Sub topic 7
Total float and free float
This chapter assumes you can run the forward and backward passes from the previous two chapters. It also assumes finish-to-start dependencies with no lags. Durations are in working days. By the end you should be able to calculate both kinds of float, explain why they differ, and say how much an activity can slip before it hurts something.
What float measures
An activity has float when it can start later, or take longer, than planned without causing a problem. The two kinds of float differ in what counts as the problem.
- Total float is the time an activity can be delayed without delaying the project finish date (or a imposed deadline).
- Free float is the time an activity can be delayed without delaying the earliest start of any immediate successor.
Total float answers "will the project finish late?" Free float answers "will I disturb the next team's plan?" Free float is the stricter measure, so it is never larger than total float.
Total float
Total float comes straight from the two passes. For any activity:
- Total float = latest start − earliest start
- Total float = latest finish − earliest finish
The two formulas always give the same number, because the duration cancels out. Use whichever pair of values you have in front of you. Many people compute both as a check.
The sign and size of the result tell you the activity's status:
| Total float | Meaning |
|---|---|
| Greater than 0 | The activity can slip by that amount without moving the finish date. |
| Exactly 0 | The activity is critical. Any slip moves the finish date. |
| Less than 0 | The schedule cannot meet the target date. The activity is already late relative to the constraint. |
Negative float appears when you impose a deadline earlier than the forward pass result. If the forward pass gives 11 days and the sponsor requires 9, you start the backward pass with a latest finish of 9 for the last activity. Every activity on the longest path then has total float of −2. The number tells you how much the plan must be compressed, which leads into the schedule compression chapter.
Free float
Free float looks forward only one step. For an activity with successors:
- Free float = (earliest start of the earliest-starting successor) − (earliest finish of this activity)
In other words, take the smallest earliest start among all immediate successors and subtract this activity's earliest finish. If the activity has no successors, use the project end date in place of the successor start.
Free float does not need the backward pass at all. It uses only forward pass values. That is a useful check on your understanding: you can calculate it before you know any latest dates.
Why the two differ: a worked network
Consider five activities:
| Activity | Duration | Predecessors |
|---|---|---|
| A | 3 | none |
| B | 2 | A |
| C | 1 | B |
| D | 6 | A |
| E | 2 | C, D |
The forward pass gives these earliest dates:
| Activity | ES | EF |
|---|---|---|
| A | 0 | 3 |
| B | 3 | 5 |
| C | 5 | 6 |
| D | 3 | 9 |
| E | 9 | 11 |
E starts at 9 because it waits for the later of C (finishing at 6) and D (finishing at 9). The project takes 11 days. The backward pass starts with E's latest finish of 11 and works back:
| Activity | LS | LF | Total float | Free float |
|---|---|---|---|---|
| A | 0 | 3 | 0 | 0 |
| B | 6 | 8 | 3 | 0 |
| C | 8 | 9 | 3 | 3 |
| D | 3 | 9 | 0 | 0 |
| E | 9 | 11 | 0 | 0 |
Both B and C show total float of 3, but their free float differs. B's only successor is C, which starts at day 5. B finishes at day 5. So B's free float is 5 − 5 = 0. C's only successor is E, which starts at day 9, and C finishes at day 6, so C's free float is 9 − 6 = 3.
Float is shared along a path
B and C sit on the same non-critical path, A → B → C → E. That path is 8 days long against the critical 11, so the path as a whole has 3 days of slack. B and C do not each own 3 days. They share one pool of 3 days.
Suppose B takes 3 extra days. B finishes at day 8, C starts at day 8 and finishes at day 9, and E still starts at day 9. The project holds, but the path's float is now used up. C's total float has dropped from 3 to 0, even though nobody touched C.
Free float shows where the pool can be spent without side effects. B has free float 0, so any delay to B immediately eats into C's float. C has free float 3, so C can use all of it without affecting anything else.
