Sub topic 3
Dependencies and the critical path
This chapter assumes you can list project tasks with duration estimates, that you know what a milestone is, and that you can add numbers and compute averages.
Dependencies and the critical path
A dependency is a rule that one task cannot start until another finishes. The longest chain of dependent tasks, measured in duration, is the critical path. It sets the earliest possible finish date for the project. A delay on any critical task delays the project. Tasks off the critical path have slack, the amount they can slip without moving the end date.
Find the critical path with two passes. The forward pass computes each task's earliest start and finish. The backward pass computes each task's latest start and finish. Slack equals latest start minus earliest start.
Common biases and how to counter them
Estimators tend to be optimistic (the planning fallacy), anchor on the first number they hear, and forget time lost to handoffs and reviews. To counter these, compare each estimate with the actual duration of similar past work. Then ask: "What would make this take twice as long?"
Contingency and buffers without padding
Padding hides risk inside each task, where no one can see or manage it. A buffer is a separate, visible allowance for known risk. Size it from the riskiest tasks and place it at the end of the critical path or at the project level. Report it as its own line item.
Tracking actuals and calibrating future estimates
Record the planned and actual duration of every task. For each task type, divide actual by estimate. If the median ratio for a task type is 1.4, multiply new estimates of that type by 1.4 until new data shows a different ratio.
Communicating estimates, assumptions and confidence
Give a range with a confidence level instead of a single date. For example: "6 to 9 weeks, 80 percent confidence, assuming two developers and no change to the API contract." Write the assumptions beside the estimate so that a changed assumption is visible to everyone.
Exercise
Task A (3 days) and task B (2 days) are independent. Both must finish before task C (4 days) starts. What is the project length, and which tasks are on the critical path?
Show answer
The project takes 7 days. C starts after A (day 3) and ends on day 7. The chain B then C takes only 6 days. The critical path is A then C. B has 1 day of slack.