Know Your Stakeholders
This chapter assumes you have worked on a team project, you can read a simple task board, and you have already drafted a project goal (the previous chapter). By the end you will be able to find the people who affect or are affected by your project, learn what each of them expects, and plan how to keep each one informed.
What a stakeholder is
A stakeholder is anyone who can affect your project or who will be affected by its result. Your team members are stakeholders. So are the person who asked for the work, the people who will use the result, and the people who must approve, fund, or support it.
Stakeholders matter because most small projects fail in a quiet way. The work gets done, but someone who needed to be consulted was missed, or someone expected something different. You find out at the end, when changing course is expensive. A short stakeholder review at the start moves that discovery to a time when it is cheap.
Common stakeholder roles
Not every project has all of these. Use the list as prompts for finding people you have not yet thought of.
| Role | What they care about | Example |
|---|---|---|
| Sponsor | Whether the outcome is worth the cost. Often holds the budget or the final say. | The manager who asked you to lead the project |
| Users | Whether the result makes their work easier. | The support staff who will use a new form |
| Contributors | A clear task, a fair workload, and enough time. | Your teammates |
| Approvers | That rules, quality, or security standards are met. | A legal reviewer, a security team |
| Dependencies | Whether you will need their time or output, and when. | The team that manages the test environment |
| Affected bystanders | Whether your change disrupts what they already do. | Staff whose reporting process will change |
Find them
Do this as a short working session, ideally with your sponsor and one or two teammates. Three questions surface most stakeholders:
- Who asked for this, and who must say yes before it is released?
- Who will use the result, or have their work changed by it?
- Whose time, access, or output do we need to finish?
Then ask each person you find one more question: "Who else should I talk to?" People close to the work often name someone you had missed.
Learn what they expect
A list of names is not enough. For each stakeholder, write down three things:
- What they need from the project. Be specific. "Wants fewer manual entries" is useful. "Wants it to be good" is not.
- How much influence they have. Can they stop the project, change the scope, or only give an opinion?
- How much they are affected. Will the result change their daily work a lot or a little?
Ask them directly. A 15-minute conversation with open questions works well:
- What would a good result look like for you?
- What worries you about this project?
- What has gone wrong on similar work before?
- How would you like to hear about progress, and how often?
Take notes, then repeat back what you heard. "So the main thing is that the form works on mobile, and you want a heads-up before anything goes live. Is that right?" This catches misunderstandings while they are still small.
Sort them to plan your effort
You cannot give everyone the same attention. A common method is a two-by-two grid of influence and impact. Place each stakeholder in one cell and use the cell to choose an approach.
| Row | Low impact on them | High impact on them |
|---|---|---|
| High influence | Keep satisfied: brief updates, and consult before big decisions | Manage closely: involve early and often, ask for input, confirm decisions with them |
| Low influence | Monitor: share major milestones only | Keep informed: regular updates, and a way to ask questions or raise concerns |
The grid is a planning aid, and people move between cells. A user with low influence can become a loud critic if surprised by a change. An approver who seemed distant may become central when a risk appears. Review the grid whenever scope changes.
Record it in one table
Keep the result in a small stakeholder register. It can live in a document or a spreadsheet. Here is a format as a YAML sketch using the feedback-form project from the task example:
project: Customer feedback form
stakeholders:
- name: Dana
role: Product owner (sponsor)
needs: Questions that produce data she can act on
influence: high
impact: high
approach: Manage closely
updates: Weekly written update, plus approval of the question list
- name: Support team
role: Users of the response data
needs: Responses in a format they can filter by topic
influence: low
impact: high
approach: Keep informed
updates: Short demo before release, a contact for questions
- name: Security reviewer
role: Approver
needs: Confirmation that responses are stored safely
influence: high
impact: low
approach: Keep satisfied
updates: Early review request, then sign-off before releaseNotice that the register ties directly to the project brief. The "Stakeholders" section of the brief can be a short version of this list, and each stakeholder's needs feed the success measures you set in the next chapter.
Common errors
- Listing only the people you already know. Teammates and your sponsor are easy to name. The approver, the support team, and the owner of a dependency are the ones most often forgotten. Use the three discovery questions to find them.
- Treating the sponsor as the only voice. The sponsor may speak for the project's value, but not for what users do day to day. Talk to users directly.
- Confusing a request with a need. A stakeholder asks for "a dashboard." The need may be "know by Monday which orders are late." Ask what the request is for before you commit to it.
- Promising everything. Stakeholders will have conflicting wishes. You do not have to satisfy all of them, but you do have to be honest about trade-offs. Say what you can do, what you cannot, and why.
- Collecting needs once and never again. Expectations shift as the project does. Check in at the points where scope or schedule change.
- Skipping hard conversations. A stakeholder who is skeptical or opposed is useful information. Meet them early, listen, and find out what would change their mind or what they need to feel safe.
When stakeholders conflict
Sometimes two stakeholders want incompatible things. Sales wants the form to ask ten questions. Support wants three, because long forms lower completion. Try this sequence:
- Restate each need in terms of its purpose, not its solution.
- Check whether the project goal and success measures favor one side.
- Offer options, such as a short form now and an optional follow-up later.
- If they still disagree, bring it to your sponsor with the options and your recommendation, and record the decision.
Do not settle the matter by quietly choosing the stakeholder you like best.
Summary of the practice
- List stakeholders with the three discovery questions, and ask each person who else to include.
- Interview each one briefly and repeat back what you heard.
- Record needs, influence, and impact in a short register.
- Choose an approach and an update frequency for each group.
- Revisit the register when scope, schedule, or people change.
Exercise
You are leading a project to replace a paper sign-in sheet at a front desk with a tablet app. Name four stakeholders, say what each one probably needs, and assign each one an approach from the influence and impact grid (manage closely, keep satisfied, keep informed, monitor).
Show answer
A sample answer. (1) The office manager, who sponsors the project: needs a lower-effort way to track visitors and a short rollout. High influence, high impact: manage closely. (2) Front desk staff, who use the tablet every day: need it to be fast and to work when the network is slow. Lower influence, high impact: keep informed, and involve a few of them in testing. (3) The IT or security team, who approve new devices and data storage: need confirmation that visitor names are stored securely. High influence, lower direct impact: keep satisfied, with an early review request. (4) Visitors, who sign in: need a quick process. Low influence, moderate impact: monitor, and collect feedback at the desk. Other valid answers include the building security team and the legal or privacy officer. The key points are that each stakeholder has a specific need and that the approach matches their influence and impact.
Exercise
A stakeholder tells you, "I need a weekly report emailed to me every Friday." What question should you ask before adding it to the project, and why?
Show answer
Ask what the report is for, for example, "What decision will you make with it?" The request is a solution, and the underlying need may be met in a simpler way, such as a shared dashboard or a short note covering only the numbers they act on. Asking also shows whether the work belongs inside the project's scope or is a separate request.