Computing both in code
The code below extends the forward and backward pass approach from the chapter on computing the critical path. Tasks are listed so that predecessors come first.
tasks = {
# name: (duration in days, predecessors)
"A": (3, []),
"B": (2, ["A"]),
"C": (1, ["B"]),
"D": (6, ["A"]),
"E": (2, ["C", "D"]),
}
# Forward pass
es, ef = {}, {}
for t, (dur, preds) in tasks.items():
es[t] = max((ef[p] for p in preds), default=0)
ef[t] = es[t] + dur
project_end = max(ef.values())
# Successor lookup
succs = {t: [] for t in tasks}
for t, (dur, preds) in tasks.items():
for p in preds:
succs[p].append(t)
# Backward pass
ls, lf = {}, {}
for t in reversed(list(tasks)):
lf[t] = min((ls[s] for s in succs[t]), default=project_end)
ls[t] = lf[t] - tasks[t][0]
total_float = {t: ls[t] - es[t] for t in tasks}
free_float = {
t: min((es[s] for s in succs[t]), default=project_end) - ef[t]
for t in tasks
}
print(total_float) # {'A': 0, 'B': 3, 'C': 3, 'D': 0, 'E': 0}
print(free_float) # {'A': 0, 'B': 0, 'C': 3, 'D': 0, 'E': 0}The only new line compared with the critical path code is the free float expression. It uses es of successors, not ls, which is why it needs no backward pass. To model a deadline, replace project_end in the backward pass with the deadline value. Total float then goes negative where the plan cannot meet it, while free float is unchanged.
Reading float for decisions
Float is most useful when you know which question you are asking.
- Can this task slip without moving the finish date? Check total float. If the slip is no larger than the total float, the finish date holds, though other activities on the path may lose float.
- Can this task slip without changing anyone else's start? Check free float. Within the free float, no successor is affected at all, so you can agree the slip without replanning.
- Where should I watch closely? Activities with zero total float come first. After those, look at activities whose total float is small relative to the uncertainty in their duration.
- Where can I move people? Resources on activities with large free float can be borrowed with the least coordination cost.
Common errors
- Using free float where total float is needed. An activity with free float 0 can still have a lot of total float, as B does above. Treating it as critical would overstate the risk.
- Using total float where free float is needed. Telling the team owning C "you have 3 days" is only true if B has not already used them.
- Forgetting the end-of-network case. An activity with no successors takes its free float from the project end date. Leaving it blank or zero hides real slack, or produces an error in code.
- Reading float from a calendar-day view. Float is counted in working time on the activity's calendar. If the successor works different days, count carefully and confirm what your scheduling tool reports.
- Ignoring negative float. A schedule with negative float is not a schedule that "has float problems". It cannot meet its constraint as planned.
- Assuming float is permanent. Float is a result of the current durations and logic. Change either and the values change, as covered in the chapter on keeping the critical path current.
Summary table
| Property | Total float | Free float |
|---|---|---|
| Question answered | Does the project finish date move? | Does any successor's earliest start move? |
| Formula | LS − ES (or LF − EF) | min(successor ES) − EF |
| Needs backward pass | Yes | No |
| Can be negative | Yes, with a binding deadline | Not in a valid forward pass |
| Shared with others on the path | Yes | No, by definition |
| Relationship | Free float ≤ total float |
Exercise
In the worked network, B takes 2 extra days (4 days instead of 2). What are B's new finish, C's new earliest start, and C's new total float and free float? Does the project finish date change?
Show answer
B now runs from day 3 to day 7. C's earliest start moves from 5 to 7, so C's earliest finish is 8. C's latest start and finish are unchanged (LS 8, LF 9), so its total float is 8 − 7 = 1. Its free float is E's earliest start minus C's earliest finish, 9 − 8 = 1. The project finish date stays at 11 because the path A, B, C, E is now 3 + 4 + 1 + 2 = 10 days, still shorter than the critical path of 11.
Exercise
Explain why free float can never be greater than total float for the same activity.
Show answer
Delaying an activity by more than its free float pushes back at least one successor's earliest start. Delaying it by no more than its total float keeps the project finish date intact. Any delay that leaves all successors untouched also cannot move the finish date, so the free float amount is always safe for the finish date. The total float is therefore at least as large as the free float. The two are equal when the delay can be absorbed only by the end of the path, as with C above.