01Chapter 1: Modelling a project as an activity networkA critical path calculation starts from a model of the project, not from a calendar. This chapter shows how to turn a task list into an activity network: a set of activities, their durations, and the dependencies between them. Every later calculation in this tutorial (forward pass, backward pass, fl6 min read
02Chapter 2: Activity durations and what they assumeEvery critical path calculation starts from one number per activity: its duration. The forward and backward passes are plain arithmetic, so they are only as good as those inputs. This chapter covers what a duration means, how it differs from related quantities, and which assumptions are built into i6 min read
03Chapter 3: Paths through the network and their lengthsThis chapter assumes you can read a task list with durations and predecessors, and that you know the terms task, duration, milestone, and dependency. The code uses basic Python (dictionaries, loops, functions). It does not need the forward or backward pass, which come in later chapters.5 min read
04Chapter 4: Checking the network before you calculateThis chapter assumes you can describe a project as tasks with durations and predecessors, and that you know what the forward and backward passes compute. The code uses basic Python: dictionaries, loops, and functions. Here you learn to test the network for structural faults before you run any pass.6 min read
05Chapter 5: The forward pass: earliest start and finishThis chapter assumes you can read a task list with durations and predecessors. It also assumes you know what a dependency is and can do day arithmetic. The code uses Python dictionaries and loops. The chapter shows how to compute the earliest time each activity can start and finish, and how those ti7 min read
06Chapter 6: The backward pass: latest start and finishThis chapter assumes you can already run a forward pass. You know that earliest finish (EF) equals earliest start (ES) plus duration, and that a task's ES is the largest EF among its predecessors. You should also be comfortable reading a predecessor table. The Python examples use only dictionaries, 6 min read
07Chapter 7: Total float and free floatThis chapter assumes you can run the forward and backward passes from the previous two chapters. It also assumes finish-to-start dependencies with no lags. Durations are in working days. By the end you should be able to calculate both kinds of float, explain why they differ, and say how much an acti6 min read
08Chapter 8: Reading the critical path from zero floatThis chapter assumes you can run a forward and backward pass and that you know total float and free float. You need to be comfortable with early and late dates in days. The code uses basic Python.6 min read
09Chapter 9: Multiple critical paths and near-critical pathsThe previous chapters showed how to find the critical path from zero float. This chapter covers two cases that the single-path picture hides. In the first, several paths are critical at once. In the second, a path that is not critical sits a day or two behind and can overtake the critical path after6 min read
10Chapter 10: Dependency types, leads, and lagsThis chapter assumes you can run a forward and backward pass on a finish-to-start network and compute total float. Earlier chapters covered both. Here you change the rules for how one activity constrains another, and see what that does to the critical path.6 min read
11Chapter 11: Shortening the schedule: crashing and fast-trackingThis chapter assumes you can run a forward and backward pass, compute total float, and read the critical path from the zero-float activities. It also assumes you know the example network from earlier chapters: A (3 days), B (2 days), C (4 days) and D (3 days). A leads to B and C, and both B and C le6 min read
12Chapter 12: Uncertain durations and three-point estimatesThis chapter assumes you can run a forward and backward pass, calculate float, and read the critical path from zero-float activities. The code uses basic Python (dictionaries, loops, functions). Here you replace single-number durations with ranges. You will learn what that does to the critical path 6 min read
13Chapter 13: When resources break the critical pathThis chapter assumes you can run the forward and backward passes, calculate total float, and read the critical path from zero-float activities. The code example uses basic Python (dictionaries, loops, functions).5 min read
14Chapter 14: Keeping the critical path current during executionThis chapter assumes you can run the forward and backward passes, compute total float, and read a critical path from zero-float activities. The code example uses basic Python (dictionaries, loops). The critical path you calculated at planning time is a forecast. Once work starts, durations change, t6 min read
15Chapter 15: Computing the critical path in codeThis chapter turns the forward pass, backward pass and float rules from earlier chapters into a small, reusable Python program. It assumes you can already do those calculations by hand. It also assumes basic Python: dictionaries, loops, functions and exceptions.5 min read