01Chapter 1: Start with a work breakdown structureA Gantt chart can only show tasks that someone has defined. If the task list is incomplete, vague or overlapping, every later step inherits those flaws. That includes the dates, the critical path and the progress bars. This chapter covers the first step: turning a project goal into a work breakdown 8 min read
02Chapter 2: Estimate task durationsEvery bar on a Gantt chart has a length, and that length is the task's duration. This chapter covers how to produce durations you can defend, how to record them, and which errors make a schedule wrong before you draw anything.7 min read
03Chapter 3: Link tasks with dependenciesA schedule is more than a list of tasks with durations. The order in which tasks can happen decides when the project ends. A dependency is the rule that connects one task to another, and the forward pass and critical path in later chapters both depend on getting these rules right.7 min read
04Chapter 4: Mark milestonesThis chapter assumes you can list tasks with durations and dependencies, read a calendar, and run a short Python script. You should know that a finish-to-start dependency means a task cannot begin until its predecessor ends. The chapter covers what a milestone is, how to choose good ones, how they b6 min read
05Chapter 5: Read the parts of a Gantt chartThis chapter assumes you know basic project vocabulary (task, deadline, deliverable) and can read a calendar. You don't need to calculate anything yet. The goal is to look at any Gantt chart and say what each mark means, what it doesn't mean, and which questions the chart can answer.8 min read
06Chapter 6: Account for working days and holidaysA Gantt chart plots time on a calendar, but people only work on some calendar days. This chapter shows how to make the schedule respect weekends and holidays, in Mermaid and in Python.6 min read
07Chapter 7: Calculate start and finish dates with a forward passThis chapter assumes you can already write a task list with durations and finish-to-start dependencies (task B cannot start until task A finishes). It also assumes you can read basic Python. The forward pass is the step that turns those inputs into dates. The Gantt chart needs it, and so does the cr6 min read
08Chapter 8: Find the critical pathThe forward pass from the previous chapter gave you the earliest start and finish for every task, and a project length of 26 days. This chapter explains which tasks decide that length. Those tasks form the critical path. Delaying any task on it delays the whole project.7 min read
09Chapter 9: Draw the chart in Mermaid and PythonThis chapter turns the schedule you calculated earlier into a picture. You will draw it twice. First you will write it as text that Mermaid renders. Then you will compute it and plot it with Python and matplotlib. It assumes you can read a task list with durations and predecessors, and that you have6 min read
10Chapter 10: Use slack to plan flexibilityThis chapter assumes you can already compute earliest start and finish dates with a forward pass and can pick out the critical path. It also assumes you read Gantt bars and finish-to-start dependencies without trouble. Here you compute slack, separate its two forms, and use it to make scheduling dec6 min read
11Chapter 11: Track progress against a baselineThis chapter assumes you can run the forward pass and name the critical path from the earlier chapters. It also assumes you can run a short Python script. Here you will freeze a plan as a baseline, record progress against it, and show the difference on a chart.6 min read
12Chapter 12: Avoid common mistakesThis chapter assumes you have worked through the earlier chapters. You should be able to write a work breakdown structure (WBS), give tasks durations and finish-to-start dependencies, run a forward pass, and name the critical path. It also assumes you can read short Python and Mermaid examples. Here8 min read