Sub topic 8
Planning the timeline and milestones
A timeline in a brief tells the supplier when work starts, when you will review it, and when it must be live. It also shows how long you will take to respond. This chapter assumes you already know your objective, deliverables and channels, because the timeline depends on all three. It also assumes you can read a basic campaign plan and have managed at least one campaign with an outside supplier.
Why the timeline belongs in the brief
Suppliers price and staff work against dates. A launch date with no intermediate dates leaves them guessing how long you need to review drafts. A vague "as soon as possible" forces them to assume the shortest schedule, and that usually means rushed work or a surcharge.
A good timeline does three things:
- It fixes the dates the supplier must hit.
- It fixes the dates you must hit, such as supplying assets and giving approvals.
- It shows what depends on what, so a delay on one side is visible to both.
Most late campaigns are late because of waiting time, not production time. Feedback arrives after five days instead of three. Brand assets turn up after kickoff. Tracking is not ready at launch. Put these waiting steps in the timeline and assign each an owner.
Work backwards from the launch date
Start with the date the campaign must go live, then count backwards. The reason is that launch dates are often fixed by something outside the project, such as a product release, a trade show or the end of a budget period.
Take the sample brief from this tutorial. Launch is 19 December 2026, kickoff is 1 December and first drafts are due 12 December. That gives about seven working days between drafts and launch. The brief also says approvals take up to three working days. So one round of feedback fits, and a second round only fits if the first is fast.
Check your own schedule with a simple calculation:
- List every step between kickoff and launch.
- Give each step a duration in working days.
- Add the approval waits you control.
- Compare the total with the days available.
The script below does step 4 for you. It counts working days between two dates, skipping weekends, and reports whether the plan fits.
from datetime import date, timedelta
def working_days(start: date, end: date) -> int:
"""Count weekdays from start up to, but not including, end."""
days = 0
current = start
while current < end:
if current.weekday() < 5:
days += 1
current += timedelta(days=1)
return days
kickoff = date(2026, 12, 1)
first_drafts = date(2026, 12, 12)
launch = date(2026, 12, 19)
# Steps after first drafts, in working days
feedback_round_1 = 3
revisions = 2
feedback_round_2 = 3
technical_setup_and_qa = 2
needed = (
feedback_round_1 + revisions + feedback_round_2 + technical_setup_and_qa
)
available = working_days(first_drafts, launch)
print(f"Working days from kickoff to first drafts: {working_days(kickoff, first_drafts)}")
print(f"Working days needed after drafts: {needed}")
print(f"Working days available after drafts: {available}")
print("Plan fits" if needed <= available else "Plan does not fit")Run it and you will see that 12 December 2026 is a Saturday. First drafts due on a weekend is a sign the dates were set without a calendar. Seven working days are not available, and the plan does not fit. Fixing this means moving drafts earlier, removing a feedback round, or moving launch.
Milestones: choose points that can be checked
A milestone is a dated point at which something specific is delivered or decided. A good milestone can be checked by looking at a thing, not by asking how someone feels about progress.
| Weak milestone | Stronger milestone |
|---|---|
| Creative underway | Three landing page wireframes shared for review |
| Tracking set up | Conversion events firing in a test, confirmed by screenshot |
| Ads ready | 12 ad groups uploaded in draft, not yet live |
| Final approval | Marketing lead signs off in writing |
Typical milestones for a digital campaign are:
- Kickoff held and open questions listed.
- Access and assets handed over by you.
- Tracking plan agreed, including the UTM convention.
- First drafts delivered.
- Feedback returned.
- Revised drafts delivered.
- Final approval given.
- Technical QA complete.
- Launch.
- First performance review.
Not every project needs all of these. A small freelance task might need only four. A multi-channel campaign may need more. Match the number of milestones to the risk: more checkpoints for new suppliers and large budgets, fewer for a trusted partner doing routine work.
Dependencies and who owns the wait
A dependency is a step that cannot start until another step finishes. The risky ones in marketing work are mostly on the client side:
- Brand assets, logos and product images.
- Access to analytics, ad accounts and the website content system.
- Legal or compliance review of claims.
- Sales sign-off on what counts as a qualified lead.
- Budget release.
