Sub topic 1
Effort, Duration and Elapsed Time: What You Are Actually Estimating
Prerequisites
This chapter assumes you know basic project vocabulary (task, milestone, deliverable, schedule), that you have worked in a small delivery team, and that you can compute averages.
Three measures of time
Effort is the labor a task needs, usually measured in person-hours or person-days. Duration is how many working days the task takes on the calendar, given the people assigned to it. Elapsed time is the clock time from start to finish, including waiting for reviews, approvals, and other people.
| Measure | Question it answers | Example |
|---|---|---|
| Effort | How much labor is needed? | 12 person-hours |
| Duration | How many working days will it take? | 2 days with one developer at 6 productive hours per day |
| Elapsed time | When will it be finished? | 4 days, because the reviewer is busy until Thursday |
Estimate effort first, convert it to duration using the people and their focus time, then check elapsed time against dependencies.
Why estimates are ranges
Early estimates carry large uncertainty. Barry Boehm's cone of uncertainty shows that a concept-stage estimate can land anywhere from about 0.25 times to 4 times the final result. The range narrows as the team makes decisions and completes work. Present estimates as ranges with stated assumptions, such as "6 to 10 days, assuming the API design is settled."
Breaking work down
A work breakdown structure splits the project into deliverables, and each deliverable into tasks. Keep tasks small enough to estimate with confidence, typically one to five days of effort. If you cannot describe a task in one sentence, it is probably too large to estimate well.
Choosing units and granularity
Use one unit per estimate: hours for small tasks, days for larger work. Match precision to uncertainty. "About 3 days" is more honest than "27.5 hours" for a task you have never built before.
Analogous estimation
Analogous estimation uses actuals from similar past work. If a comparable login feature took 8 days last quarter, a new one probably takes a similar amount, adjusted for known differences such as a new framework or a smaller team. It is fast and useful early in a project, but its accuracy depends on how closely the past work matches the new work.
Exercise
Exercise
A task needs 12 person-hours of effort. One developer gives it 6 productive hours per day. What is the duration in working days, and what should you check before you commit to that date?
Show answer
The duration is 2 working days (12 / 6). Before committing, check elapsed time: confirm reviewers, approvals, or other dependencies will not add waiting days.