Time to market and the cost of delay
This chapter assumes you know what net present value (NPV) is and can read a short Python script. It also assumes you have estimated the cost of building a capability, which the previous chapter covered. Here you add the second half of the build side: how long building takes, and what each month of waiting costs.
Why time belongs in the comparison
A build estimate that lists only engineering salaries and tooling leaves out the largest cost. While the team builds, the company earns nothing from the capability, competitors may take customers, and the market itself may change shape. Buying is often expensive, but it can shorten the wait from years to months. Whether that shortcut is worth the price depends on the cost of delay.
The cost of delay is the value lost for each unit of time that a capability reaches the market later than it could have. It is usually expressed per month or per quarter, so you can set it against the premium you would pay to move faster.
Where a delay costs money
Delay damages value in four ways. Estimate each separately, because they behave differently.
- Deferred revenue. Every benefit shifts later, so each dollar is discounted more heavily. This effect exists even in a market with no competitors.
- Lost window. Many markets have a fixed period in which entry pays off, such as a regulatory deadline, a platform transition, or a buying season. A launch after the window closes earns far less than a late launch inside it.
- Lost position. Early entrants sign customers, collect data, and set standards. A late entrant must win customers away from them, which costs more than winning them first.
- Carrying cost. The team keeps being paid while it builds, and the people working on the build are not working on something else. The previous chapter's build cost covers the salaries. The cost of those people's other uses is an opportunity cost, and it also belongs here.
Estimating the build timeline
An honest build timeline has a range, not a single date. Three habits help.
- Use reference classes. Look at how long comparable internal projects took, not how long the team says this one will take. Projects that need new skills, new infrastructure, or approval from several groups tend to run late.
- Count the time before the build. Hiring, procurement, and security review can add months before the first line of code.
- Count the time after the build. A finished product still needs customer pilots, certification, and sales training before it earns revenue. Measure time to market as the date the first revenue arrives, not the date engineering finishes.
Buying has its own timeline, and it is not zero. Signing, regulatory clearance, and integration all take time. A deal that closes in six months may still need another year before the acquired product is sold through your channels. Compare both options on the same measure: months until the benefits start.
Putting a number on the delay
The simplest model holds the annual benefit constant and shifts its start date. A fixed horizon represents the closing window: whatever you launch late loses the years at the end that no longer exist.
def npv(cash_flows, rate):
"""Net present value; the list index is the year, year 0 is undiscounted."""
return sum(cf / (1 + rate) ** year for year, cf in enumerate(cash_flows))
def benefit_stream(start_year, annual_benefit, horizon):
"""Constant benefit from start_year through horizon (the window closes there)."""
return [annual_benefit if year >= start_year else 0
for year in range(horizon + 1)]
rate = 0.10
horizon = 8 # the market window closes after year 8
annual_benefit = 3 # $M per year once the capability is live
for start in range(1, 7):
value = npv(benefit_stream(start, annual_benefit, horizon), rate)
print(f"Launch in year {start}: benefit NPV {value:.2f}")
build_start, buy_start = 4, 2
gap = (npv(benefit_stream(buy_start, annual_benefit, horizon), rate)
- npv(benefit_stream(build_start, annual_benefit, horizon), rate))
print(f"Value of launching in year {buy_start} instead of {build_start}: {gap:.2f}")
print(f"Per month of delay: {gap / ((build_start - buy_start) * 12):.3f}")With these inputs, a year-4 launch is worth about 8.54 and a year-2 launch about 13.28, so the two years of delay cost about 4.73 in present value. That is roughly 0.20 per month. The figure is the most you should pay, beyond the build's own cost, for the speed that buying gives. If the acquisition premium exceeds it, speed alone does not justify the deal, and you need another reason such as talent or market access.
Notice that the loss grows as the window shrinks. Moving from year 5 to year 6 costs less than moving from year 2 to year 3, because later launches already earn little. This is why delay matters most in short windows.
