Sub topic 7
Writing action items that can be done
This chapter assumes you have attended or run team meetings and can write short, clear sentences. It also assumes you already separate decisions from discussion in your notes. Here you will learn how to write the action items that follow from those decisions.
What an action item is
An action item is a task that someone agreed to do after the meeting. It is different from a decision. A decision says what the group chose. An action item says what one person will now do about it.
A good action item can be done and checked. Someone reading it a week later should know what to do, and whether it is finished.
Start with a verb
Begin each action item with a verb that names a visible result. Verbs like "send", "update", "draft", and "book" describe work you can see. Verbs like "look into", "think about", and "handle" do not. They hide the real task.
| Vague | Doable |
|---|---|
| Look into the vendor list | Send the vendor contract list to Finance |
| Handle the calendar | Update the recurring calendar invitation to Wednesday |
| Think about the budget | Draft two budget options and share them with the team |
If you cannot find a concrete verb, the group may not yet know what the task is. In that case, make the first action small, such as "Draft a proposal". You can add more actions later.
Name the owner and the due date
Every action item needs two more parts: one owner and a due date. The full pattern is:
- [ ] <verb + task> (Owner: <name>, Due: <YYYY-MM-DD>)Use one name as owner. If you write "Priya and Marcus", each may assume the other will do it. When two people work on a task, pick one to be responsible and mention the helper in the task text.
Write the due date as a calendar date in YYYY-MM-DD form. Words like "soon" or "next week" mean different things to different readers, and they change meaning as time passes.
Ask for the owner and the date in the meeting, before people leave. An owner who volunteers is more likely to finish the task than one who is assigned later in an email.
Before and after
The example below shows a weak note turned into a decision and an action item.
Weak: - Talked about the budget. John will look into it.
Strong: - D2: We will freeze new vendor contracts until the Q1 budget is approved.
- [ ] Send the vendor contract list to Finance (Owner: John, Due: 2026-12-04)The weak version hides the decision. It also gives John no clear task and no deadline. The strong version records the decision as its own statement and gives John one task that he can finish and others can check.
A filled-in section
Here is how the section looks in a finished set of notes:
## Action items
- [ ] Update the recurring calendar invitation to Wednesday (Owner: Priya, Due: 2026-12-02)
- [ ] Tell the support team about the new meeting day (Owner: Marcus, Due: 2026-12-03)Each line has a verb, one owner, and a date. Each can be tied back to a decision in the notes above it.
Common errors
- No owner. "We should update the invitation" becomes nobody's job.
- Several owners. Responsibility is shared, so no one feels it.
- A task that is really a topic. "Budget" is a subject, not an action.
- A task that is too big. "Redesign onboarding" cannot be done by one date. Split it into steps, such as "Draft the new onboarding checklist".
- A missing date. Without one, the task has no point at which anyone checks it.
How action items connect to the rest of the notes
Action items come after decisions in the notes because most of them carry out a decision. The dates you write here are also what you will use later to follow up. A task with no date cannot be followed up.
Exercises
Exercise
Rewrite this action item so it can be done: "Marketing and Sam to look into the launch page." Assume Sam will own it, the task is to draft new headline text, and the date is 2026-12-10.
Show answer
- [ ] Draft new headline text for the launch page (Owner: Sam, Due: 2026-12-10)
Exercise
A note says "- [ ] Redesign the onboarding process (Owner: Dana)". Name two problems and suggest one fix.
Show answer
The task is too big to finish as one item, and it has no due date. Fix it by splitting it into a smaller step with a date, for example: "- [ ] Draft the new onboarding checklist (Owner: Dana, Due: 2026-12-11)".