Sub topic 10
Brownfield: converting the existing system
This chapter assumes you know the basics of SAP ERP modules, the development, quality, and production landscape, and the difference between custom ABAP code and master and transactional data. It also assumes you have read the overview of the three paths.
What a system conversion is
A brownfield approach, which SAP calls a system conversion, upgrades your existing ECC system in place. The result is an S/4HANA system that keeps your configuration, custom code, master data, and transactional data. You do not rebuild processes. You change the technical foundation and adapt what no longer fits.
The conversion is done once per system in the landscape. Teams usually convert a sandbox copy first, then development, quality, and finally production.
The tools
Three SAP tools carry most of the work:
| Tool | Purpose |
|---|---|
| Readiness Check and Simplification Item Check | Finds items in your system that S/4HANA changes or removes |
| Software Update Manager (SUM) with Database Migration Option (DMO) | Updates the software and, if needed, migrates the database to SAP HANA in one run |
| ABAP Test Cockpit (ATC) with the S/4HANA checks | Finds custom code that breaks or needs adjustment |
The conversion flow
- Analyze. Run the readiness check and the simplification item check. Each simplification item tells you what changes and what you must do before or after conversion.
- Prepare. Complete pre-conversion tasks in the source system. A typical one is converting customers and vendors to Business Partner, which S/4HANA requires. You also confirm that your add-ons and industry solutions are supported.
- Convert. SUM updates the software, and DMO moves the database to HANA. Data in tables is converted, for example finance data moves into the Universal Journal.
- Adapt. Fix custom code flagged by ATC, adjust interfaces, and apply the follow-on configuration the simplification items call for.
- Test and cut over. Run regression tests on business processes, then plan the production downtime window.
Strengths and limits
Strengths:
- Existing processes and data stay, so business disruption is lower.
- Full history is kept without a separate migration.
- Effort is often lower than a new implementation when the system is in good shape.
Limits:
- You carry over old design decisions, poor data quality, and unused custom code.
- The source system must meet technical prerequisites, such as a supported Unicode setup and a compatible starting release.
- Downtime is a single window for the whole production conversion, and the process is hard to reverse once started.
- Redesigning processes to use new S/4HANA features is optional and often postponed.
Common errors
- Starting the conversion without running the simplification item check early enough, so blocking items appear late.
- Treating custom code adaptation as an afterthought. Run ATC checks against an S/4HANA target early.
- Skipping a full rehearsal on a production-sized copy, which hides the real downtime.
- Leaving Business Partner conversion to the end.
Exercise
A company has a stable ECC system with well-fitting processes, a lot of useful custom code, and a need to keep ten years of history. Which tool finds the custom code that must change, and why is brownfield a reasonable fit?
Show answer
The ABAP Test Cockpit with the S/4HANA readiness checks finds the custom code that needs adjustment. Brownfield fits because it keeps the existing processes, custom code, and full history, so there is no need to rebuild or migrate data separately.
Exercise
Why should you rehearse the conversion on a copy of production before the real cutover?
Show answer
A rehearsal shows the real downtime and exposes technical and data problems. Without it, the production window is an estimate and the risk of overrunning it is high.