Sub topic 12
Finding Root Causes
Assume you know basic project terms such as scope, deliverable, stakeholder, and sponsor. You should also understand the project lifecycle and have taken part in a small or medium project.
A root cause is an underlying condition that allowed a problem to occur. A symptom is the visible result. For example, “the report was delivered late” describes a symptom. “The business owner approved the acceptance criteria after development began” may identify a root cause.
Root cause analysis helps a team improve the system that produced an outcome. It should not become an investigation into who made a mistake. A useful analysis explains what happened, why it happened, and what change will reduce the chance of recurrence.
Use evidence before opinions
Start with a clear problem statement. Include the expected result, the actual result, and evidence such as dates, records, or measures.
For example:
- Expected: the reporting module would pass user acceptance testing on 15 June.
- Actual: testing began on 29 June, and several completed features needed rework.
- Evidence: approval records show that business acceptance criteria were agreed on 22 June.
Separate facts from interpretations. “The team ignored the users” is an interpretation. “No business user reviewed the criteria before development” is a testable fact.
Trace causes with “why”
The five whys technique asks why an outcome occurred, then questions each answer. Five is a guide, not a required number. Stop when the team reaches a condition it can change through a practical control.
In this example, “the developer worked too slowly” might be a tempting answer, but it does not explain why late criteria and rework were possible. The missing review checkpoint is a more useful cause because the project can add one to its planning and governance.
Test the analysis
Ask whether the proposed cause explains the evidence. Then ask whether removing or controlling it would probably prevent the problem. Look for contributing causes rather than forcing one cause to explain everything. A supplier delay, unclear requirements, and an overloaded reviewer may all have played a part.
Avoid common errors:
- Stopping at blame, such as “the coordinator forgot.”
- Treating a restatement of the symptom as a cause.
- Choosing a cause because it supports a preferred solution.
- Using “poor communication” without naming the missing channel, owner, timing, or information.
- Treating correlation as proof of causation.
Record the evidence and uncertainty. If the team cannot verify a proposed cause, label it as a hypothesis and define how it will be checked.
A strong analysis leads to a specific lesson. “Improve communication” is too vague. “Add business-owner approval of acceptance criteria before development starts” identifies a control that a future project can adopt, along with an owner and a point of verification.
Exercise
A supplier delivered a component late because its interface specification changed twice. What further question should the team ask before recording the supplier as the root cause?
Show answer
Ask why the specification changed and whether the project had a controlled review and approval point before sending it to the supplier.