Sub topic 3
Getting Deliverables Accepted and Signed Off
Assume you know the terms scope, deliverable, stakeholder, and sponsor. You should also understand the project lifecycle and have experience working on a small or medium project.
A deliverable is an output that the project promised to produce. Acceptance means the authorised person confirms that the output meets the agreed requirements. Sign-off is the recorded evidence of that decision. A demonstration or a “looks good” comment is not the same as formal acceptance.
Define acceptance before delivery
Acceptance should be based on agreed acceptance criteria. An acceptance criterion is a condition that must be true for the deliverable to be accepted. Criteria should be specific enough that two people can reach the same decision.
For example, “The report is easy to use” is vague. “A user can filter the report by region and export the results to CSV” is testable.
Before requesting acceptance, check:
- The deliverable matches the approved scope.
- Every acceptance criterion has been tested.
- Test results, approvals, and supporting documents are available.
- Known defects are recorded with owners and target dates.
- The person who will accept the deliverable has authority to do so.
The project manager should confirm who can accept each deliverable. A person who helped create the work may review it, but that does not always give them authority to approve it.
Run the acceptance review
Give the reviewer enough time and context. Send the deliverable, acceptance criteria, test evidence, and decision deadline together. During the review, show how the deliverable meets each criterion.
| Review result | Meaning | Required action |
|---|---|---|
| Accepted | All required criteria are met | Record formal sign-off |
| Accepted with minor conditions | The output is usable and remaining issues are agreed | Record conditions, owners, and dates |
| Rejected | One or more essential criteria are not met | Correct the work and arrange another review |
Do not treat silence as acceptance unless the contract or governance process explicitly allows it.
Record the decision
Store the signed decision in the project records. It should identify:
- The deliverable and version reviewed.
- The acceptance criteria used.
- The name, role, and date of the approver.
- Conditions, exclusions, or unresolved defects.
- The location of supporting evidence.
A version number matters because acceptance applies to a particular version. If the deliverable changes materially after approval, ask whether it needs another acceptance review.
Exercise
A sponsor says in a meeting, “I am happy with the deliverable,” but does not approve the acceptance record. What should you do?
Show answer
Ask the sponsor to confirm the decision in the agreed approval record, linked to the reviewed version and acceptance criteria. Treat the deliverable as awaiting sign-off until that record exists.