
- Move anything that crossed a trigger into the weekly status update, under "Risks and blockers," with the action or owner.
This links the risk log to the status report from the communication chapters. Stakeholders should not first learn about a risk when it becomes an issue.
Common errors
- Listing risks without owners or actions. The list looks thorough and changes nothing.
- Hiding risks to look in control. Bad news that arrives early can be handled. Bad news that arrives at the deadline cannot. Make it normal to say "this might go wrong" in your team.
- Treating the plan as a promise. If the plan has no room for surprises, the first surprise becomes a crisis.
- Confusing risks with tasks. "Write the test plan" is a task. "The test plan may miss important cases" is a risk.
- Never closing risks. An old list teaches people to ignore it.
- Carrying risks you cannot influence. If you cannot act on a risk, such as a decision by senior leadership, tell the person who can, and then record that you did.
When to escalate
You will meet risks that are beyond your authority, such as a budget cut, a conflict with another team's priorities, or a need for another person. Escalate early and with a specific request. State the risk, the impact on the goal, what you have already tried, and what decision or help you need and by when. A message like "I need a decision by Thursday on whether to extend the deadline or reduce scope" can be acted on. A message like "the project is struggling" cannot.
Exercise
A project has three tasks in a chain: design (2 days), build (4 days), and review (1 day). The build is owned by one person who has never used the required tool, and the deadline is fixed. Write one risk for this project in a single sentence. Then give its likelihood, impact, a response from avoid, reduce, transfer, or accept, and one trigger.
Show answer
A sample answer: "The build may take longer than 4 days because the owner has not used the tool before." Likelihood: high. Impact: high, because the chain is sequential and the deadline is fixed. Response: reduce, for example by having the owner do a half-day trial with the tool before design ends, and by adding a one-day buffer after the build. Trigger: the trial is not finished, or shows a basic task taking more than a day, by the end of the design task. Other reasonable answers exist, such as avoid (choose a tool the owner knows) or transfer (ask an experienced colleague to build it). The answer must name an owner of the risk, a response that matches its rating, and a trigger that can be observed.
Exercise
Your risk log has 25 open items, and the team has stopped looking at it. What two steps would you take at the next check-in?
Show answer
First, merge duplicates and close items that have passed, are no longer relevant, or that you accepted and have no trigger for, so that 5 to 10 live risks remain. Second, make sure each remaining risk has an owner, an action, and a trigger, and add a standing five-minute review slot to the weekly check-in so the log is used again.