Sub topic 8
The Parts of a Status Update
This chapter assumes you can write clear workplace English, send email or team chat messages, and know what a project or work stream is. It covers the working model of a status update: the parts, what each one does, and the errors that make updates hard to use. Later chapters cover the rating, risks and asks in more depth. Here you learn how the pieces fit together.
What a status update is for
A status update answers one question for a reader who is not doing the work: "Do I need to do anything?" Most readers spend under a minute on it. If they can find the state of the project, the evidence for it, and any request aimed at them within that minute, the update has worked.
A status update is not a diary of your week, and it is not a place to prove you were busy. It reports outcomes, what is coming, and what could go wrong. It also says what you need from the reader.
The five parts
A reliable status update has five parts, in a fixed order.
| Part | Question it answers | Typical length |
|---|---|---|
| Summary | What is the overall state, and what is the one thing to know? | 1 to 2 sentences |
| Done | What changed since the last update? | 2 to 5 bullets |
| Next | What will change before the next update? | 2 to 5 bullets |
| Risks and blockers | What could stop or delay the work, and when? | 0 to 3 bullets |
| Ask | What do you need, from whom, by when? | 1 sentence per ask |
The status rating (on track, at risk, off track) usually goes in the subject line and is explained in the summary. It is covered in its own chapter.
Summary
The summary is the only part some readers will read, so write it last and make it complete on its own. It states the overall state and the main thing the reader should know. Include the date that matters.
Summary: On track for the Dec 15 launch except for payment testing, which is two days behind.This works because it contains the state ("on track"), the exception ("payment testing"), and the size of the problem ("two days"). A summary such as "Good progress this week, some items to discuss" contains none of these.
Done
"Done" lists outcomes, not activities. An outcome is something that now exists or now works. An activity is something you spent time on. Readers cannot judge activities, because they do not know how much progress "worked on the address form" represents.
Done this week:
- Shipped the new address form to staging
- Fixed 14 of 18 open accessibility bugsEach bullet names a result and, where possible, a number. "Fixed 14 of 18" tells the reader the remaining count without a follow-up question. Report only what changed since the last update. Repeating older items makes the list longer and hides what is new.
Next
"Next" lists the outcomes you plan to deliver before the next update. It sets expectations, so the reader can compare it with the next "Done" list. Name the outcome and, if it matters, the date.
Next week:
- Finish payment provider testing
- Start load testingKeep this list to commitments you expect to keep. If an item depends on something outside your control, put the dependency under risks and keep the item here.
Risks and blockers
A blocker is something that is already stopping work. A risk is something that might stop or delay work later. Both belong in this section, and each entry needs three facts: the issue, the impact, and the date it matters.
Risks and blockers:
- Payment sandbox has been down since Tuesday. Launch slips about 2 days if it is not restored by Dec 2.Compare this with "Payment sandbox issues may cause delays." The weak version leaves the reader asking what is broken, how long, and by when it must be fixed. The strong version answers all three in two sentences.
If there are no risks, write "None." An empty section looks like an omission. A visible "None" tells the reader you checked.
Ask
The ask is the sentence that turns a report into action. State who you want, what you want them to do, and by when.
Ask: Can someone from Platform contact the payment provider by Monday?If you have no ask, write "Ask: None." This tells the reader they can stop reading without acting. If you have more than one ask, number them, and keep them to the few that matter.
How the parts connect
The parts are not independent lists. Each one feeds the next.
The summary comes first for the reader but is written last, because it depends on everything below it. A risk with a near date changes the summary and often creates an ask. If you find a risk that has no ask, check whether you need help. If you find an ask that matches no risk, check whether the reader will understand why you are asking.
A worked example
Here is a draft that many people would send.
Subject: Update
Hi all,
This week was busy. I worked on the migration and had several meetings with the data team. Things are going well overall, though there are a few concerns about timing. Let me know if you have any questions.
ThanksThe reader cannot tell the state, the progress, the problem, or what to do. Here is the same information in the five-part layout.
Subject: Data migration: weekly status, Nov 27 (At risk)
Summary: 40 of 52 services are migrated. The last 12 are scheduled for Dec 4, but that date depends on a schema review that has not been booked.
Done this week:
- Migrated 9 services, bringing the total to 40 of 52
- Finished rollback testing for the billing database
Next week:
- Migrate the 12 remaining services
- Run a full reconciliation of record counts
Risks and blockers:
- The schema review has no date. The Dec 4 cutover slips one week for each week the review is late.
Ask: Can Priya book the schema review for before Dec 2?The second version is longer, but the reader finishes it faster, because every line answers a question they would otherwise have to send.
Common errors
- Listing activities as progress. "Met with vendor" and "worked on tests" describe effort. Replace each with the result: "Vendor confirmed Dec 2 delivery" or "Passed 212 of 230 tests."
- Burying the problem. A risk placed in the sixth paragraph is often missed. Put the state and the key risk in the summary as well.
- Repeating old items. If an item appeared last week and nothing changed, drop it or move it to the risks section with a reason.
- Writing a risk without a date. "May cause delays" gives the reader no way to rank it. Add the date after which the impact begins.
- Hiding the ask in prose. A request inside a long paragraph is easy to miss. Give it its own labeled line.
- Changing the layout each week. Readers learn where to look. If the order moves, they have to hunt again.
- Padding with "None" sections that are not true. Write "None" only after you have checked.
Edge cases
A quiet week. If little changed, say so in the summary: "No change since last update. Waiting on vendor response due Dec 1." Keep the layout, and keep "Done" short. Do not invent items to fill the space.
Bad news with no fix yet. Report the problem and impact now, and state when you will know more: "Root cause unknown. I will update by Tuesday noon." The reader can plan around a known gap, but not around silence.
Several audiences. A team and an executive may need different detail. Write one update with a short summary on top, and let the executive stop there. Avoid maintaining two parallel versions that drift apart.
Very long projects. If "Done" grows past about five bullets, group by milestone or drop the minor items. Link to a tracker for detail instead of copying it.
A reusable template
Subject: [Project name]: weekly status, [date] ([On track | At risk | Off track])
Summary: [One or two sentences: overall state and the main thing the reader should know.]
Done:
- [Outcome with a number or date]
Next:
- [Planned outcome and when]
Risks and blockers:
- [Issue, impact, date it matters]
Ask: [Who, what, by when. Write "None" if there is no ask.]Copy this into your drafts folder and fill it in each cycle. Using the same template also supports the consistency covered in a later chapter.
Practice
Exercise
Rewrite this "Done" bullet as an outcome with a number: "Worked on the test suite and had a sync with QA."
Show answer
Any version that reports a result works, for example: "Raised automated test coverage from 61% to 74% and agreed the release test plan with QA." The key changes are replacing the activities (worked on, had a sync) with results, and adding figures the reader can compare with the last update.
Exercise
This risk entry is weak: "There might be some delay because of the vendor." Rewrite it using the three facts a risk needs, and add the matching ask. Invent plausible details.
Show answer
Example: "Risks and blockers: The vendor has not delivered the API keys that were due Nov 24. Integration testing cannot start until they arrive, and launch slips about 3 days for each day of delay after Dec 1. Ask: Can Marcus escalate to the vendor's account manager by Monday?" A correct answer names the issue (keys not delivered), the impact (testing blocked, launch slips), the date it matters (Dec 1), and an ask with who, what and by when.