Sub topic 6
Defining scope and deliverables
This chapter assumes you can already state a measurable objective and describe your audience, as covered in the earlier chapters. Here you turn those into a list of work a supplier can quote, build and hand over.
Scope versus deliverables
Scope is the boundary of the work: what the supplier will do, and what they will not. A deliverable is a concrete item you receive, such as a set of ad groups or a landing page. Scope tells the supplier where the job ends. Deliverables tell them what to hand over.
A vague scope such as "run our lead generation" lets each side assume something different. Disputes over extra fees usually start here.
Turning objectives into deliverables
Work backward from the objective and the audience. For the objective of raising qualified demo requests from 120 to 180 per month, ask what the audience needs to see to reach a demo request. Each answer becomes a deliverable.
deliverables:
- 3 landing page variants
- 12 search ad groups
- 4 email nurture messagesEach line has a quantity and a type. A supplier can price "12 search ad groups". They cannot price "some ads".
Make each deliverable checkable
For every deliverable, state four things:
- Format and quantity: for example, 3 landing page variants, each with one headline, one form and one call to action.
- Specification: sizes, word counts, languages, file types or platforms.
- Revisions included: for example, two rounds of changes per item.
- Acceptance: how you will decide it is finished, such as "passes brand check and the form submits to the CRM".
State what is out of scope
List the exclusions that people often assume are included. Common examples are:
- Photography or video production
- Translation into other languages
- Ongoing account management after launch
- Setting up the analytics tools themselves
- Paid media spend, which is usually budgeted separately from fees
If you want a supplier to price an option, mark it as optional, so you can compare quotes fairly.
Separate one-off work from ongoing work
Mark each item as a one-off project or a recurring service. A landing page build is one-off. Weekly bid adjustments are recurring. Recurring work should state its frequency and the time period covered, because it affects the monthly fee.
Show dependencies
Some deliverables cannot start until something else exists. Ads need approved copy. Landing pages need the tracking convention. Note what you will provide and by when, such as logos, product images and CRM access. Late client inputs are a common cause of slipped launches.
Worked example
Weak: "Create ad content for the autumn campaign."
Stronger: "Write 12 search ad groups, each with 3 responsive search ads (15 headlines and 4 descriptions per ad), delivered as a spreadsheet by 12 December. Two revision rounds are included. Keyword research is included. Landing page build is out of scope."
The second version states quantity, specification, date, revisions and exclusions. Two suppliers reading it will quote for the same work.
Exercise
A brief says "Provide social media support for the product launch." Rewrite it as a deliverable that can be quoted and checked. Include quantity, a deadline, revisions and one exclusion.
Show answer
One possible answer: "Produce 8 LinkedIn posts (text plus one image each) for the launch week, delivered by 5 March. Two revision rounds per post are included. Image photography and paid promotion are out of scope." Any answer that gives a countable output, a date, a revision limit and an exclusion is correct.