Sub topic 13
The Security Market Line and Mispricing
This chapter assumes you know how to compute beta and apply the CAPM formula from the previous chapters. You should also be comfortable with expected return, the risk-free rate, and the market risk premium. Here you use the security market line (SML) to decide whether a security is fairly priced, underpriced, or overpriced.
What the Security Market Line Is
The SML is the graph of the CAPM equation. It plots required return against beta:
E[Ri] = Rf + βi × (E[Rm] − R_f)
The vertical axis is the return investors require. The horizontal axis is beta, which is systematic risk. The line has three features:
- The intercept is the risk-free rate. A security with beta 0 earns R_f.
- The slope is the market risk premium, E[Rm] − Rf. Each extra unit of beta adds this much required return.
- The market portfolio sits at beta 1.0, with required return E[R_m].
The SML applies to every asset and every portfolio, efficient or not. The capital market line (CML) applies only to efficient portfolios.
| Feature | Security market line | Capital market line |
|---|---|---|
| Risk on the x-axis | Beta (systematic risk) | Standard deviation (total risk) |
| Applies to | Any security or portfolio | Efficient portfolios only |
| Slope | Market risk premium | Market portfolio Sharpe ratio |
| Used for | Required return, mispricing | Allocating between risk-free asset and market |
Required Return Versus Expected Return
Two different returns appear in SML problems, and mixing them up is the most common error.
- The required return comes from the SML. It is what investors demand for the security's systematic risk.
- The expected return (also called the forecast or estimated return) is your own analysis of what the security will earn.
The gap between them is the security's alpha:
α = E[R] (your forecast) − required return (from the SML)
A security that plots on the line has an alpha of zero. It is fairly priced.
Judging Mispricing
Plot the security's forecast return against its beta.
- Above the SML: the forecast exceeds the required return, so alpha is positive. The security is underpriced. Buy it.
- Below the SML: the forecast is less than the required return, so alpha is negative. The security is overpriced. Sell it or avoid it.
- On the SML: alpha is zero. The security is fairly priced.
Why Price Moves Fix the Gap
The forecast return depends on the price you pay. If a stock is above the SML, investors buy it. Buying pushes the price up. A higher price lowers the return on the future cash flows. The expected return falls until the stock plots on the line again. An overpriced stock goes through the same process in reverse. Selling pushes the price down and raises the expected return until it reaches the line.
This is why the SML is a statement about equilibrium. If CAPM holds and markets are efficient, alpha should be zero for all securities.
A Worked Example
Assume Rf = 3% and E[Rm] = 8%, so the market risk premium is 5%.
| Stock | Beta | Forecast return | Required return | Alpha | Verdict |
|---|---|---|---|---|---|
| A | 1.2 | 10.0% | 3% + 1.2 × 5% = 9.0% | +1.0% | Underpriced |
| B | 0.8 | 6.5% | 3% + 0.8 × 5% = 7.0% | −0.5% | Overpriced |
| C | 1.0 | 8.0% | 3% + 1.0 × 5% = 8.0% | 0.0% | Fairly priced |
Stock A has a higher beta than the market, so it needs more than the 8% market return. It needs 9.0%. The analyst expects 10.0%, so A is above the line.
Stock B has low systematic risk, so its required return is only 7.0%. The forecast of 6.5% falls short of that, so B is below the line.
The next program applies the same steps and labels each stock.
def required_return(rf, beta, e_rm):
return rf + beta * (e_rm - rf)
def classify(name, beta, forecast, rf, e_rm, tol=1e-9):
req = required_return(rf, beta, e_rm)
alpha = forecast - req
if alpha > tol:
verdict = "underpriced (buy)"
elif alpha < -tol:
verdict = "overpriced (sell)"
else:
verdict = "fairly priced"
print(f"{name}: required={req:.2%} forecast={forecast:.2%} alpha={alpha:+.2%} -> {verdict}")
rf, e_rm = 0.03, 0.08
classify("A", 1.2, 0.100, rf, e_rm)
classify("B", 0.8, 0.065, rf, e_rm)
classify("C", 1.0, 0.080, rf, e_rm)The tolerance guards against floating-point noise. Without it, a stock that is exactly fair could print as slightly over or under because of rounding.
Using the SML for Valuation
Required return is also a discount rate. If you know a stock's expected cash flows, you can discount them at the SML rate to get an intrinsic value. Then compare that value to the market price.
