Sub topic 8
Estimating Yardage and Checking It Against the MOQ
Assume you can read a tech pack, understand a basic marker, and convert between meters and yards. A marker is a cutting layout that shows how pattern pieces fit on the fabric. Its fabric consumption is the best starting point for a production estimate.
Start with consumption per garment
Record the planned unit count and the marker consumption for one garment. Include the fabric width used by the marker. A marker for 150 cm fabric cannot be used for a 110 cm fabric without recalculating the layout.
Use this formula:
required fabric = units × consumption per unit × (1 + allowance)
The allowance covers cutting loss, small defects, shade problems, and test pieces. A common planning allowance is 3% to 10%, but the right value depends on the fabric and order. Plaids, stripes, directional prints, nap, and unstable knits often need more.
Do not add the same loss twice. If the marker consumption already includes an agreed production waste factor, use that figure as your consumption and add only the remaining allowance.
Work example
Suppose you plan 300 garments. The marker uses 1.8 meters per garment, and you add 5% for waste and defects:
- Base requirement:
300 × 1.8 = 540 meters - Waste allowance:
540 × 0.05 = 27 meters - Required quantity:
540 + 27 = 567 meters
Round up to the supplier's selling unit. If the supplier sells full rolls or 50-meter increments, the order may need to be 600 meters rather than 567 meters.
units = 300 # garments planned
consumption_m = 1.8 # meters of fabric per garment, from the marker
waste = 0.05 # 5% allowance for cutting loss and defects
moq_m = 500 # supplier minimum, in meters
needed_m = round(units * consumption_m * (1 + waste), 1)
if needed_m >= moq_m:
print(f"Need {needed_m} m, meets the {moq_m} m MOQ")
else:
print(f"Need {needed_m} m, short by {round(moq_m - needed_m, 1)} m")Compare the result with the MOQ
A minimum order quantity, or MOQ, is the smallest amount a supplier will sell under stated terms. The MOQ may apply to:
- The whole order
- Each fabric color
- Each print or finish
- Each dye lot
- Each width or composition
A 500-meter MOQ does not always mean that 500 meters can be divided freely across five colors. Ask the supplier to state the rule in writing.
If your requirement is below the MOQ, calculate the shortfall:
shortfall = MOQ - required fabric
Then check whether ordering the MOQ creates useful inventory. Extra fabric may support future production, but it also ties up cash and can become unusable if the color, finish, or season changes.
Record assumptions
Keep the calculation with the sourcing request. Record fabric width, marker version, consumption unit, allowance, MOQ scope, and rounding rule. Recalculate when the size range, order quantity, marker, or fabric width changes.
Exercise
A run needs 220 garments. The marker uses 2.1 meters per garment, the waste allowance is 8%, and the supplier MOQ is 500 meters. Does the run meet the MOQ, and what is the shortfall if it does not?
Show answer
Required fabric is 220 × 2.1 × 1.08 = 498.96 meters, usually rounded to 499 meters. It is 1 meter below a 500-meter MOQ, before any supplier-specific roll rounding.