Sub topic 8
Planning the timeline and milestones
This chapter assumes you can already write objectives, scope and deliverables for a brief, and that you have a budget and channels in mind. Here you turn those into dates a supplier can commit to.
Why the timeline belongs in the brief
A deadline alone ("launch before Christmas") hides the work between now and then. A supplier who sees only the end date cannot tell whether you expect a first draft in a week or in a month. Milestones make the schedule checkable, and they show both sides where a delay will start.
Work backwards from the date that matters. For the autumn campaign, the launch is 19 December. Everything else is fixed by what must happen before it.
Build the schedule from dependencies
Some tasks cannot start until another finishes. Landing pages need approved copy. Ads need approved landing pages. Tracking must be tested before any paid traffic runs. List these dependencies first, then add dates.
What a good milestone looks like
Each milestone needs a date, an owner and a clear "done" condition. "Drafts delivered" is vague. "Three landing page variants and twelve ad groups delivered in the shared folder" can be confirmed by anyone.
| Milestone | Owner | Date | Done when |
|---|---|---|---|
| Kickoff | Client and supplier | 1 Dec | Brief confirmed, questions logged |
| First drafts | Supplier | 12 Dec | All deliverables in the shared folder |
| Feedback returned | Client | 17 Dec | One consolidated set of comments |
| Tracking test | Supplier | 18 Dec | Test conversion appears in analytics |
| Launch | Supplier | 19 Dec | Ads and pages live |
Count your own time
The client's review time is part of the schedule. In the brief, the approval window is three working days. If the first drafts arrive on Friday 12 December, three working days ends on Wednesday 17 December. Leaving only two days after that for revisions, testing and launch is tight. Say so in the brief and, if the date is fixed, cut scope rather than review time.
Also allow for known gaps: public holidays, your team's leave, and the platforms' own ad review, which can take a day or more.
Show the timeline in the brief
Keep the format short and machine-readable, as in the template from the previous chapters:
timeline:
kickoff: 2026-12-01
first_drafts: 2026-12-12
feedback_due: 2026-12-17
tracking_test: 2026-12-18
launch: 2026-12-19Add a note on what is fixed and what is flexible. A hard launch date and a soft draft date lead to different quotes and different trade-offs.
Common errors
- Giving only a launch date, with no interim milestones.
- Leaving out client review time, then blaming the supplier for delay.
- Putting the tracking test after launch.
- Treating every date as fixed, so the supplier cannot flag a conflict.
Exercise
First drafts are due on Monday 8 June. The brief gives the client three working days to review, then two working days for revisions, and the launch must be on Friday 19 June. Does the schedule fit, and what is the latest date feedback can arrive and still leave the revisions window?
Show answer
Yes, it fits. Three working days of review ends on Thursday 11 June, and two working days of revisions ends on Monday 15 June. That leaves Tuesday 16 to Thursday 18 June for the tracking test and any platform ad review before the Friday launch. To keep the two-day revision window and still reach launch with a day for testing, feedback must arrive by Wednesday 17 June at the very latest. Realistically, feedback by Thursday 11 June leaves a comfortable buffer.