Sub topic 11
Lead Times and Building a Sourcing Timeline
Working assumptions
This chapter assumes you can read a tech pack, distinguish common fabric types, and convert between meters and yards. It also assumes you understand that a fabric specification must be confirmed with a supplier before ordering.
A lead time is the time between placing an order and receiving the goods. The quoted lead time may apply only to one stage, such as fabric production. It may not include sampling, testing, freight, customs, or inspection.
Build your timeline from the date the fabric must arrive at the cut-and-sew factory. Work backward, then add time for risks.
The sourcing sequence
A typical fabric order moves through these stages:
| Stage | What happens | Main dependency |
|---|---|---|
| Supplier response | The supplier confirms availability, price, MOQ, and dates | Complete fabric specification |
| Swatches | Small pieces are sent for color and hand evaluation | Supplier has matching stock or can cut samples |
| Sample yardage | Enough fabric is sent for a garment sample or test | Swatch approval and payment |
| Testing | Shrinkage, colorfastness, pilling, or performance tests are run | Representative sample |
| Bulk production | The supplier reserves stock or makes the fabric | Approved specification, deposit, and quantity |
| Freight and receiving | Fabric is shipped, inspected, and delivered | Export documents and transport capacity |
Some stages can overlap. For example, you can request freight estimates while testing sample yardage. Do not overlap stages that depend on approval. Bulk production should not begin until the fabric specification, color, quantity, and quality requirements are written and approved.
Building the timeline
Start with the required delivery date. Record each task, its duration, its owner, and its dependency. Use calendar dates rather than vague phrases such as “four weeks.” Ask whether the supplier means business days or calendar days.
For example, suppose a factory needs fabric on 1 September. You estimate five business days for supplier confirmation, ten days for swatches, fourteen days for sample yardage, ten days for testing, twenty-five days for bulk production, and twelve days for freight and receiving. These stages total seventy-six working days if they happen one after another. Add a buffer for delayed approvals, failed tests, and transport disruption.
Ask the supplier to confirm:
- Whether the fabric is in stock or made to order.
- The date production can start, not only the number of weeks.
- Whether the lead time starts after payment, approval, or purchase order receipt.
- Whether the quoted time includes finishing, packing, and shipping.
- What happens if the required dye lot or color is unavailable.
- How long the quotation and reserved stock remain valid.
Common timeline errors
A quoted bulk lead time may exclude dyeing, finishing, or laboratory approval. A supplier may also reserve capacity only after receiving a deposit. If the fabric is imported, customs clearance can add an uncertain delay.
Plan approval deadlines explicitly. Assign one person to approve swatches and another to verify technical tests if needed. Keep written records of the approved color, construction, width, weight, and test results. If any of those changes, treat the order as a new approval point.
Exercise
Exercise
A supplier quotes 30 business days for bulk fabric production, but the order also needs 10 days for testing and 12 days for freight and receiving. How much working time should you reserve before the factory can cut the fabric, before adding a buffer?
Show answer
Reserve at least 52 working days: 10 days for testing, 30 days for production, and 12 days for freight and receiving.