Identify Who Needs to Hear From You
Assume you know basic project terms such as scope, milestones, and deliverables. You should also be familiar with workplace tools such as email, chat, and meetings.
A communication plan begins with people, not tools. Before choosing a meeting schedule or writing a status report, identify everyone who can affect the project, is affected by it, or needs information to make a decision.
A stakeholder is a person or group with an interest in the project or the ability to influence its outcome. Stakeholders can work inside or outside your organization. They may include:
- The executive sponsor who provides funding and removes barriers
- Customers who define whether the result is useful
- Team members who create the deliverables
- Managers who provide staff or approve changes
- Suppliers who provide products or services
- Compliance, security, or legal specialists
- Users who will work with the final product
Start with the project context
Review the project charter, scope statement, milestone plan, and risk list. These documents reveal who needs to be involved.
Ask:
- Who approved the project?
- Who owns the business problem?
- Who supplies people, money, data, or systems?
- Who approves scope, schedule, or budget changes?
- Who will use or support the deliverable?
- Who could block progress if they are ignored?
- Who has specialist knowledge needed for a decision?
Do not rely on the project team’s first list. Ask each team member, sponsor, and customer representative, “Who else should know about this project?” This question often reveals operational teams, external partners, or decision-makers who were missed.
Analyze influence and interest
After listing stakeholders, assess two factors:
- Influence is the stakeholder’s ability to change the project’s direction, resources, or outcome.
- Interest is how closely the stakeholder follows the project or how strongly the result affects them.
This analysis helps you choose an appropriate communication approach. It does not rank people by importance or determine whose opinion matters more.
A sponsor with high influence and high interest usually needs concise, regular updates and early notice of decisions. A department affected by the rollout may have low influence but high interest, so it may need clear progress information and opportunities to ask questions. A senior leader with high influence but low interest may need only milestone summaries and alerts about major risks.
Treat this classification as a working view. A stakeholder’s influence or interest can change when the project enters a new phase.
Record the analysis
Use a stakeholder register, which is a maintained list of stakeholders and the communication choices associated with them. Record facts that help the team act:
stakeholder: Executive sponsor
interest: high
influence: high
strategy: manage closely
information_needs:
- schedule and budget status
- top three risks
- decisions awaiting approval
channel: email report
frequency: biweekly
owner: project managerAt this stage, focus on identifying the audience and understanding its position. Detailed messages, channels, and frequencies can be refined later. However, recording early assumptions prevents the team from treating communication as someone else’s responsibility.
Common errors
- Listing only the project team: Include people who approve, fund, use, support, regulate, or can delay the work.
- Confusing job titles with stakeholders: A department may contain several audiences with different needs.
- Assuming influence never changes: A user representative may become highly influential during acceptance testing.
- Using one communication style for everyone: Executives, specialists, and end users need different levels of detail.
- Ignoring informal influence: A person without formal authority may shape adoption or team decisions.
- Failing to name an owner: Every important stakeholder relationship should have a person responsible for maintaining it.
Worked example
A team is replacing an internal expense system. Its initial list includes the sponsor, project manager, developers, and finance lead. Further questioning adds employees who submit expenses, payroll staff, the security team, the help desk, and the software supplier.
The security team has high influence and high interest during design and testing. Employees have low influence but high interest because the change affects their daily work. The supplier has medium influence and high interest because it must resolve technical issues. These differences should shape the later communication matrix.
Exercise
A department will use the new system but has no authority to approve scope or budget. How should you initially classify it, and what should you do next?
Show answer
Class it as low influence and high interest. Keep it informed, confirm what information its users need, and review the classification if its representatives gain decision-making authority.