Sub topic 1
What DMAIC Is and How a Project Flows Through It
Prerequisites
This chapter assumes you understand process variation, can read simple statistics such as the mean and a defect rate, and recognize roles such as Champion, Black Belt, Green Belt and Process Owner.
DMAIC overview
DMAIC is a five-phase method for improving an existing process. The letters stand for Define, Measure, Analyze, Improve and Control. Each phase has a purpose, activities and deliverables that should be complete before the project moves on.
Why projects pass through tollgate reviews
A tollgate is a formal review at the end of a phase. The sponsor and reviewers check the evidence and decide whether the project proceeds. Common outcomes are go, conditional go, hold, or stop. Tollgates prevent teams from building solutions on guesses.
Define: agreeing on the problem and the goal
Define states the problem, the goal, the scope and the team. Its main deliverable is the project charter.
Writing a project charter
A project charter is a short document that contains:
- A problem statement
- A goal with a number and a date
- The scope, including what is out of scope
- The sponsor and team members
- The expected benefit
Turning customer voice into CTQ requirements
Voice of the customer (VOC) is what customers say they need, gathered through interviews, complaints or surveys. A critical to quality (CTQ) requirement turns that voice into a measurable target, such as "invoices are issued within 2 working days."
ctq_limit_days = 2
measured_days = [1, 3, 2, 4, 1]
on_target = sum(1 for d in measured_days if d <= ctq_limit_days)
print(f"{on_target / len(measured_days):.0%} of invoices met the CTQ")Scoping the process with SIPOC
SIPOC is a high-level map with five columns: Suppliers, Inputs, Process, Outputs and Customers. It shows where the process starts and ends.
| Suppliers | Inputs | Process | Outputs | Customers |
|---|---|---|---|---|
| Sales team | Order form | Invoice creation | Issued invoice | Accounts receivable |
Exercise
Why does the CTQ "invoices issued within 2 working days" need a number?
Show answer
A number lets the team measure whether the process meets the requirement. Without one, the team cannot tell whether the process has improved.