Sub topic 7
Being honest about the time you have
This chapter assumes you already keep a task list and use a calendar. It also assumes you have a candidate list from the capture step and a rough sense of which tasks matter most. Here you check those candidates against the hours you really have today. This is the capacity check that comes before you pick your three.
Why the check matters
A day has 24 hours, but you cannot spend all of them on tasks. Meetings, meals, travel, messages, and breaks take most of the working day. If you pick three tasks as if the whole day were free, you will finish one and carry the others forward. That pattern is the main way a three-task plan fails.
The goal is to find your focus time. This is the time left after fixed commitments, when you can do work that needs real attention.
Count your focus time
Work through these steps each morning, or the evening before.
- Start with the hours you plan to work today.
- Subtract fixed commitments: meetings, calls, appointments, and commute or school runs.
- Subtract routine overhead: email, chat, and admin. Most people lose between one and two hours to these.
- Subtract buffer for the unexpected. Leave about 20 to 30 percent of what remains unplanned.
- What is left is your focus time.
Here is a worked example for a day with 8 working hours.
| Step | Hours | Remaining |
|---|---|---|
| Working hours | 8.0 | 8.0 |
| Meetings (stand-up, planning call) | 2.5 | 5.5 |
| Email, chat, admin | 1.0 | 4.5 |
| Buffer (about 25%) | 1.0 | 3.5 |
You have about 3.5 hours of focus time. That is the budget your three tasks must fit inside.
Estimate each task, then add a margin
Give each candidate a time estimate. People tend to guess too low, so add about 50 percent to your first guess for any task you have not done before. If a similar task took 90 minutes last time, plan for 90 minutes, not the 60 you hope for.
Now compare the total with your focus time.
- If the three estimates fit, move on.
- If they do not fit, shrink a task to a clear first part, swap it for a smaller one, or move it to another day.
- Do not squeeze the estimates to make the plan look workable.
Match the task to your energy
Hours are not all equal. Hard thinking goes best when you are fresh, and routine tasks suit low-energy periods. Look at where your focus time falls. A 3.5-hour budget made of a single 90-minute gap and several 20-minute gaps cannot hold a task that needs two uninterrupted hours.
Common mistakes
- Counting the whole day. Meetings and overhead are real. Subtract them.
- No buffer. A plan with zero slack breaks at the first interruption.
- Using your best-case estimate. Plan for the typical case.
- Ignoring energy. A hard task placed in your slowest hour often takes twice as long.
Exercise
Your day has 7 working hours. You have 3 hours of meetings, 1 hour of email and admin, and you want a buffer of about 25% of what remains after those. Your three candidates are estimated at 90 minutes, 60 minutes, and 45 minutes. Do they fit? What would you do?
Show answer
Remaining after meetings and admin: 7 - 3 - 1 = 3 hours. A 25% buffer is 0.75 hours (45 minutes), which leaves 2.25 hours (135 minutes) of focus time. The three tasks total 195 minutes, so they do not fit by 60 minutes. Options: move the 60-minute task to another day, or cut the 90-minute task to a clear first part of about 30 minutes. Dropping the 60-minute task leaves 135 minutes of work in 135 minutes of focus time, which has no slack left, so a smaller scope for the largest task is safer.