Write these into the brief with a date and a name. For example: "Client provides logo files and analytics access by 3 December. Owner: marketing manager." If the client misses the date, the brief should say what happens. A common rule is that launch moves by the same number of days as the delay.
The diagram shows why a late asset handover matters: both branches must finish before drafts can begin, so the slower one sets the pace.
Build in buffer, and say where it is
Plans that have no spare time fail on the first delay. Add buffer, but place it deliberately:
- Put buffer before the fixed launch date, not after it.
- Keep it visible. Hidden buffer gets used up by early steps.
- Size it to the uncertainty. Work with new suppliers, new platforms or legal review needs more than repeat work.
A rough guide is 10 to 20 percent of the total schedule. If you are launching ads that need platform review, allow at least one extra working day, because ad platforms can take time to approve new ads and sometimes reject them.
Seasonality and calendar clashes
Check the dates against real calendars before you commit:
- Public holidays in your country and in the supplier's country. A supplier abroad may be away on days you are not.
- Peak trading periods, when media costs rise and approval queues get longer.
- Your own events, such as product launches, sales campaigns and reporting deadlines.
- Planned leave for the people who must approve work.
December in the sample brief is a good example. A launch on 19 December leaves little time before holidays, so the brief should say who can approve during that period and whether the campaign runs through the holiday week.
Phasing: launch, learn, optimize
Not all work ends at launch. Many digital campaigns need a learning phase in which the supplier watches results and changes targeting, ads or pages. Show this in the timeline as phases:
| Phase | Typical content | Typical end point |
|---|---|---|
| Setup | Tracking, accounts, creative, QA | Launch |
| Learning | Early data, fixes to errors, first tests | First performance review |
| Optimization | Budget shifts, test rollouts | Mid-point review |
| Wrap-up | Final report, handover, lessons | Campaign close |
For the sample objective of reaching 180 demo requests per month by 31 January, the timeline must leave enough time after launch to reach that rate. A 19 December launch gives about six weeks. Ask yourself whether six weeks, including the holidays, is realistic for the budget and channels. If not, move the target or the deadline, not the supplier's patience.
Common timeline mistakes
- Supplier-only dates. Listing only supplier deadlines hides your own. Add yours.
- No review time. A draft due on Friday and launch on Monday leaves no time for feedback.
- Weekend or holiday deadlines. Check each date against a calendar.
- One date for everything. "Delivered by 19 December" with no steps gives no early warning.
- No change process. Say how dates move: who can ask, who agrees, and whether fees change.
Writing the timeline into the brief
Use a short block with dates, owners and conditions. This sits inside the full brief template.
timeline:
kickoff: 2026-12-01
client_assets_and_access: 2026-12-03 # owner: marketing manager
tracking_plan_agreed: 2026-12-04 # owner: supplier, approved by client
first_drafts: 2026-12-11 # Friday, moved from 12 Dec (Saturday)
feedback_due: 2026-12-16 # 3 working days after drafts
final_drafts: 2026-12-17
final_approval: 2026-12-18
launch: 2026-12-19 # note: check weekday before confirming
first_review: 2027-01-08
rules:
- A late client handover moves launch by the same number of days
- Date changes are agreed in writing by both sidesNote that 19 December 2026 is also a Saturday. Many campaigns do launch at weekends, but if you did not intend this, move the date. Checking every date against a calendar is a small step that avoids a real delay.
Exercise
A brief sets kickoff on Monday 1 June, first drafts on Friday 5 June, launch on Friday 12 June, and says approvals take up to three working days. The supplier needs two working days for revisions and one for technical QA. Does one feedback round fit, and what would you change if you wanted two rounds?
Show answer
After drafts on Friday 5 June, the working days before launch on 12 June are 8, 9, 10, 11 (Monday to Thursday) if the launch day itself is not counted, so four days are available. One feedback round (3 days) plus revisions (2 days) plus QA (1 day) is 6 working days, so it does not fit even with one round. You would need to move launch later, move drafts earlier, shorten approval to one or two days, or cut scope. Two rounds need at least 3 + 2 + 3 + 1 = 9 working days, so launch would need to be roughly a week later, or approval time must be cut sharply.