When RACI Is Not Enough: RASCI and DACI
Assume you already know the four RACI roles: Responsible, Accountable, Consulted, and Informed. RACI works well when you need to clarify ownership of tasks and deliverables. Some situations need a more specific model, though. RASCI adds a support role for hands-on assistance. DACI focuses on making a decision rather than completing a task.
Choosing the right model depends on what you are trying to clarify:
- Use RACI when you need ownership across project work.
- Use RASCI when support work is important and would otherwise be hidden.
- Use DACI when the main problem is slow or unclear decision-making.
RASCI: Adding a Support role
RASCI is a RACI matrix with one additional role:
- Responsible does the work.
- Accountable owns the result and accepts the outcome.
- Support helps the Responsible person complete the work.
- Consulted provides expertise or feedback before the work is completed.
- Informed receives updates or the final result.
The difference between Support and Consulted is practical. A Consulted person gives input. A Support person actively helps perform the work. For example, a security specialist who reviews a design is Consulted. A security specialist who configures scanners, writes test cases, and helps fix findings is Support.
RASCI is useful when a project has shared services or specialist teams. Examples include legal, security, data engineering, technical writing, and change management.
| Task | Product owner | Developer | Security specialist | Technical writer |
|---|---|---|---|---|
| Define feature scope | A | R | C | I |
| Build feature | A | R | S | I |
| Run security testing | A | R | S | I |
| Publish release notes | A | C | I | R |
The Support role should not become a general label for everyone who attends a meeting. Mark a person as Support only when they contribute effort to the task. If their contribution is advice, use Consulted instead.
DACI: Focusing on decisions
DACI is a decision-making model. Its roles are:
- Driver coordinates the decision process. The Driver gathers information, schedules discussions, records options, and moves the decision toward completion.
- Approver has the authority to make the final decision.
- Contributors provide analysis, recommendations, or specialist input.
- Informed people need to know the decision and its effect.
DACI answers a different question from RACI. RACI asks, “Who owns and performs this work?” DACI asks, “Who moves this decision forward, who decides, and who contributes information?”
A DACI entry might describe whether to build a feature, select a vendor, change a launch date, or adopt a technical design. The decision should be written as a clear question.
| Decision | Driver | Approver | Contributors | Informed |
|---|---|---|---|---|
| Which payment provider should we use? | Product manager | Sponsor | Finance, developer, legal | Support team |
| Should the release move to 15 June? | Project manager | Product owner | Developer, marketing, support | All stakeholders |
DACI usually has one Approver. Multiple Approvers can make a decision slow or impossible because the model does not identify whose disagreement controls the outcome. Contributors can disagree, but the Approver must still make the final call.
RACI, RASCI, and DACI compared
The models can look similar in a spreadsheet, but their purposes differ.
| Model | Main purpose | Special role | Best used for |
|---|---|---|---|
| RACI | Clarify work ownership | Accountable | Tasks, deliverables, and process steps |
| RASCI | Clarify work ownership and hands-on help | Support | Work involving specialist or shared-service teams |
| DACI | Clarify decision authority and decision flow | Driver and Approver | Choices that need a clear decision owner |
Do not replace every RACI matrix with DACI. A decision model does not show who builds, tests, documents, or operates the resulting solution. Do not add Support to every RACI matrix either. An extra role adds detail, but it also adds maintenance work and more opportunities for confusion.
Choosing and combining models
Start by naming the object you are mapping. If the object is “create test cases,” use RACI or RASCI. If the object is “choose the testing tool,” use DACI. A project may need both models because projects contain work and decisions.
Keep the models separate when they answer different questions. For example:
- A RASCI matrix can show that the developer is Responsible for implementing a payment feature and that security Supports the implementation.
- A DACI record can show that the product owner Approves the choice of payment provider.
- The two records can link to the same project milestone without forcing one matrix to describe everything.
You can also use a RACI matrix for routine work and create a small DACI table for major decisions. This keeps the main responsibility matrix readable.
Common mistakes with variants
A common mistake is using DACI for an entire project plan. DACI can identify who decides whether a release happens, but it does not identify who prepares the release, tests it, or supports users afterward.
Another mistake is marking an entire team as Support. A team name hides the person or subteam that must act. Use the smallest useful role or group, and make the expected support explicit.
A third mistake is giving the Driver authority that belongs to the Approver. The Driver organizes the process and prepares the recommendation. The Approver makes the final decision unless the project explicitly defines another rule.
A fourth mistake is creating a new model without explaining the transition. If a team changes from RACI to RASCI or DACI, explain the new letters, update the legend, and show one completed example. Otherwise, people may interpret the same letter differently.
A practical selection process
Use this process when deciding which model to apply:
- Write the item as either a task, deliverable, or decision.
- If it is a task or deliverable, start with RACI.
- Add Support only when someone will perform hands-on assistance that is different from the Responsible person’s work.
- If it is a decision, use DACI.
- Assign one Accountable person for each RACI or RASCI item.
- Assign one Approver for each DACI decision.
- Review the matrix with the people named in it.
- Record the decision or deliverable link so the matrix remains connected to project work.
Exercise
A project team must decide whether to delay a launch. The project manager will collect schedule data and organize the discussion. The product owner has final authority. Engineering and marketing will provide analysis, and customer support needs the result. Which DACI roles should they receive?
Show answer
The project manager is the Driver, the product owner is the Approver, engineering and marketing are Contributors, and customer support is Informed.
Exercise
A security engineer will configure automated scans during feature development, while another security reviewer will only comment on the design. Which RASCI roles fit these two people?
Show answer
The engineer configuring the scans is Support. The reviewer giving design feedback is Consulted.