Sub topic 8
Variable consideration and the constraint
This chapter assumes you know the five-step model and how to find the transaction price in a fixed-price contract. It covers the part of step 3 where the price is not a fixed number.
What variable consideration is
Variable consideration is any part of the price that can change depending on a future event. Common sources are:
- Discounts, rebates and volume incentives.
- Refunds, credits and price concessions.
- Performance bonuses and penalties.
- Rights of return.
The variability can be written into the contract. It can also come from your own practice. If you have a history of giving customers price concessions, the price is variable even though the contract states a fixed amount.
Step 1: Estimate the amount
Pick the method that better predicts the amount you will be entitled to. Use one method consistently for the whole contract.
| Method | Best when | How it works |
|---|---|---|
| Expected value | You have many contracts with similar characteristics | Sum of each possible amount times its probability |
| Most likely amount | The outcome is binary or has few results | The single most probable amount |
from decimal import Decimal
fixed_fee = Decimal("200000")
# (probability, bonus amount) for each possible outcome
outcomes = [
(Decimal("0.20"), Decimal("0")),
(Decimal("0.50"), Decimal("10000")),
(Decimal("0.30"), Decimal("20000")),
]
assert sum(p for p, _ in outcomes) == Decimal("1")
expected_bonus = sum(p * amount for p, amount in outcomes)
most_likely_bonus = max(outcomes, key=lambda o: o[0])[1]
print("Expected value:", expected_bonus)
print("Most likely amount:", most_likely_bonus)
print("Unconstrained price (expected value):", fixed_fee + expected_bonus)The expected value is 11,000.00 and the most likely amount is 10,000. The two methods give different estimates, so choose the one that fits the contract. Do not choose the one that gives the answer you want.
Step 2: Apply the constraint
The estimate is not yet the transaction price. The constraint limits the amount you include. You include variable consideration only to the extent that a significant reversal of cumulative revenue is unlikely when the uncertainty resolves.
The threshold wording differs between the two standards:
- ASC 606 says a significant reversal must not be probable.
- IFRS 15 says a significant reversal must not be highly probable.
In practice the two usually give similar answers, but the IFRS wording is closer to "very likely".
Factors that raise the risk of a reversal include:
- The amount depends on things outside your control, such as market prices or the customer's behavior.
- The uncertainty will last a long time.
- You have little experience with similar contracts.
- You have a history of price concessions.
- The range of possible outcomes is wide.
Suppose the entity above concludes that a reversal is unlikely only for a bonus of 10,000 or less. The transaction price is then 200,000 + 10,000 = 210,000. This is lower than the 211,000 estimate. The 1,000 difference is the amount the constraint removed.
Common errors
- Skipping the constraint. Estimating the amount is only half the job. Always test the estimate against the reversal criterion.
- Constraining the whole contract. The constraint applies to the variable amount. The fixed fee is not constrained.
- Estimating once. You update the estimate and the constraint at every reporting date. Changes in the price are covered in a later chapter.
- Forgetting the refund liability. If you expect to refund part of what you collect, you record a refund liability and do not recognize revenue for that part.
- Applying this to sales-based royalties on licenses of intellectual property. These have a separate exception. You recognize them only when the later sale happens, so you do not estimate them.
Exercise
A contractor has a fixed fee of 500,000 and a 40,000 bonus for finishing early. The outcome is binary, with a 70% chance of earning the bonus. Management judges that a significant reversal of revenue is not probable only if the bonus is excluded. Which method estimates the bonus, and what is the transaction price?
Show answer
The outcome is binary, so the most likely amount (40,000) is the better estimate, since expected value would give 28,000, which is an amount that cannot actually occur. The constraint then removes the bonus because a significant reversal is probable if it is included. The transaction price is 500,000. The bonus is added when the uncertainty resolves or the constraint no longer applies.