Sub topic 5
Read the parts of a Gantt chart
This chapter assumes you know basic project vocabulary (task, deadline, deliverable) and can read a calendar. You don't need to calculate anything yet. The goal is to look at any Gantt chart and say what each mark means, what it doesn't mean, and which questions the chart can answer.
What a Gantt chart shows
A Gantt chart is a table of tasks drawn against a time axis. Each task gets one row. The row has a name on the left and a horizontal bar on the right. The bar's position tells you when the task happens, and its length tells you how long it takes.
The chart shows four things at once:
- What work exists (the rows).
- When each piece of work happens (bar position).
- How long each piece takes (bar length).
- How pieces relate to each other (grouping, arrows, and milestones).
It doesn't show effort, cost, or who is busy. A 10-day bar can represent one person for two hours a day or a team of six working full time. Keep this in mind when reading the parts below.
The anatomy at a glance
The next table lists the parts you will meet in almost every tool. Names vary between tools, and the table gives the common alternatives.
| Part | Where it appears | What it tells you |
|---|---|---|
| Task list | Left column | The work breakdown, usually indented to show hierarchy |
| Time axis | Top or bottom edge | The scale: days, weeks, or months |
| Task bar | Main area | Start, finish, and duration of one task |
| Summary bar | Row of a parent task | The span from the earliest child start to the latest child finish |
| Milestone marker | Main area, usually a diamond | A date with no duration |
| Dependency arrow | Between bars | Which task must start or finish before another can |
| Progress fill | Inside a bar | How much of the task is done |
| Today line | Vertical line | The current date |
| Baseline bar | Thin bar under a task bar | The originally planned dates |
The task list and its hierarchy
The left column is the work breakdown structure from the first chapter, laid out as rows. Indentation or grouping shows parent and child relationships. A parent row is a summary task. Its dates are not entered by hand but derived from its children. If you move a child, the summary bar changes with it.
Check three things when you read this column:
- Every row should be a deliverable or a clearly bounded piece of work. Rows such as "Misc" or "Support" hide work that has no clear end.
- Leaf rows (rows with no children) carry the real durations. Summary rows only summarize.
- Row order is usually by start date or by logical phase. It does not imply priority.
In Mermaid, a section creates a group heading for the rows beneath it. It is a visual grouping only. Mermaid does not compute a summary bar for you, unlike full project tools.
The time axis
The axis converts horizontal distance into dates. Two choices matter:
- Scale. A daily scale suits projects of a few weeks. A weekly or monthly scale suits projects of several months. On a coarse scale a 2-day task becomes a sliver that is hard to see.
- Non-working days. Some charts draw weekends as shaded columns. Others remove them from the axis, so Friday sits next to Monday. The bar for a five-working-day task looks the same length in both cases only if you know which convention is in use. A later chapter covers calendars in detail. For now, check the axis before you compare bar lengths.
A frequent misreading comes from this. If weekends stay on the axis and a task spans one, the bar covers more calendar days than its duration in working days.
Bars: start, finish, duration
A bar has a left edge (start), a right edge (finish), and a length (duration). These three values are linked: start plus duration gives finish. Tools let you enter any two and compute the third.
Read bars with these points in mind:
- The left edge is the earliest the task is planned to start. It is not a promise that work has begun.
- The bar is a plan for elapsed time. If a task is interrupted, the bar doesn't show the gap.
- Overlapping bars mean the tasks run in parallel. They do not mean the same person does both at once.
- A bar with no visible length is probably a milestone.
Milestones
A milestone is a point in time with zero duration. Typical examples are "Design approved" and "Launch". Tools draw it as a diamond. A milestone marks a decision, a hand-off, or the end of a phase, so it has no work of its own.
Milestones are useful because they are checkable. Either the design was approved by the date or it wasn't. When a milestone follows a task by a dependency, it moves automatically when the task moves.
Dependency arrows
An arrow connects a predecessor bar to a successor bar and says the successor is constrained by the predecessor. The most common type is finish-to-start: the successor can't start until the predecessor finishes. The arrow leaves the right end of the predecessor and enters the left end of the successor.
Read an arrow in two steps. First, identify the constraint type from where the arrow attaches. Second, ask whether a gap exists between the two bars. A gap means the successor starts later than it needs to. That can be deliberate (a lag, or a resource that isn't free) or a sign that the dates were typed in by hand rather than driven by the dependency.
Not every tool draws arrows. Mermaid, for example, does not draw them. It expresses dependencies with after, so the link is visible only in the source text and in the fact that bars line up end to start. Dependencies get a full chapter later.
