Sub topic 8
The Capital Allocation Process
This chapter assumes you understand present value, basic financial statements, risk and required return, and elementary algebra. Capital allocation is the process of deciding how an issuer should use limited funds. Examples include buying equipment, opening a facility, developing a product, or acquiring another company.
Why capital allocation matters
A corporate issuer usually faces more possible investments than it can fund. Each project competes for cash. Management must estimate the project's future cash flows, compare its risk-adjusted return with the required return, and decide whether the project increases shareholder wealth.
The process is broader than calculating a return. A sound decision also considers strategy, liquidity, risk, and the issuer's ability to carry out the project.
Forecasting relevant cash flows
The analysis uses incremental cash flows, which are the additional cash flows caused by accepting the project. Include cash flows that change because of the decision. Exclude accounting amounts that do not affect cash.
Important adjustments include:
- Sunk costs are costs already incurred. They are irrelevant to the decision because they cannot be recovered.
- Opportunity costs are benefits lost when an existing resource is used for the project. They are relevant even if no new payment occurs.
- Externalities are effects on other company activities. For example, a new product may reduce sales of an existing product.
- Working capital investment is cash tied up in inventory or receivables. Include the investment when it occurs and the expected recovery when the project ends.
- Taxes and depreciation effects affect cash flow. Depreciation itself is not a cash payment, but it can reduce taxes and therefore create a tax shield.
- Financing costs are normally reflected in the discount rate rather than deducted from project cash flows. Counting them in both places would double-count financing effects.
| Cash-flow item | Include in project cash flow? | Reason |
|---|---|---|
| Additional equipment purchase | Yes | It is caused by the project |
| Feasibility study paid last year | No | It is a sunk cost |
| Rent forgone by using an existing building | Yes | It is an opportunity cost |
| Interest expense | Usually no | It is reflected in the discount rate |
From proposal to decision
A typical capital allocation process follows these steps:
- Generate and screen proposals for strategic fit.
- Estimate the project's incremental cash flows and timing.
- Select a discount rate consistent with the project's risk.
- Calculate NPV, IRR, or other decision measures.
- Consider capital limits, liquidity, and implementation risks.
- Approve, reject, or modify the project.
- Compare actual results with the original forecast.
A positive NPV generally indicates that the project is expected to add value at the chosen required return. However, managers should investigate the assumptions behind the forecast rather than accept the result mechanically.
Exercise
A company spent $20,000 last month studying a project. It must also give up warehouse rent of $8,000 per year to use the warehouse for the project. Which amount is relevant to the project analysis?
Show answer
The $20,000 study is a sunk cost and is excluded. The $8,000 forgone rent is an opportunity cost and is included.