Sub topic 3
Selecting solutions and running a pilot
This chapter assumes you know DMAIC phases, basic process capability, and the difference between a defect rate and a sigma level. A pilot is a small trial of a fix on part of the real process, run before a full rollout.
Selecting solutions and running a pilot
Rank candidate fixes by their expected effect on the root causes you verified in Analyze, and by cost and risk. Choose one or two to test. Run the pilot on a limited scope, such as one shift or one line, for a fixed period. Compare its results with the baseline.
baseline_defect_rate = 0.054
pilot_defects = 9
pilot_units = 250
pilot_rate = pilot_defects / pilot_units
improvement = (baseline_defect_rate - pilot_rate) / baseline_defect_rate * 100
print(f"Pilot defect rate: {pilot_rate:.3f}")
print(f"Improvement vs baseline: {improvement:.1f}%")Control: keeping the gains
The Control phase makes sure the improvement lasts. Document the new method, train the operators, and monitor the key metric with a control chart.
Building a control plan and handing over to the process owner
A control plan lists each key process input, its measurement, its limit, the response when the limit is breached, and the owner. Hand the plan and the monitoring data to the process owner, who keeps the process running after the project closes.
Who attends a tollgate and the possible decisions
A tollgate is a review between phases. The project sponsor, the Champion, the process owner, and the Black Belt or Green Belt usually attend. The review ends with one of these decisions:
| Decision | Meaning |
|---|---|
| Go | Evidence is complete. Move to the next phase. |
| Conditional go | Move on, with named actions due by a set date. |
| Hold | Evidence is incomplete. Fix the gaps and review again. |
| Stop | The project no longer has a sound case. Close it. |
Preparing tollgate evidence and checklists
Prepare a checklist for each phase. Each item should point to a document or data set that the reviewers can inspect. Send the pack before the meeting so decisions are based on evidence, not on the presenter's summary.
Common tollgate pitfalls and how to avoid them
- The pilot runs too briefly to show stable results. Set the duration and sample size before starting.
- The control plan has no named owner. Assign one before the handover.
- The sponsor skips the review to save time. Keep the tollgate on the calendar.
- Teams present activities instead of results. Lead with the metric and its change from baseline.
Exercise
A baseline defect rate is 5.4 percent. A pilot produces 9 defects in 250 units. What is the percentage improvement over baseline?
Show answer
The pilot rate is 9 / 250 = 3.6 percent. The improvement is (5.4 - 3.6) / 5.4 = 33.3 percent.