Allocating the price in proportion to relative standalone selling prices
This chapter assumes you can already list a contract's performance obligations and have determined the transaction price. It also assumes you know what a standalone selling price (SSP) is: the price at which the entity would sell a promised good or service separately to a customer.
Why allocation is needed
When a contract has more than one performance obligation, each one needs its own share of the price. Revenue is recognized for each obligation when or as it is satisfied, and the timing often differs. A software license may be satisfied on delivery. Support is satisfied over a year. Allocation is step 4 of the five-step model.
The default method in ASC 606 and IFRS 15 is relative SSP allocation. Each obligation receives a share of the transaction price equal to its SSP divided by the total of all the SSPs.
The calculation
- Determine the SSP of each performance obligation.
- Add the SSPs to get the total.
- Multiply the transaction price by each SSP and divide by the total.
A bundle sells for $100,000. The standalone prices are $60,000 for a license, $30,000 for implementation and $30,000 for support. They total $120,000, so the customer receives a $20,000 discount for buying the bundle.
| Obligation | SSP | Share of total SSP | Allocated price |
|---|---|---|---|
| License | $60,000 | 50% | $50,000 |
| Implementation | $30,000 | 25% | $25,000 |
| Support | $30,000 | 25% | $25,000 |
| Total | $120,000 | 100% | $100,000 |
Each obligation absorbs the discount in proportion to its SSP. Here that is about 16.7% off each item.
The calculation in code
The function below rounds each amount to cents. The last obligation takes the remainder, so the allocated amounts always sum exactly to the price.
from decimal import Decimal, ROUND_HALF_UP
def allocate_relative_ssp(price, ssps):
"""Allocate a transaction price in proportion to standalone selling prices."""
total_ssp = sum(ssps.values())
names = list(ssps)
allocated = {}
running = Decimal("0")
for name in names[:-1]:
amount = (price * ssps[name] / total_ssp).quantize(
Decimal("0.01"), rounding=ROUND_HALF_UP
)
allocated[name] = amount
running += amount
# The last obligation takes the remainder so the allocations sum exactly to the price.
allocated[names[-1]] = price - running
return allocated
price = Decimal("100000")
ssps = {
"license": Decimal("60000"),
"implementation": Decimal("30000"),
"support": Decimal("30000"),
}
print(allocate_relative_ssp(price, ssps))The output is 50000.00, 25000.00 and 25000.00.
Common errors
- Allocating by contract list prices. The basis is the SSP, not whatever price appears on the quote. List prices work only if they are also the observable standalone prices.
- Allocating the price to the wrong set of obligations. Only separate performance obligations receive an allocation. Promises that are not distinct are combined first, and the combined obligation gets one SSP.
- Updating SSPs after inception. Allocation uses the SSPs at contract inception. Later changes in SSPs do not cause a reallocation.
- Ignoring the price used. The amount allocated is the transaction price, which already reflects variable consideration after the constraint. Allocating the stated contract price can give the wrong total.
- Forgetting the exceptions. A discount or variable amount that clearly relates to only some obligations may be allocated to them directly. The next chapters cover both cases.
Exercise
A contract with a $90,000 price has two performance obligations. Product A has an SSP of $70,000 and Product B has an SSP of $50,000. How much is allocated to each?
Show answer
The total SSP is $120,000. Product A gets 90,000 × 70,000 / 120,000 = $52,500. Product B gets 90,000 × 50,000 / 120,000 = $37,500. The two amounts add up to $90,000.