Suppose a stock with beta 1.2 is expected to pay a dividend of 2.00 next year and be sold for 52.00 at that time. The required return is 9.0%.
- Intrinsic value = (2.00 + 52.00) / 1.09 = 49.54
- If the market price is 47.00, the stock is underpriced. The market price is below intrinsic value.
- If the market price is 52.00, the stock is overpriced.
Both methods give the same answer. The return view says the stock yields more than required. The price view says the stock costs less than it is worth.
Shifts in the Line and Movements Along It
Learn to separate a change in the line from a change in position on the line.
- A change in beta moves a security along the line. Higher beta means higher required return.
- A rise in the risk-free rate shifts the intercept up. If the market risk premium is unchanged, the whole line moves up in parallel.
- A rise in the market risk premium makes the line steeper. High-beta assets see their required returns rise the most. A beta of 0 is unaffected.
- A security's price changes in response to a change in its required return, with expected cash flows held constant. A higher required return means a lower price.
Check on Slope
When the market risk premium rises from 5% to 6% with R_f at 3%, stock A (beta 1.2) has required return 3% + 1.2 × 6% = 10.2%, up from 9.0%. Stock C (beta 1.0) goes up by 1 percentage point. A beta-0 asset stays at 3%. The change in required return equals beta times the change in premium.
Common Errors
- Using the SML forecast and the required return interchangeably. Only the required return comes from the formula.
- Reading "above the line" as "better" without checking that beta is right. A high forecast return at a high beta may still sit below the line.
- Using total risk (standard deviation) in the CAPM formula. Only beta belongs there.
- Using the market return instead of the market risk premium. The slope is E[Rm] − Rf.
- Treating alpha as certain. Alpha rests on a forecast, and the beta estimate has its own error.
- Judging mispricing by comparing the stock's return to the market's return. The comparison must be against the stock's own required return.
Practical Limits on Mispricing Signals
The SML conclusion is only as good as its inputs. Beta estimated from past data can be unstable. Different return windows, data frequencies, and market indexes give different betas. The forecast return is a judgment. A small positive alpha can vanish once you account for estimation error and transaction costs. In the exam, you take the inputs as given. In practice, you treat the signal with caution.
Summary Table
| Position | Forecast vs required | Alpha | Action | Price pressure |
|---|---|---|---|---|
| Above SML | Forecast > required | Positive | Buy | Price rises |
| On SML | Forecast = required | Zero | Hold | None |
| Below SML | Forecast < required | Negative | Sell | Price falls |
Exercise
The risk-free rate is 4% and the expected market return is 9%. An analyst forecasts a return of 11% for a stock with beta 1.4. Compute the required return and alpha, and state whether the stock is underpriced or overpriced.
Show answer
Required return = 4% + 1.4 × (9% − 4%) = 4% + 7% = 11%. Alpha = 11% − 11% = 0. The stock plots on the SML and is fairly priced. It is not underpriced even though its forecast exceeds the 9% market return, because its beta of 1.4 raises its required return to 11%.
Exercise
A stock has beta 0.6 and a forecast return of 7%. With Rf = 3% and a market risk premium of 5%, is the stock under- or overpriced? Then suppose the market risk premium rises to 8% with Rf unchanged. What happens to its required return and verdict?
Show answer
Initially the required return is 3% + 0.6 × 5% = 6%. Alpha is 7% − 6% = +1%, so the stock is underpriced. After the premium rises to 8%, the required return is 3% + 0.6 × 8% = 7.8%. Alpha is 7% − 7.8% = −0.8%, so the stock is now overpriced. With a higher premium the SML is steeper, and this low-beta stock's fixed forecast no longer clears the line.
Exercise
A stock with beta 1.0 is expected to pay a dividend of 1.50 and sell for 31.50 in one year. The market risk premium is 6% and the risk-free rate is 2%. The stock trades at 30.00. Is it under- or overpriced?
Show answer
Required return = 2% + 1.0 × 6% = 8%. Intrinsic value = (1.50 + 31.50) / 1.08 = 33.00 / 1.08 = 30.56. The market price of 30.00 is below intrinsic value, so the stock is underpriced. Equivalently, the forecast return is 33.00 / 30.00 − 1 = 10%, which is above the 8% required return.