Sub topic 11
NPV Versus IRR Ranking Conflicts and Project Pitfalls
Assume you know present value, discounting, cash flows, and the meaning of a required return. This chapter explains why net present value (NPV) and internal rate of return (IRR) can rank projects differently.
The decision rules
NPV is the present value of expected cash inflows and outflows, discounted at the required return. Accept an independent project when NPV is positive. For mutually exclusive projects, choose the project with the higher NPV.
IRR is the discount rate that makes NPV equal to zero. Accept an independent project when IRR exceeds the required return. For mutually exclusive projects, IRR can give the wrong ranking.
The conflict usually occurs because projects differ in size or in the timing of their cash flows.
| Cause of conflict | Why IRR can mislead |
|---|---|
| Different project sizes | IRR is a percentage and ignores the total dollars of value created |
| Different cash-flow timing | IRR may favor earlier returns even when a later project creates more value |
| Nonconventional cash flows | Multiple sign changes can produce multiple IRRs or no meaningful IRR |
A ranking example
Suppose the required return is 10%.
- Project A costs $100 today and pays $130 in one year.
- Project B costs $1,000 today and pays $1,300 in one year.
Project A has an IRR of 30%, and Project B also has an IRR of 30%. Their NPVs differ:
- NPV(A) = $130 / 1.10 − $100 = $18.18
- NPV(B) = $1,300 / 1.10 − $1,000 = $181.82
If the projects are mutually exclusive, B creates more value even though both IRRs are equal. A high percentage return does not necessarily mean a high dollar gain.
When timing differs, calculate the incremental cash flows. Subtract the cash flows of one project from the other, then calculate the incremental IRR. This rate is the crossover rate. If the required return is below the crossover rate, one project may rank higher; above it, the other may rank higher. NPV at the actual required return remains the primary decision rule.
def npv(rate, cash_flows):
return sum(cf / (1 + rate) ** t for t, cf in enumerate(cash_flows))
projects = {
"A": [-100, 130],
"B": [-1000, 1300],
}
for name, flows in projects.items():
print(name, round(npv(0.10, flows), 2))Other IRR pitfalls
An investment with cash flows that alternate between positive and negative more than once can have multiple IRRs. For example, a project may require a later cleanup payment after producing operating inflows. In such cases, IRR may not provide a unique decision rule. NPV is more reliable.
Do not compare projects using different required returns without considering risk. A riskier project normally requires a higher discount rate. Also distinguish a project's standalone NPV from its contribution to a larger investment program.
Exercise
Project X has an IRR of 25% and an NPV of $40,000. Project Y has an IRR of 18% and an NPV of $75,000. If the projects are mutually exclusive, which should the company choose?
Show answer
Choose Project Y because it has the higher NPV and therefore creates more value at the required return.