Sub topic 3
Reading the Matrix: Tasks, Roles, and Cells
This chapter assumes you know basic project terms such as task, deliverable, stakeholder, and role. You should also be comfortable reading a simple table and have worked with at least one project team.
A RACI matrix is a table that connects project work to the people or roles involved. The rows describe work. The columns describe roles. Each cell shows how a role participates in a task.
Reading the table correctly helps you answer questions such as:
- Who does the work?
- Who owns the result?
- Whose advice is needed?
- Who only needs an update?
- Where is a responsibility missing or unclear?
The two directions of a RACI matrix
Read a RACI matrix in two directions.
Read across a row to understand one task. This shows everyone involved in that task and what each person must do.
Read down a column to understand one role. This shows all the tasks assigned to that role and can reveal an overloaded person.
A row usually represents a task, deliverable, decision, or milestone. A column usually represents a person, team, department, or project role.
For example, a row might be called “Write requirements.” This row describes one piece of project work. The columns might include Product owner, Business analyst, Developer, and Sponsor. The cells show each role’s relationship to writing the requirements.
What each cell means
A cell contains one or more RACI letters. Each letter describes a different type of participation.
| Letter | Name | Meaning when reading a cell |
|---|---|---|
| R | Responsible | This role performs the work or makes sure the work gets done. |
| A | Accountable | This role owns the result and approves that the task is complete. |
| C | Consulted | This role gives advice before or during the work. |
| I | Informed | This role receives updates but does not help make the task happen. |
The letters describe roles, not necessarily job titles. For example, “Developer” can be a column even when several developers share the work. In that case, the team must still decide who specifically acts as Responsible or Accountable.
Responsible and Accountable are different
Responsible and Accountable are often confused.
The Responsible role performs the work. This person may draft a document, configure a system, run a test, or coordinate an activity.
The Accountable role owns the outcome. This person makes the final decision, accepts the result, and answers for the task if it fails. The Accountable person may also perform the work, but ownership remains a separate idea.
A task can have several Responsible roles when several people actively contribute. It should normally have exactly one Accountable role. One owner prevents competing decisions and makes escalation clear.
Some teams use A/R in one cell. This means the same role owns the result and performs the work. For example:
| Task | Product owner | Business analyst | Developer | Sponsor |
|---|---|---|---|---|
| Write requirements | A | R | C | I |
| Build feature | C | C | A/R | I |
| Approve release | R | I | C | A |
In the “Build feature” row, the Developer both performs the work and owns its completion. In the “Write requirements” row, the Business analyst does the work, while the Product owner accepts the result.
How to inspect a task row
Use this sequence when reading one row:
- Identify the task or deliverable named at the left.
- Find the Accountable cell. This is the owner of the outcome.
- Find every Responsible cell. These roles carry out the work.
- Find Consulted cells. These roles should provide input before important decisions.
- Find Informed cells. These roles need communication but should not be pulled into the work unnecessarily.
- Check whether the pattern makes sense for the task.
Suppose a row for “Approve release” marks the Sponsor as Accountable, the Product owner as Responsible, the Developer as Consulted, and the Business analyst as Informed. The row says that the Product owner prepares or coordinates the approval, the Sponsor makes the final decision, and the other roles support communication or advice.
The matrix does not replace the task plan. It does not state the deadline, acceptance criteria, or detailed steps. It states who participates and how.
How to inspect a role column
A column gives you a role-centered view of the project. Scan downward and list the letters assigned to that role.
This view helps answer different questions:
- Is one person Responsible for too many tasks at the same time?
- Is a stakeholder marked Consulted on nearly every row?
- Is a sponsor Informed about routine details that do not require attention?
- Is a role missing from important work?
- Does someone have Accountable ownership without enough authority or capacity?
A column with many C entries may indicate that the project is asking for too much review. A column with many I entries may indicate that communication is broad but not focused. Neither pattern is automatically wrong. The team should check whether the participation is useful.
How to interpret blank cells
A blank cell means the role has no defined participation in that task. This is different from I.
Use I when the role must receive information. Leave the cell blank when the role does not need to be involved or updated.
Filling every cell with a letter makes a matrix look complete, but it reduces its value. A useful matrix shows meaningful differences between roles. If everyone is Consulted or Informed for every task, the matrix does not help the team decide whom to contact.
Reading boundaries and ambiguity
Before using a matrix, check its boundaries. A row named “Testing” may refer to planning tests, executing tests, reviewing results, or approving quality. These may need separate rows if different people own them.
Likewise, “Project team” is often too broad as a column. A specific role or named group makes communication clearer. Use the smallest useful unit without creating unnecessary detail.
When a cell contains multiple codes, read each code separately. A/R means ownership and execution are combined. C/I means the role should be consulted and kept informed, though the team should confirm that both forms of participation are necessary.
Exercise
In a row called “Prepare deployment plan,” the Developer is marked R, the Product owner is marked A, the Operations team is marked C, and the Sponsor is marked I. Who performs the work, who owns the result, and who gives advice?
Show answer
The Developer performs the work, the Product owner owns the result, and the Operations team gives advice. The Sponsor receives updates.