This chapter assumes you know what makes a contract (offer, acceptance, consideration) and that you are comfortable with the terms party, obligation, and performance. It covers the definition of breach, the common ways a breach happens, and the mistakes learners make most often. It does not yet decide whether a breach is minor or material. Later chapters do that. This is general education, not legal advice, and rules vary by jurisdiction.
The working definition
A breach of contract is a failure, without legal excuse, to perform a contractual duty when performance is due. The Restatement (Second) of Contracts section 235(2) says it this way: when performance of a duty is due, any nonperformance is a breach.
That definition has four parts, and each one matters.
- A contractual duty exists. The duty must come from the agreement, from terms the law implies into it, or from a statute that governs it, such as the UCC for sales of goods.
- Performance is due. A party cannot breach a duty that has not yet matured. If your payment is due on the 30th, you have not breached on the 15th. One exception is anticipatory repudiation, covered in a later chapter.
- Nonperformance happens. The party does not perform, performs late, or performs defectively.
- No excuse applies. Defenses such as impossibility, a failed condition, or the other side's prior breach can mean the failure is not a breach at all.
Notice what the definition leaves out. Breach does not require bad intent, carelessness, or harm. A party who tries hard and fails has still breached. Contract liability is mostly strict: the promisor takes on the risk that performance will not happen.
Forms a breach can take
Breaches usually fall into a few patterns. A single set of facts can show more than one.
| Form | What it looks like | Example |
|---|---|---|
| Total nonperformance | The party does nothing it promised | A supplier never ships the goods |
| Late performance | The party performs after the due date | A contractor finishes six weeks late |
| Defective performance | The party performs, but not as promised | Paint of the wrong grade is used |
| Partial performance | The party does some of the work and stops | A builder finishes three of four floors |
| Repudiation | The party says, or shows by conduct, it will not perform | A seller announces it will sell to someone else |
| Interference | The party blocks the other side's ability to perform | A buyer denies the seller access to the site |
Late performance deserves a note. Unless the contract makes time essential, a short delay is often a breach but a small one. The delay still gives the other side a claim, but it may not let them walk away. Later chapters explain how courts draw that line.
Where the duty comes from
You find the duty by reading the contract, but the text is not the only source.
- Express terms are the promises the parties wrote or said.
- Implied terms fill gaps. Courts imply a duty to perform in a reasonably workmanlike manner for service contracts in many settings.
- The implied covenant of good faith and fair dealing exists in most US jurisdictions. It stops a party from destroying the other side's right to the benefit of the bargain, even while it follows the literal words.
- Statutory terms apply by law. The UCC adds warranties and gap-filling rules for sales of goods.
A party who follows the literal words but acts to deprive the other side of the deal's benefit can still breach through the good faith covenant. The covenant does not create new obligations that contradict the express terms. It protects the reasonable expectations the express terms create.
A sequence of events
The following diagram shows how a question of breach is usually reasoned through.
Only after the last step does the minor versus material question arise. Skipping the earlier steps is a common mistake, so work through them in order.
A worked example
Harlow Print Co. agrees to print 5,000 brochures for Dunmore Tours. The contract says delivery is due on March 1 and payment of $4,000 is due 30 days after delivery.
Consider four scenarios.
- Harlow delivers on March 10. The duty existed and was due on March 1. Performance came late. Unless an excuse applies, this is a breach. Whether it is minor depends on facts such as whether Dunmore needed the brochures for a March 5 trade show.
- Harlow delivers 4,800 brochures. This is partial or defective performance. It is a breach because the contract promised 5,000.
- Dunmore pays on day 25. This is not a breach. Early payment performs the duty in a way that does not harm Harlow, and the duty to pay is not violated by paying before the deadline unless the contract says otherwise.
- Dunmore refuses to pay after a proper delivery. This is a breach. The duty was due and no excuse exists.
In scenario 3, you can see the "duty is due" element at work. Whether early performance counts as proper depends on the contract. Payment of money early is usually accepted. Early delivery of goods may not be.
Excuses that mean no breach
A failure to perform is not a breach if the law excuses it. You should check for these before concluding a breach occurred.
- Failure of a condition. If a duty depends on an event that has not happened, the duty never became due. The next chapter covers conditions.
- Prior material breach by the other side. A party whose own performance is excused by the other side's serious breach may stop performing without being in breach.
- Impossibility, impracticability, or frustration of purpose. These doctrines can discharge a duty when an unforeseen event changes the deal.
- Waiver or modification. The other party may have agreed to accept different performance.
- Valid tender and refusal. If one party offers to perform and the other refuses to accept, the offering party has not breached.
Common errors
- Requiring harm. A breach exists even when no loss follows. The harm question affects remedies, not whether a breach occurred. A party with no provable loss may recover only nominal damages, a token amount.
- Requiring bad faith. Honest mistakes still breach. Intent matters for other doctrines, such as fraud and punitive claims, not for ordinary breach.
- Treating every breach as a reason to terminate. Every breach gives a claim for damages. Only some breaches also let the other side end the contract. That difference is the subject of the rest of the tutorial.
- Ignoring the contract's own terms. A clause may define what counts as default, set notice requirements, or limit remedies. Read it before you apply general rules.
- Skipping the due-date check. A party that is likely to fail later has not yet breached, except in the case of repudiation.
What breach leads to
Once you have found a breach, two questions follow. First, how serious is it? Second, what can the other party do? The answers are tied together. A breach that is serious enough lets the innocent party suspend its own performance and terminate. Any breach lets the innocent party claim damages. The next chapters on conditions, minor breach, and material breach build this out.
Exercise
A caterer agrees to serve dinner at a wedding at 6:00 p.m. on June 4. The caterer arrives at 6:20 p.m. because of a traffic jam, serves the full meal, and the guests are satisfied. Has the caterer breached the contract? Does the answer change if the couple lost no money?
Show answer
Yes, probably. The duty to serve at 6:00 p.m. existed and was due, the caterer performed late, and traffic is not a recognized legal excuse in this setting. Breach does not require intent or fault. The lack of loss does not change whether a breach occurred. It affects remedies, so the couple may recover only nominal damages. Whether the breach is minor or material is a separate question that later chapters address.
Exercise
A buyer agrees to pay $10,000 on May 1 for a used machine. On April 20, the buyer pays $10,000. Is this a breach? Name the element of the definition that decides it.
Show answer
No. Early payment of money does not usually violate the duty to pay, and the seller loses nothing by receiving it sooner. The element at issue is that nonperformance must occur when performance is due, and here the buyer performed the duty fully. The result could differ only if the contract barred early payment.