Delay is not symmetric: schedules slip, they do not speed up
A plan that says "three years" is a target, not an average. Builds finish early rarely and late often, and a late launch costs more than an early launch gains, because the closing window cuts off benefits at the end. So the expected value of an uncertain schedule is lower than the value of the planned one.
def npv(cash_flows, rate):
return sum(cf / (1 + rate) ** year for year, cf in enumerate(cash_flows))
def benefit_stream(start_year, annual_benefit, horizon):
return [annual_benefit if year >= start_year else 0
for year in range(horizon + 1)]
rate, horizon, annual_benefit = 0.10, 8, 3
# Launch year for the build, with a subjective probability for each outcome
scenarios = [(3, 0.3), (4, 0.4), (6, 0.3)]
planned = npv(benefit_stream(4, annual_benefit, horizon), rate)
expected = sum(p * npv(benefit_stream(year, annual_benefit, horizon), rate)
for year, p in scenarios)
print(f"Planned (launch in year 4): {planned:.2f}")
print(f"Expected over scenarios: {expected:.2f}")
print(f"Cost of schedule risk: {planned - expected:.2f}")The expected value is about 8.05 against 8.54 for the plan, a gap of about 0.50. The scenarios here are an illustration. Build your own from the reference class of similar projects, and keep the probabilities honest, since a 30% chance of a two-year slip changes the answer noticeably.
Different products lose value at different speeds
The constant-benefit model is a start. The shape of the loss differs by market, and it changes how much speed is worth.
| Pattern | What happens as launch slips | Example | Effect on build versus buy |
|---|---|---|---|
| Gradual | Revenue shifts later, and the loss is steady | Internal tooling that cuts costs | Delay cost is small, so building is usually affordable |
| Eroding | Share falls each quarter a rival is ahead | A feature customers compare in sales demos | Delay cost grows over time, so speed has real value |
| Cliff | Value drops sharply at a date | A regulatory deadline or a platform shutdown | Missing the date can make building worthless |
| Winner-take-most | The first scaled player captures most of the market | Network-driven marketplaces | Delay cost can exceed the whole acquisition premium |
State which pattern applies before you choose a number. If you cannot name one, the cost of delay is probably small, and you should be skeptical of any argument that rests on urgency alone.
Common errors
- Treating urgency as proof. "We have to move fast" is a claim to test. Compute the cost of delay and compare it with the premium. Urgency often feels larger than it measures.
- Comparing signing dates to launch dates. The buy option starts the clock at signing, but its benefits start at integration. Use the same endpoint, first revenue, for both.
- Ignoring that buying can also be late. Antitrust review, a failed integration, or the departure of key staff can push the buy timeline out. The next chapters price this in as risk.
- Using one discount rate everywhere. A speculative launch deserves a higher rate than a certain cost saving. Section by section, the later risk-adjustment chapter handles this properly.
- Double counting. If you reduce the revenue forecast for lost share and also add a separate "competitive loss" line, you charge for the same damage twice.
What to carry forward
Time to market turns "buying is faster" from a feeling into a figure. You now have a cost of delay per month, a schedule range for the build, and a view of how the loss behaves in your market. The next chapter prices the other side: what you actually pay to buy.
Exercise
A build will launch in year 5 and a purchase will launch in year 2. The annual benefit is $4M, the discount rate is 10%, and the window closes after year 8. Write the Python call you would use to find the value of the speed advantage, and say what the result means for a $9M acquisition premium over the cost of building.
Show answer
Use the helpers from this chapter: gap = npv(benefitstream(2, 4, 8), 0.10) - npv(benefitstream(5, 4, 8), 0.10). The discount factors for years 2 to 4 sum to 0.8264 + 0.7513 + 0.6830 = 2.2607, and the years 5 to 8 appear in both streams. The difference is the benefit in years 2, 3, and 4 only, so gap = 4 * 2.2607, about 9.04. The speed advantage is worth about $9.0M, which just covers a $9M premium. Speed alone breaks even, so the deal needs a second reason, such as talent or market access, or a lower price. Because the margin is so thin, test it with a cost of delay set to half, which would make the premium unjustified on speed alone.