Adjusting for Execution and Integration Risk
This chapter assumes you can compute a net present value (NPV) from a list of yearly cash flows, as in the previous chapter. It also assumes you know what a discount rate does. You should be comfortable reading short Python scripts.
Why one NPV number is not enough
A discounted cash flow comparison gives each option a single NPV. That number is only as honest as the cash flows behind it. Those cash flows usually come from a plan, and plans describe what happens when everything goes right.
Both routes can miss their plan:
- A build can run over budget, ship late, or ship something customers do not want.
- An acquisition can close at the agreed price and still fail to deliver. Customers may leave, key engineers may quit, or systems may not connect.
Risk adjustment replaces the plan-case cash flows with expected cash flows. An expected cash flow weights each outcome by how likely it is. You then compare the two options on that basis.
Two kinds of risk
| Row | Execution risk (mostly build) | Integration risk (mostly buy) |
|---|---|---|
| Typical failure | Cost overrun, schedule slip, weak product | Customer churn, talent loss, systems that do not fit together |
| When the money goes out | Gradually, as the project runs | Mostly up front, at closing |
| Can you stop early? | Often yes, by cancelling the project | Rarely. The price is already paid |
| Main effect on the NPV | Costs rise and benefits start later | Costs stay fixed and benefits shrink or never arrive |
The last two rows explain why the two routes need different treatment. A build's spending can be stopped if early results look bad, so part of the downside is capped. An acquisition's price is a sunk cost from day one. Integration risk therefore falls almost entirely on the benefits side.
Certain costs, uncertain benefits (buy)
The simplest adjustment for a purchase splits the cash flows in two. The price and integration spend are paid whatever happens. The benefits arrive only if integration works.
def npv(cash_flows, rate):
return sum(cf / (1 + rate) ** year for year, cf in enumerate(cash_flows))
def risk_adjusted_npv(costs, benefits, rate, p_success):
"""Costs are always paid; benefits arrive only with probability p_success."""
return npv(costs, rate) + p_success * npv(benefits, rate)
rate = 0.10
# Buy option, split into spend and benefits (both $M per year)
buy_costs = [-10, -1, 0, 0, 0, 0, 0]
buy_benefits = [0, 0, 3, 3, 3, 3, 3]
for p in (1.0, 0.7, 0.5):
value = risk_adjusted_npv(buy_costs, buy_benefits, rate, p)
print(f"P(integration succeeds) = {p:.1f} -> NPV {value:.2f}")The present value of the costs is -10.91 and the present value of the benefits is 10.34. The results are:
| P(integration succeeds) | Buy NPV ($M) |
|---|---|
| 1.0 | -0.57 |
| 0.7 | -3.67 |
| 0.5 | -5.74 |
Each 10-point drop in the success probability removes about $1M of value. The cost side never moves. In this example the deal is already slightly negative at certainty, so risk only widens the gap.
Scenarios for the build side
For a build, the usual risks are overruns and delays. Model them as scenarios, each with a probability, a cost multiplier, and a number of years the benefits slip.
def npv(cash_flows, rate):
return sum(cf / (1 + rate) ** year for year, cf in enumerate(cash_flows))
rate = 0.10
build_costs = [-2, -2, -1, 0, 0, 0, 0]
build_benefits = [0, 0, 0, 0, 3, 3, 3]
def build_scenario(overrun, delay_years):
"""Scale the spend, and push the benefits back by inserting empty years."""
costs = [c * overrun for c in build_costs]
benefits = [0] * delay_years + build_benefits
return npv(costs, rate) + npv(benefits, rate)
scenarios = [
("On plan", 0.60, 1.0, 0),
("Cost overrun of 50%", 0.25, 1.5, 0),
("Overrun and 1-year slip", 0.15, 1.5, 1),
]
expected = 0.0
for name, prob, overrun, delay in scenarios:
value = build_scenario(overrun, delay)
expected += prob * value
print(f"{name:<26} p={prob:.2f} NPV {value:6.2f}")
print(f"Expected build NPV: {expected:.2f}")| Scenario | Probability | NPV ($M) |
|---|---|---|
| On plan | 0.60 | 0.96 |
| Cost overrun of 50% | 0.25 | -1.36 |
| Overrun and 1-year slip | 0.15 | -1.87 |
| Expected | -0.04 |
The plan-case build NPV of +0.96 shrinks to about zero once overruns and delays are weighted in. The buy case at 70% success is -3.67. After adjustment the build still comes out ahead, but the margin has grown from about $1.5M to $3.6M. The ranking did not change here. It can change, and that is the reason to run the adjustment.
Where the probabilities come from
The arithmetic is easy. The hard part is choosing the inputs. These sources are in rough order of reliability:
- Your own history. Check how past projects and past acquisitions compared with their plans. A company that has overrun its last five builds by 40% should not assume 0% this time.
- Reference classes. Look at outcomes for similar projects or deals in the same industry, and start from that base rate before adjusting for specifics.
- Structured judgment. Ask several people independently for a range (low, likely, high) and compare their answers. Large disagreement is useful information.
Do not rely on one point estimate. Run the calculation across a range, such as 40% to 90% for integration success, and see where the decision flips. If the answer holds across the plausible range, the decision is robust. If it flips at 65% and your best guess is 65%, you have learned that the decision is a close call.
Common errors
- Double counting risk. Some teams raise the discount rate to "account for risk" and then also apply probability haircuts. This counts the same risk twice and penalizes both options unevenly. Pick one method for a given risk and apply it to both options.
- Haircutting only one side. Applying scenarios to the acquisition but treating the build plan as certain biases the result toward building. The reverse mistake is equally common.
- Ignoring the cost of failure. A failed integration often has extra costs: severance, rehiring, write-offs, or management time. These belong in the downside scenarios, not just the missing benefits.
- Treating risks as independent. Talent loss and customer churn tend to occur together, because customers often follow the people they know. Model them as one scenario, not two separate coin flips.
- Forgetting the option to stop. A staged build can be cancelled after phase one. Spending that stops in the bad scenarios is worth modeling, because it raises the build's expected value.
Reducing risk instead of only measuring it
Once you can see how much risk costs, you can price ways to reduce it:
- Earn-outs. Part of the price is paid only if agreed targets are met. This shifts some integration risk back to the seller. It converts a fixed cost into a contingent one.
- Retention packages. These cost money up front, but they raise the probability that key people stay. You can test whether the success probability gain is worth the spend.
- Staged commitments. A partnership or minority stake can come first, followed by full acquisition if it works. A later chapter covers these in detail.
Each of these is testable with the functions above. Change the costs or the probability, and check whether the expected NPV improves by more than the measure costs.
Exercise
In the buy model, why is the success probability applied only to the benefits and not to the purchase price?
Show answer
The price and integration spend are paid at or soon after closing whether or not the integration works, so they are certain. Only the benefits depend on the integration succeeding. Multiplying the costs by the probability would understate the downside.
Exercise
Suppose the buy option's benefits were $4M per year in years 2 to 6 instead of $3M, with the same costs and a 10% discount rate. Roughly what integration success probability makes the expected NPV equal zero? (Hint: the present value of the original $3M benefits is 10.34, and the present value of the costs is -10.91.)
Show answer
The benefits scale by 4/3, so their present value is about 10.34 x 4/3 = 13.78. Setting -10.91 + p x 13.78 = 0 gives p of about 0.79. The deal needs roughly a 79% chance of successful integration just to break even.