Status marks: progress, today, and critical tasks
Three marks describe the state of the project at the moment you look at it:
- Progress fill. A darker portion inside the bar shows the percentage complete. A bar filled to 60% means 60% of the work is done, not that 60% of the time has passed.
- Today line. A vertical line at the current date. Bars entirely to the left should be complete. A bar crossing the line should be in progress. A bar to the left of the line with little fill is late.
- Critical highlighting. Many tools color the tasks on the critical path red, or use another strong color. These tasks have no spare time, so a delay in any of them delays the finish. You will calculate this yourself in a later chapter.
The baseline appears when you save a copy of the original plan. The tool then draws it as a thin bar under the current bar. If the two bars differ, the task has slipped or been pulled in. The chapter on tracking progress covers baselines in full.
A chart with every part labeled
This Mermaid definition uses sections, a done task, an active task, a critical task, and a milestone. Mermaid draws it as one row per task, grouped under two section headings.
gantt
title Website Launch
dateFormat YYYY-MM-DD
section Design
Wireframes :done, des1, 2026-01-05, 5d
Mockups :active, des2, after des1, 7d
section Build
Frontend :crit, dev1, after des2, 10d
Launch :milestone, m1, after dev1, 0dRead each task line as name : tags, id, start, duration:
done,active, andcritare optional tags that change the bar's styling.des1,des2,dev1, andm1are IDs. They exist so that other tasks can refer to them withafter.after des1means "start whendes1finishes", which is a finish-to-start dependency written in text.0dwith themilestonetag draws a diamond.
The next figure shows how the parts of one row relate to the data behind it.
Adjusting the axis in Mermaid
Mermaid has a few settings that change how the axis reads. This version adds a date format for the axis labels, skips weekends, and hides the today line.
gantt
title Website Launch
dateFormat YYYY-MM-DD
axisFormat %d %b
excludes weekends
todayMarker off
section Design
Wireframes :done, des1, 2026-01-05, 5d
Mockups :active, des2, after des1, 7d
section Build
Backend :dev2, after des1, 12d
Frontend :crit, dev1, after des2, 10d
Integration :crit, int1, after dev1, 4d
Launch :milestone, m1, after int1, 0dHere is what changed:
axisFormat %d %blabels ticks as "05 Jan" instead of the default.excludes weekendsremoves Saturdays and Sundays from the schedule, so a 5-day task starting on a Monday ends on the following Monday's edge rather than on a Saturday.todayMarker offhides the today line, which is useful when you publish a plan that shouldn't look stale.Backendstarts afterdes1at the same time asMockups, so the two bars overlap. That is parallel work.
Common misreadings
Most errors come from reading more into the picture than it contains.
- Bar length is not effort. Two 10-day bars can need very different amounts of work.
- Bars that line up are not necessarily linked. Two tasks may sit end to end because someone typed the dates, not because a dependency exists. Move the first task and see whether the second follows. If it doesn't, no link exists.
- A long bar is not always critical. Criticality depends on dependencies and spare time, not on size.
- The right edge is a plan, not a forecast. Unless the chart is updated, it shows what was intended.
- A summary bar is not a task. Nobody works on it. It is only the span of its children.
A quick reading checklist
When you open an unfamiliar Gantt chart, answer these in order:
- What is the scale of the axis, and are non-working days shown or removed?
- Which rows are summary tasks and which are leaves?
- Where are the milestones, and what do they mark?
- Which bars are linked, and how do you know?
- Where is the today line, and which bars sit to its left without being complete?
- Is a baseline shown, and how far do current bars differ from it?
Exercise
In the second Mermaid example, Backend is defined as after des1, 12d and Mockups as after des1, 7d. What does the chart show about these two tasks, and what does it not show?
Show answer
Both start when Wireframes finishes, so their bars start at the same point and overlap for 7 working days. This shows parallel work. The chart does not show who does each task or how much effort each needs, so it can't tell you whether one team can really do both at the same time.
Exercise
You see two bars end to end, and the second one starts the moment the first finishes. How can you tell whether a dependency exists?
Show answer
Move the first task later. If the second task moves with it, the link is a real dependency, written as after in Mermaid or drawn as an arrow in other tools. If the second task stays put, the dates were typed in by hand and the alignment is accidental.
Exercise
A summary bar for "Build" runs from day 6 to day 26. A teammate asks you to add 3 days to it. Why is that the wrong request?
Show answer
A summary bar is derived from its child tasks, so it has no duration of its own. To change it you must change the dates or durations of the child tasks, or the dependencies between them.